1/8" preformed bearing pad, type CDP, ODOT 516E41100

Low bidders on ODOT contracts carried a median of $30.00 per EACH for this item, from 23 JAN 2020 to 24 AUG 2023, across 59 low bids. Half of all 276 bids fell between $19.00 and $50.00.

Owner
Ohio DOT
Item
516E41100
Unit
EACH
Data through
12 NOV 2026

ODOT prints this item as “1/8" PREFORMED BEARING PAD”.

$30.00Low bidder's median, per EACH
$30.50Median of all bids, per EACH
53Contracts in the window

By year of letting

1/8" preformed bearing pad, type CDP, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201821$25.00114$29.50
20211214$25.0063$20.00
20221010$32.5051$40.00
20231314$37.0048$42.03

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
MAR5$44.0038$44.00
MEG6$25.0023$25.00
HIG3$25.0018$31.50
PRE5$32.4417$25.00
CAR3$25.0017$20.00
1/8" preformed bearing pad, type CDP, ODOT: unit prices by county, all lettings

Countys with at least three low bids, over all lettings.

By quantity

Quantity (EACH)Low bidsLow-bid median
2 to 1414$29.75
14 to 1815$20.00
20 to 2415$35.00
24 to 13215$32.44
1/8" preformed bearing pad, type CDP, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Eagle Bridge Co1310 (77%)
R & I Construction Inc97 (78%)
Shelly & Sands Inc225 (23%)
D G M Inc115 (45%)
Miller Bros Const Inc164 (25%)
Kokosing Construction Company Inc54 (80%)
1/8" preformed bearing pad, type CDP, ODOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
24 AUG 2023230433MRG24$39.00$78.005Shelly & Sands IncODOT
24 AUG 2023234020HOL16$30.00$45.003Bog Construction IncODOT
11 MAY 2023230298RIC16$35.00$54.502Mosser Construction IncODOT
27 APR 2023230263MEG24$25.00$55.002D G M IncODOT
27 APR 2023230263MEG24$25.00$55.002D G M IncODOT
13 APR 2023230206ADA16$47.00$48.504Allard Excavation LLCODOT
13 APR 2023230223MEG12$25.00$26.002D G M IncODOT
13 APR 2023238001HAR84$5.00$5.003Miller Bros Const IncODOT
30 MAR 2023234012CAR16$51.56$28.003BCC Ohio IncODOT
23 FEB 2023230126MEG24$45.00$30.004Axis Civil Construction LLCODOT
23 FEB 2023234008WOO72$44.06$44.061BCC Ohio IncODOT
09 FEB 2023230098MAR8$40.00$54.122Shelly & Sands IncODOT
09 FEB 2023230100MOE12$25.00$30.005Buds IncODOT
26 JAN 2023230058PIK12$118.75$50.0010Allard Excavation LLCODOT
15 DEC 2022220670MOT44$10.00$75.003Eagle Bridge CoODOT
Latest ODOT contracts carrying 1/8" preformed bearing pad, type CDP

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the ODOT letting of 12 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy