ODOT contract 240576 bid tabulation

DEL-SR 521-10.32 and Various (BRIDGE REPLACEMENT (2 BRIDGES)). Let by Ohio DOT on January 16, 2025, DEL. 7 bids received; low bid $2,571,926 by Miller Bros Const Inc, -16% against the engineer's estimate of $3,075,000.

Owner
Ohio DOT
Letting
16 JAN 2025
Pay items
116
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Miller Bros Const Inc$2,571,926Low-16%
2Buds Inc$2,617,665+2.0%-15%
3Shelly & Sands Inc$2,642,059+3.0%-14%
4Double Z Construction Company$2,730,160+6.0%-11%
5E S Wagner Company$2,956,743+15%-4.0%
6Complete General Construction Company$3,101,198+21%+1.0%
7Ruhlin Company$3,615,776+41%+18%
ODOT contract 240576: bids by rank

Engineer's estimate: $3,075,000.

Bid tabulation

LinePay itemUnitQuantity1. Miller Bros Const Inc2. Buds Inc3. Shelly & Sands Inc4. Double Z Construction Company5. E S Wagner Company6. Complete General Construction Company
1Clearing and grubbing (201E11000)LS1$20,000$6,500.00$16,000$25,000$20,000$10,000
2Pavement removed (202E23000)SY2,032$9.00$30.00$17.00$35.00$30.00$25.00
3Pipe removed, 24" and under (202E35100)FT161$37.00$45.00$20.00$12.00$24.00$35.00
4Guardrail removed (202E38000)FT1,157$6.00$2.50$2.50$6.00$6.09$2.00
5Excavation (203E10000)CY1,502$35.00$20.00$24.00$25.00$15.00$26.00
6Embankment (203E20000)CY3,583$20.00$25.00$21.00$32.00$34.00$34.00
7Subgrade compaction (204E10000)SY5,320$2.00$2.00$5.00$5.00$3.50$3.50
8Proof rolling (204E45000)HR3$325.00$50.00$220.00$200.00$425.00$130.00
9Guardrail, type MGS (606E15050)FT525$20.00$28.50$20.00$20.00$20.30$19.60
10Guardrail, type MGS with long posts (606E15100)FT200$24.00$21.50$21.50$24.00$24.37$21.40
11Guardrail, type MGS, long-span (606E17360)FT100$22.00$24.00$24.00$22.00$22.34$23.60
12Anchor assembly, MGS type E (MASH 2016) (606E26150)EACH12$2,350.00$2,450.00$2,500.00$2,350.00$2,385.79$2,585.00
13MGS bridge terminal assembly, type TST-2 (606E34600)EACH4$2,450.00$2,450.00$2,500.00$2,450.00$2,487.31$2,420.00
14Reference monument, type A (623E40500)EACH1$311.76$1,200.00$1,200.00$800.00$188.52$1,500.00
15Right-of-way monument, type B (623E40520)EACH16$311.76$850.00$175.00$500.00$377.46$500.00
16Special - mailbox removed and reset (690E50350)EACH1$275.00$250.00$275.00$300.00$275.00$275.00
17Inspection and compaction testing of unbound materials (878E25000)LS1$11,920$7,500.00$20,000$26,000$32,000$15,300
18Rock channel protection, type B with geotextile fabric (601E32104)CY853$98.00$90.00$92.00$110.00$135.00$125.00
19Topsoil (659E00300)CY1,453$25.00$10.00$16.00$43.00$35.00$35.00
20Seeding and mulching (659E10000)SY11,131$0.92$1.50$0.87$4.50$1.40$1.85
21Commercial fertilizer (659E20000)TON1.51$1,500.00$800.00$912.00$1,720.00$1,250.00$535.00
22Lime (659E31000)ACRE2.29$200.00$150.00$159.00$850.00$150.00$20.00
23Water (659E35000)MGAL59$1.00$0.01$1.00$25.00$1.00$1.00
24Slope erosion protection (670E00500)SY1,958$1.95$3.00$1.46$2.80$2.50$2.50
25Storm water pollution prevention plan (832E15000)LS1$2,875.00$4,500.00$2,875.00$4,000.00$2,500.00$6,000.00
26Storm water pollution prevention inspections (832E15002)LS1$6,420.00$5,000.00$6,800.00$9,000.00$14,000$8,000.00
27Storm water pollution prevention inspection software (832E15010)LS1$10,164$5,000.00$10,164$12,000$9,300.00$10,200
28Erosion control (832E30000)EACH29,853$1.00$1.00$1.00$1.00$1.00$1.00
29Aggregate drains (605E31100)FT926$19.00$20.00$16.00$15.00$20.00$19.00
306" conduit, type E (611E01400)FT120$28.00$18.00$15.00$8.00$23.00$36.00
316" conduit, type F (611E01500)FT120$28.00$15.00$15.00$8.00$24.00$38.00
3212" conduit, type D (611E04900)FT50$48.00$75.00$45.00$65.00$60.00$94.00
3315" conduit, type D (611E06400)FT128$55.00$85.00$61.00$65.00$65.00$85.00
34Pavement planing, asphalt concrete (1.5") (254E01000)SY1,479$16.50$15.50$18.00$18.00$18.00$16.50
35Asphalt concrete base, PG64-22, (449) (301E56000)CY734$192.00$192.00$195.00$195.00$195.00$197.75
36Aggregate base (304E20000)CY907$67.00$85.00$75.00$95.00$66.00$115.00
37Aggregate base, as per plan (304E20001)CY77$65.00$105.00$90.00$95.00$128.00$165.00
38Non-tracking tack coat (407E20000)GAL751$3.90$3.90$3.50$3.50$3.50$3.90
39Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY356$278.00$278.00$270.00$270.00$270.00$290.75
40Compacted aggregate (617E10100)CY25$97.00$98.00$190.00$110.00$91.00$134.00
41RPM (621E00100)EACH22$130.00$220.00$199.00$172.00$266.36$284.00
42Raised pavement marker removed (621E54000)EACH12$60.00$5.00$9.00$20.00$21.00$45.00
43Barrier reflector, type 1 (BI-directional) (626E00102)EACH4$13.00$10.00$10.00$13.00$13.20$10.50
44Barrier reflector, type 3 (BI-directional) (626E00112)EACH22$13.00$15.00$15.00$13.00$13.20$12.00
45Ground mounted support, no. 3 post (630E03100)FT81.10$25.00$17.50$17.50$28.00$27.30$18.00
46Sign post reflector (630E08600)EACH4$80.00$50.00$50.00$78.00$77.53$45.00
47Sign, flat sheet (630E80100)SF53.40$26.50$25.00$25.00$30.00$29.76$28.00
48Removal of ground mounted sign and disposal (630E84900)EACH11$60.00$12.00$25.00$16.50$16.10$10.00
49Removal of ground mounted post support and disposal (630E86002)EACH7$65.00$12.00$25.00$21.50$21.46$20.00
50Edge line, 6", type 1 (642E00104)MI0.60$4,500.00$2,100.00$1,800.00$1,800.00$1,800.00$1,800.00
51Center line, type 1 (642E00300)MI0.40$11,250$2,500.00$2,500.00$2,000.00$2,000.00$2,000.00
52Traffic compacted surface, type A or B (410E12000)CY15$156.00$100.00$92.00$70.00$100.00$88.00
53Law enforcement officer with patrol car for assistance (614E11110)HR80$98.00$65.00$110.00$55.00$78.00$85.00
54Detour signing (614E12420)LS1$9,330.00$13,500$9,452.00$13,500$12,598$20,000
55Asphalt concrete for maintaining traffic (614E13000)CY50$680.00$115.00$265.00$150.00$440.00$300.00
56Water (616E10000)MGAL16$61.00$1.00$44.00$25.00$300.00$90.00
57Structure removed, over 20 foot span (202E11002)LS1$30,000$45,000$36,500$30,000$156,000$55,000
