FDOT contract T7614 bid tabulation
SR 45 (US41) FROM WASHINGTON LN TO S OF COUNTY LINE RD. Let by Florida DOT on August 26, 2026, Pasco, District 7. 6 bids received; low bid $5,519,971 by Pigott Asphalt and Sitework LLC.
- Owner
- Florida DOT
- Letting
- 26 AUG 2026
- Pay items
- 85
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pigott Asphalt and Sitework LLC | $5,519,971 | Low |
| 2 | Superior Asphalt, Inc. | $5,576,001 | +1.0% |
| 3 | Hubbard Construction Company | $5,626,218 | +2.0% |
| 4 | C.W. Roberts Contracting, Inc. | $5,678,952 | +3.0% |
| 5 | Ajax Paving Industries of Florida LLC | $5,897,601 | +7.0% |
| 6 | Preferred Materials Inc. | $7,146,825 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pigott Asphalt and Sitework LLC | 2. Superior Asphalt, Inc. | 3. Hubbard Construction Company | 4. C.W. Roberts Contracting, Inc. | 5. Ajax Paving Industries of Florida LLC | 6. Preferred Materials Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $175,000 | $145,418 | $130,675 | $394,978 | $259,000 | $246,300 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $150,000 | $169,108 | $249,634 | $154,593 | $610,000 | $441,550 |
| 0015 | Pedestrian escort/flagger (0102-5) | HR | 4,800 | $0.05 | $4.00 | $38.68 | $0.20 | $1.00 | $1.36 |
| 0020 | Traffic control officer (0102-14) | HR | 56 | $250.00 | $130.00 | $87.54 | $90.00 | $110.62 | $93.60 |
| 0025 | Work zone sign (0102-60) | ED | 29,600 | $0.10 | $0.27 | $0.25 | $0.27 | $0.20 | $0.25 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 44,000 | $0.01 | $0.12 | $0.11 | $0.12 | $0.04 | $0.14 |
| 0035 | Temporary raised/retroreflective pavement marker, type B (0102-78-2) | EACH | 5,818 | $3.60 | $3.89 | $4.44 | $4.50 | $4.21 | $4.56 |
| 0040 | Portable changeable message sign, temporary (0102-99) | ED | 400 | $10.00 | $11.35 | $12.25 | $11.50 | $10.50 | $14.04 |
| 0045 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 200 | $20.00 | $24.64 | $9.62 | $25.00 | $48.04 | $64.35 |
| 0050 | Sediment barrier (0104-10-3) | LF | 8,936 | $1.50 | $1.19 | $1.81 | $1.11 | $1.50 | $1.52 |
| 0055 | Inlet protection system (0104-18) | EACH | 13 | $100.00 | $135.10 | $136.78 | $138.00 | $263.38 | $175.50 |
| 0060 | Litter removal (0107-1) | ACRE | 883.11 | $1.00 | $34.13 | $35.08 | $26.00 | $41.09 | $45.34 |
| 0065 | Mowing (0107-2) | ACRE | 883.11 | $1.00 | $60.05 | $61.72 | $41.00 | $41.09 | $45.34 |
| 0070 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $5,000.00 | $15,526 | $24,767 | $9,327.00 | $25,355 | $26,083 |
| 0075 | Borrow excavation, truck measure (0120-2-2) | CY | 3.90 | $440.00 | $248.58 | $111.69 | $370.00 | $316.14 | $117.63 |
| 0080 | Turnout construction- asphalt/driveway base- asphalt material (0286-2) | TN | 35.40 | $200.00 | $270.19 | $331.20 | $430.00 | $380.92 | $348.81 |
| 0085 | Milling existing asphalt pavement, 1" avg depth (0327-70-1) | SY | 40,061 | $1.00 | $1.86 | $3.36 | $1.25 | $1.61 | $3.98 |
| 0090 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 64,909 | $1.50 | $1.18 | $3.03 | $2.00 | $2.94 | $3.89 |
| 0095 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 2,036 | $3.00 | $13.08 | $3.09 | $8.35 | $11.07 | $39.93 |
| 0100 | Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8) | SY | 61,890 | $1.50 | $1.20 | $2.82 | $1.65 | $2.70 | $3.74 |
| 0105 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 12,992.30 | $140.00 | $138.70 | $112.61 | $112.40 | $121.88 | $148.45 |
| 0110 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 13,933.90 | $165.00 | $149.88 | $144.14 | $162.00 | $140.53 | $189.71 |
| 0115 | Miscellaneous asphalt (0339-1) | TN | 21.30 | $300.00 | $777.70 | $439.68 | $1,000.00 | $736.23 | $660.79 |
| 0120 | Replace grate (0425-82) | EACH | 1 | $2,500.00 | $2,485.87 | $3,026.94 | $8,040.00 | $1,697.66 | $3,187.83 |
| 0125 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 42 | $150.00 | $402.06 | $300.58 | $530.00 | $832.04 | $316.55 |
| 0130 | Pipe culvert, optional material, round, 24"SD (0430-174124) | LF | 8 | $250.00 | $694.96 | $497.47 | $1,158.00 | $1,563.96 | $523.91 |
| 0135 | Pipe culvert, optional material, other shape - ellip/arch, 15"SD (0430-174215) | LF | 8 | $150.00 | $679.83 | $381.83 | $1,134.00 | $1,587.70 | $402.13 |
| 0140 | Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218) | LF | 32 | $200.00 | $317.75 | $248.35 | $196.00 | $632.72 | $261.55 |
| 0145 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 11 | $1,500.00 | $2,253.49 | $3,263.73 | $2,783.00 | $2,056.98 | $3,437.20 |
| 0150 | Mitered end section, optional round, 24" SD (0430-984129) | EACH | 2 | $1,800.00 | $2,485.87 | $5,413.38 | $2,985.00 | $2,198.64 | $5,701.11 |
| 0155 | Mitered end section, optional other - ellip/arch, 15" SD (0430-984623) | EACH | 2 | $1,800.00 | $2,361.57 | $2,904.01 | $2,965.00 | $1,894.29 | $3,058.36 |
| 0160 | Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625) | EACH | 4 | $2,000.00 | $2,453.44 | $3,394.32 | $3,037.00 | $1,995.74 | $3,574.73 |
| 0165 | Mitered end sect, replace slab- construction use (0430-991) | EACH | 17 | $1,200.00 | $2,837.12 | $1,662.68 | $2,056.00 | $1,279.54 | $1,751.05 |
| 0170 | Bridge deck expansion joint, rehabilitation, poured joint backer rod (0458-1-21) | LF | 30 | $100.00 | $86.47 | $88.88 | $86.75 | $84.28 | $93.60 |
| 0175 | Bridge deck expansion joint, rehabilitation, poured joint without backer rod (0458-1-28) | LF | 280 | $65.00 | $59.44 | $61.10 | $60.00 | $57.94 | $64.35 |
| 0180 | Polymer nosing for bridge expansion joint (0458-2) | CF | 5 | $1,000.00 | $1,026.77 | $1,055.39 | $1,030.00 | $1,748.68 | $1,111.49 |
| 0185 | Guardrail -roadway, general (0536-1-1) | LF | 200 | $35.00 | $32.42 | $33.33 | $32.50 | $31.61 | $35.10 |
| 0190 | Guardrail removal (0536-73) | LF | 613 | $5.00 | $2.43 | $2.50 | $2.40 | $2.37 | $2.63 |
| 0195 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 8 | $3,500.00 | $2,593.94 | $2,666.25 | $2,603.00 | $2,528.44 | $2,807.97 |
| 0200 | Performance turf (0570-1-1) | SY | 3,854 | $1.00 | $10.75 | $3.57 | $8.50 | $6.84 | $7.44 |
| 0205 | Performance turf, sod (0570-1-2) | SY | 2,229 | $3.90 | $12.75 | $7.62 | $10.50 | $11.90 | $7.44 |
| 0210 | Shoulder drop off soil (0570-13-1) | CY | 495.40 | $25.00 | $36.21 | $53.56 | $56.00 | $153.74 | $56.41 |
| 0215 | Conduit, furnish & install, open trench (0630-2-11) | LF | 23 | $45.00 | $46.64 | $47.94 | $46.00 | $21.01 | $50.49 |
| 0220 | Conduit, furnish & install, open trench under pavement (0630-2-17) | LF | 45 | $50.00 | $62.81 | $64.56 | $62.00 | $31.81 | $67.99 |
| 0225 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 1 | $1,850.00 | $1,824.56 | $1,875.42 | $1,829.00 | $1,412.57 | $1,975.11 |
| 0230 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 2 | $3,000.00 | $2,991.26 | $3,074.65 | $3,000.00 | $2,865.89 | $3,238.07 |
| 0235 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 2 | $4,400.00 | $3,689.95 | $3,792.81 | $3,700.00 | $2,882.90 | $3,994.41 |
| 0240 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 33.79 | $1,000.00 | $1,059.20 | $1,777.29 | $1,830.89 | $979.77 | $2,193.47 |
| 0245 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 950 | $1.65 | $1.62 | $1.67 | $1.70 | $1.47 | $1.75 |
| 0250 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 608 | $2.25 | $2.16 | $2.22 | $2.29 | $1.90 | $2.34 |
| 0255 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.01 | $1,000.00 | $756.56 | $635.00 | $652.00 | $421.41 | $417.86 |
| 0260 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 2.74 | $750.00 | $648.49 | $886.80 | $919.15 | $579.43 | $788.01 |
| 0265 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 22 | $75.00 | $64.85 | $94.43 | $97.00 | $42.14 | $50.31 |
| 0270 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 130 | $40.00 | $39.99 | $44.44 | $45.50 | $34.77 | $40.95 |
| 0275 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 28.41 | $1,000.00 | $1,059.20 | $1,777.50 | $1,827.00 | $979.77 | $2,193.73 |
| 0280 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 1,894 | $1.75 | $1.62 | $1.67 | $1.71 | $1.47 | $1.75 |
| 0285 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 3.35 | $750.00 | $756.56 | $888.75 | $913.00 | $421.41 | $584.99 |
| 0290 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.60 | $1,000.00 | $648.49 | $882.86 | $922.00 | $579.43 | $784.52 |
| 0295 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $71,000 | $71,000 | $71,000 | $71,000 | $71,000 | $71,000 |
| 0300 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 22.57 | $1,650.00 | $2,457.69 | $2,266.63 | $2,548.00 | $1,790.33 | $2,835.54 |
| 0305 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 36 | $575.00 | $591.20 | $666.56 | $656.00 | $605.77 | $672.74 |
| 0310 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 3 | $2,250.00 | $2,396.15 | $2,221.88 | $2,189.00 | $2,317.73 | $2,573.97 |
| 0315 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $200.00 | $540.41 | $666.57 | $656.00 | $210.70 | $233.99 |
| 0320 | Single column ground sign assembly, remove (0700-1600) | EACH | 33 | $50.00 | $81.06 | $11.11 | $10.95 | $26.34 | $29.25 |
| 0325 | Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115) | EACH | 1 | $8,000.00 | $8,297.38 | $8,887.51 | $8,757.00 | $8,164.74 | $9,067.40 |
| 0330 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 1 | $1,000.00 | $1,296.97 | $1,666.41 | $1,641.00 | $1,316.89 | $1,462.49 |
| 0335 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 48 | $250.00 | $357.75 | $305.51 | $300.00 | $210.70 | $234.00 |
| 0340 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 48 | $50.00 | $54.04 | $11.11 | $10.95 | $47.41 | $52.65 |
| 0345 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 15 | $150.00 | $117.81 | $111.09 | $109.00 | $89.55 | $99.45 |
| 0350 | Object marker, type 1 (0705-10-1) | EACH | 9 | $200.00 | $226.97 | $333.28 | $328.00 | $184.37 | $204.75 |
| 0355 | Object marker, type 2 (0705-10-2) | EACH | 20 | $200.00 | $118.89 | $138.87 | $137.00 | $184.37 | $204.75 |
| 0360 | Raised pavement marker, type B (0706-1-3) | EACH | 2,908 | $4.00 | $3.89 | $4.44 | $4.57 | $4.21 | $4.56 |
| 0365 | Painted pavement markings, surface (0710-90) | LS | 1 | $100,000 | $99,056 | $66,656 | $68,533 | $64,759 | $97,612 |
| 0370 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 475 | $9.00 | $8.65 | $7.78 | $8.00 | $5.11 | $5.67 |
| 0375 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 304 | $10.00 | $10.27 | $10.00 | $10.29 | $6.82 | $7.57 |
| 0380 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 1.37 | $3,000.00 | $3,242.43 | $4,969.99 | $5,000.00 | $2,370.41 | $2,617.08 |
| 0385 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 11 | $200.00 | $216.17 | $277.73 | $285.00 | $144.33 | $160.29 |
| 0390 | Thermoplastic, standard, arrow (0711-11170) | EACH | 65 | $125.00 | $129.70 | $99.98 | $103.00 | $59.00 | $65.52 |
| 0395 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 947 | $9.00 | $8.65 | $7.78 | $8.00 | $4.56 | $5.07 |
| 0400 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.30 | $3,500.00 | $3,242.43 | $3,862.55 | $4,100.00 | $2,370.41 | $2,615.03 |
| 0405 | Thermoplastic, preformed, 12" white on asphalt pavement, railroad dynamic envelope (0711-14193) | LF | 576 | $20.00 | $19.45 | $13.33 | $13.70 | $8.74 | $9.71 |
| 0410 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 16.90 | $5,450.00 | $5,836.37 | $5,774.49 | $5,950.00 | $5,104.28 | $5,666.24 |
| 0415 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.01 | $10,000 | $2,593.94 | $2,777.00 | $4,082.86 | $1,276.86 | $1,417.14 |
| 0420 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 14.21 | $5,450.00 | $5,836.37 | $5,774.85 | $5,942.00 | $4,528.01 | $5,026.83 |
| 0425 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 1.68 | $2,500.00 | $2,593.94 | $2,769.06 | $2,983.00 | $1,276.86 | $1,413.79 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of August 26, 2026. Compiled by Mirage Metrics.