58Approach slab removed (202E22900)SY111$45.00$55.00$26.00$50.00$69.00$50.00
59Cofferdams and excavation bracing (503E11100)LS1$14,000$14,000$23,000$20,000$30,000$22,000
60Unclassified excavation (503E21300)LS1$16,000$20,000$9,000.00$20,000$3,000.00$80,000
61Pile driving equipment mobilization (505E11100)LS1$14,000$14,000$18,000$25,000$7,000.00$20,000
62Steel piles HP10X42, furnished (507E00100)FT560$26.00$52.00$24.55$40.00$30.00$75.00
63Steel piles HP10X42, driven (507E00150)FT480$29.00$2.00$32.00$8.00$23.00$10.00
64Galvanized steel reinforcement (509E26000)LB31,405$2.10$2.00$1.70$1.75$1.92$2.00
65Class QC2 concrete, bridge deck (511E34444)CY105$1,245.00$1,250.00$1,350.00$1,300.00$1,400.00$1,500.00
66Class QC1 concrete, abutment including footing (511E43510)CY78$880.00$880.00$890.00$750.00$847.00$800.00
67Sealing of concrete surfaces (non-epoxy) (512E10050)SY89$19.00$19.00$20.00$20.00$22.00$20.00
68Type 2 waterproofing (512E33000)SY11$42.00$42.00$75.00$40.00$71.00$45.00
69Structural steel members, level 3, as per plan (513E10261)LB48,000$2.75$2.75$2.90$3.00$2.90$2.91
70Welded stud shear connectors (513E20000)EACH1,026$5.45$4.50$6.00$5.25$5.50$8.00
711/2" preformed expansion joint filler (516E13200)SF86$9.00$9.00$3.50$12.00$9.00$11.00
721" preformed expansion joint filler (516E13600)SF86$6.00$6.00$4.00$12.00$10.00$12.00
732" preformed expansion joint filler (516E13900)SF38$8.00$8.00$7.00$17.00$14.00$13.00
74Semi-integral abutment expansion joint seal (516E14020)FT107$30.00$30.00$30.00$35.00$40.00$50.00
75Elastomeric bearing with internal laminates and load plate (516E44000)EACH12$1,550.00$1,550.00$1,200.00$1,500.00$1,509.00$1,200.00
76Railing (three steel tube bridge railing) (517E70100)FT132$427.00$450.00$450.00$450.00$442.49$460.00
77Porous backfill with geotextile fabric (518E21200)CY4$375.00$500.00$140.00$295.00$300.00$300.00
78Special - steel drip strip (518E22300)FT127$15.00$15.00$15.50$20.00$30.00$27.00
796" perforated corrugated plastic pipe (518E40000)FT121$14.00$14.00$4.50$11.00$9.00$11.00
806" non-perforated corrugated plastic pipe, including specials (518E40010)FT52$23.00$23.00$15.00$11.00$50.00$19.00
81Reinforced concrete approach slabs (T=13"), as per plan (526E15001)SY178$410.00$410.00$325.00$425.00$370.00$400.00
82Type C installation, as per plan (526E90031)FT80$295.00$295.00$250.00$275.00$220.00$320.00
83Structure grounding system (625E33000)EACH1$14,780$14,780$16,250$17,645$14,250$15,000
84Structure removed, over 20 foot span (202E11002)LS1$28,000$35,000$39,000$20,000$110,000$65,000
85Approach slab removed (202E22900)SY111$55.00$65.00$26.00$50.00$70.00$50.00
86Cofferdams and excavation bracing (503E11100)LS1$16,000$12,000$26,000$25,000$1.00$22,000
87Unclassified excavation (503E21100)CY605$100.00$35.00$25.00$30.00$135.00$100.00
88Epoxy coated steel reinforcement (509E10000)LB19,112$1.90$1.42$1.30$1.30$1.65$2.00
89Class QC1 concrete with QC/QA, footing (511E46512)CY313$500.00$725.00$550.00$410.00$388.00$600.00
90Class QC1 concrete, retaining/wingwall not including footing (511E46010)CY13$1,575.00$1,200.00$3,100.00$1,500.00$2,200.00$2,700.00
91Class QC1 concrete, headwall (511E46610)CY2$1,950.00$1,800.00$4,100.00$3,000.00$2,500.00$2,300.00
92Sealing of concrete surfaces (non-epoxy) (512E10050)SY82$13.00$25.00$20.00$20.00$22.00$20.00
93Type 2 waterproofing (512E33000)SY161$30.00$22.00$26.50$27.00$42.00$26.50
94Type 3 waterproofing (512E33010)SY289$35.00$38.00$35.00$45.00$52.00$35.00
951" preformed expansion joint filler (516E13600)SF31$7.50$15.00$1.90$12.00$11.00$13.00
96Porous backfill with geotextile fabric (518E21200)CY13$160.00$165.00$210.00$200.00$160.00$140.00
97Conduit, type A, precast reinforced concrete three sided flat topped culvert (611E70000)FT72$3,700.00$4,800.00$4,100.00$4,400.00$4,400.00$4,300.00
98Structure removed (202E11000)LS1$3,000.00$6,000.00$10,000$10,000$10,000$20,000
99Cofferdams and excavation bracing (503E11100)LS1$2,000.00$3,000.00$25,000$10,000$1.00$5,000.00
100Unclassified excavation (503E21100)CY63$66.00$45.00$125.00$60.00$80.00$250.00
101Epoxy coated steel reinforcement (509E10000)LB3,696$1.90$2.00$1.35$1.30$1.65$2.00
102Class QC1 concrete, retaining/wingwall not including footing (511E46010)CY12$1,525.00$250.00$800.00$1,300.00$2,500.00$1,100.00
103Class QC1 concrete, footing (511E46510)CY27$505.00$250.00$1,125.00$1,000.00$750.00$700.00
104Class QC1 concrete, headwall (511E46610)CY1$2,400.00$2,000.00$6,200.00$2,500.00$3,500.00$4,000.00
105Sealing of concrete surfaces (non-epoxy) (512E10050)SY41$21.00$10.00$20.00$20.00$40.00$20.00
106Type 2 waterproofing (512E33000)SY189$31.00$40.00$26.50$27.00$46.00$26.50
1071" preformed expansion joint filler (516E13600)SF26$9.00$20.00$2.20$12.00$10.00$14.00
108Porous backfill with geotextile fabric (518E21200)CY6$270.00$250.00$180.00$200.00$180.00$140.00
1099' X 4' conduit, type A, 706.05 (611E94936)FT84$1,250.00$1,400.00$1,210.00$1,225.00$1,360.00$1,700.00
110Premium for contract performance bond and for payment bond (103E05000)LS1$15,000$20,000$16,000$15,000$17,000$20,000
111Maintaining traffic (614E11000)LS1$4,800.00$7,500.00$27,000$10,000$10,000$25,000
112Field office, type A (619E16000)MNTH6$3,300.00$1,800.00$3,900.00$1,400.00$2,500.00$2,500.00
113Construction layout stakes and surveying (623E10000)LS1$21,900$10,000$25,000$12,000$8,000.00$28,000
114Preconstruction survey monument verification and report (623E50000)LS1$5,050.00$1,200.00$2,000.00$2,000.00$2,000.00$2,000.00
115Post construction survey monument verification and report (623E51000)LS1$5,050.00$1,200.00$2,000.00$2,000.00$2,000.00$2,000.00
116Mobilization (624E10000)LS1$128,000$85,000$131,562$100,000$100,000$100,000
ODOT contract 240576: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy