ODOT contract 250130 bid tabulation
MOT-SR 4-19.30 (MINOR RECONSTRUCTION). Let by Ohio DOT on February 27, 2025, MOT. 3 bids received; low bid $4,216,534 by Barrett Paving Materials Inc, -26% against the engineer's estimate of $5,723,000.
- Owner
- Ohio DOT
- Letting
- 27 FEB 2025
- Pay items
- 120
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Barrett Paving Materials Inc | $4,216,534 | Low | -26% |
| 2 | John R Jurgensen Company | $4,525,489 | +7.0% | -21% |
| 3 | R B Jergens Contractors Inc | $5,677,301 | +35% | -1.0% |
Engineer's estimate: $5,723,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Barrett Paving Materials Inc | 2. John R Jurgensen Company | 3. R B Jergens Contractors Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $20,000 | $42,011 | $4,572.40 |
| 2 | Pavement removed (202E23000) | SY | 15,926 | $12.00 | $16.76 | $15.08 |
| 3 | Concrete barrier removed (202E30700) | FT | 104 | $30.00 | $32.69 | $71.11 |
| 4 | Guardrail removed (202E38000) | FT | 3,478 | $3.00 | $3.00 | $3.11 |
| 5 | Anchor assembly removed, type E (202E42010) | EACH | 4 | $200.00 | $200.00 | $207.15 |
| 6 | Anchor assembly removed, type T (202E42040) | EACH | 3 | $100.00 | $100.00 | $103.58 |
| 7 | Bridge terminal assembly removed (202E47000) | EACH | 7 | $125.00 | $125.00 | $129.47 |
| 8 | Monument assembly removed (202E60010) | EACH | 5 | $100.00 | $470.06 | $591.03 |
| 9 | Embankment (203E20000) | CY | 2,112 | $18.50 | $42.21 | $16.63 |
| 10 | Subgrade compaction (204E10000) | SY | 20,836 | $1.30 | $1.91 | $4.16 |
| 11 | Excavation of subgrade (204E13000) | CY | 20,994 | $5.80 | $8.01 | $29.72 |
| 12 | Granular embankment, as per plan (204E21001) | CY | 20,989 | $8.50 | $7.06 | $53.88 |
| 13 | Proof rolling (204E45000) | HR | 9 | $225.00 | $211.31 | $336.81 |
| 14 | Geogrid, as per plan (204E51001) | SY | 41,955 | $8.25 | $6.15 | $7.41 |
| 15 | Geogrid, as per plan (204E51001) | SY | 20,989 | $10.25 | $7.99 | $9.14 |
| 16 | Guardrail, type MGS (606E15050) | FT | 2,400 | $20.00 | $20.00 | $20.72 |
| 17 | Anchor assembly, MGS type E, as per plan, MASH 201 (606E26151) | EACH | 3 | $2,450.00 | $2,450.00 | $2,537.60 |
| 18 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,175.00 | $1,175.00 | $1,217.01 |
| 19 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 5 | $2,350.00 | $2,350.00 | $2,434.02 |
| 20 | MGS bridge terminal assembly, type 2 (606E35102) | EACH | 3 | $425.00 | $425.00 | $440.20 |
| 21 | Concrete barrier, single slope, type D (622E10160) | FT | 154 | $300.00 | $300.00 | $169.07 |
| 23 | Reference monument, type A (623E40500) | EACH | 5 | $550.00 | $1,149.58 | $1,515.69 |
| 24 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 10 | $150.00 | $269.60 | $205.82 |
| 25 | Soil analysis test (659E00100) | EACH | 2 | $135.00 | $135.00 | $517.88 |
| 26 | Topsoil (659E00300) | CY | 1,302 | $42.00 | $35.58 | $63.58 |
| 27 | Seeding and mulching (659E10000) | SY | 11,725 | $0.90 | $0.88 | $1.19 |
| 28 | Repair seeding and mulching (659E14000) | SY | 587 | $0.90 | $0.88 | $1.04 |
| 29 | Inter-seeding (659E15000) | SY | 587 | $0.50 | $0.50 | $0.01 |
| 30 | Commercial fertilizer (659E20000) | TON | 1.64 | $900.00 | $900.00 | $1,553.63 |
| 31 | Lime (659E31000) | ACRE | 2.43 | $75.00 | $75.00 | $207.15 |
| 32 | Water (659E35000) | MGAL | 65 | $1.00 | $1.00 | $1.04 |
| 36 | Erosion control (832E30000) | EACH | 32,276 | $1.00 | $1.00 | $1.00 |
| 37 | 6" deep pipe underdrains with geotextile fabric (605E12210) | FT | 9,738 | $8.00 | $27.94 | $10.46 |
| 38 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 261 | $30.00 | $45.60 | $34.01 |
| 39 | 6" conduit, type F (611E01500) | FT | 115 | $40.00 | $50.16 | $38.94 |
| 40 | Catch basin adjusted to grade (611E98630) | EACH | 1 | $1,375.00 | $971.61 | $2,313.89 |
| 41 | Precast reinforced concrete outlet (611E99710) | EACH | 5 | $400.00 | $657.84 | $545.58 |
| 42 | Special - miscellaneous metal (611E99820) | LB | 120 | $3.00 | $7.32 | $19.32 |
| 43 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 1,870 | $155.00 | $170.00 | $183.13 |
| 44 | Aggregate base (304E20000) | CY | 2,873 | $65.00 | $62.56 | $73.88 |
| 45 | Non-tracking tack coat (407E20000) | GAL | 1,987 | $3.50 | $5.00 | $5.39 |
| 47 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 690 | $290.00 | $271.00 | $291.94 |
| 48 | Asphalt concrete intermediate course, 12.5 MM, type A (446) (442E10080) | CY | 805 | $225.00 | $210.00 | $226.22 |
| 49 | Curb, type 4-C (609E24510) | FT | 90 | $60.00 | $64.41 | $39.20 |
| 50 | Connection, fused pull apart (625E00450) | EACH | 32 | $136.40 | $136.40 | $141.28 |
| 51 | Connection, unfused permanent (625E00480) | EACH | 12 | $146.40 | $146.40 | $151.63 |
| 52 | Light pole foundation, 24" X 10' deep (625E14200) | EACH | 13 | $2,100.00 | $2,100.00 | $2,175.08 |
| 53 | Duct cable, misc.: 2" duct cable with three no. 4 (625E24400) | FT | 2,779 | $11.90 | $11.90 | $12.33 |
| 54 | Duct cable, misc.: duct cable removed (625E24400) | FT | 2,684 | $8.00 | $8.00 | $8.29 |
| 55 | Trench (625E29000) | FT | 2,674 | $11.60 | $11.60 | $12.01 |
| 56 | Pull box removed (625E31510) | EACH | 1 | $249.00 | $249.00 | $257.90 |
| 57 | Pull box, misc.: adjust to grade (625E31600) | EACH | 11 | $454.00 | $454.00 | $470.23 |
| 58 | Ground rod (625E32000) | EACH | 16 | $300.00 | $300.00 | $310.73 |
| 59 | Remove and reerect existing light pole, as per plan (625E35011) | EACH | 18 | $850.00 | $850.00 | $880.39 |
| 60 | Underground warning marking tape (625E36010) | FT | 2,674 | $3.60 | $3.60 | $3.73 |
| 61 | Special - maintain existing lighting (625E40000) | LS | 1 | $6,500.00 | $4,120.00 | $4,267.31 |
| 62 | Light pole foundation removed (625E75500) | EACH | 13 | $420.00 | $420.00 | $435.02 |
| 63 | RPM (621E00100) | EACH | 53 | $49.00 | $49.00 | $50.75 |
| 64 | Raised pavement marker removed (621E54000) | EACH | 45 | $17.00 | $18.94 | $15.28 |
| 65 | Ground mounted support, no. 3 post (630E03100) | FT | 95.60 | $14.75 | $14.75 | $15.28 |
| 66 | Ground mounted structural beam support, S4X7.7 (630E06400) | FT | 69.10 | $26.00 | $26.00 | $26.93 |
| 67 | Ground mounted structural beam support, W6X9 (630E06500) | FT | 43.80 | $27.00 | $27.00 | $27.97 |
| 68 | Sign post reflector (630E08600) | EACH | 4 | $60.00 | $60.00 | $62.15 |
| 69 | Breakaway structural beam connection (630E09000) | EACH | 6 | $330.00 | $330.00 | $341.80 |
| 70 | Overhead sign support, type TC-12.30, design 10 (630E21000) | EACH | 1 | $34,650 | $34,650 | $35,889 |
| 71 | Overhead sign support, type TC-15.116, design 1 (630E72410) | EACH | 1 | $55,000 | $55,000 | $56,966 |
| 72 | Sign, flat sheet (630E80100) | SF | 52.50 | $20.00 | $20.00 | $20.72 |
| 73 | Sign, ground mounted extrusheet (630E80200) | SF | 92 | $28.00 | $28.00 | $29.00 |
| 74 | Sign, overhead extrusheet (630E80224) | SF | 546 | $32.00 | $32.00 | $33.14 |
| 75 | Sign backing assembly (630E82000) | EACH | 1 | $500.00 | $500.00 | $517.88 |
| 76 | Ground mounted structural beam support foundation (630E84500) | EACH | 6 | $1,250.00 | $1,250.00 | $1,294.69 |
| 77 | Rigid overhead sign support foundation (630E84510) | EACH | 3 | $9,400.00 | $9,400.00 | $9,736.09 |
| 78 | Removal of ground mounted sign and disposal (630E84900) | EACH | 8 | $25.00 | $25.00 | $25.89 |
| 79 | Removal of ground mounted major sign and disposal (630E85400) | EACH | 1 | $350.00 | $350.00 | $362.51 |
| 80 | Removal of ground mounted post support and disposal (630E86002) | EACH | 7 | $50.00 | $50.00 | $51.79 |
| 81 | Removal of ground mounted structural beam support (630E86102) | EACH | 4 | $250.00 | $250.00 | $258.94 |
| 82 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 6 | $300.00 | $300.00 | $310.73 |
| 83 | Removal of overhead sign support and disposal, type TC-12.30 (630E89706) | EACH | 1 | $1,900.00 | $1,900.00 | $1,967.93 |
| 84 | Removal of overhead sign support and disposal, type TC-15.115 (630E89804) | EACH | 1 | $2,900.00 | $2,900.00 | $3,003.69 |
| 85 | Edge line, 6" (644E00104) | MI | 2.10 | $4,660.00 | $4,660.00 | $4,826.61 |
| 86 | Lane line, 6" (644E00204) | MI | 0.60 | $2,180.00 | $2,180.00 | $2,257.93 |
| 87 | Channelizing line, 8" (644E00400) | FT | 619 | $1.50 | $1.50 | $1.55 |
| 88 | Chevron marking (644E00720) | FT | 168 | $9.00 | $9.00 | $9.32 |
| 89 | Dotted line, 6" (644E01510) | FT | 659 | $2.00 | $2.00 | $2.07 |
| 90 | Traffic compacted surface, type A or B (410E12000) | CY | 50 | $230.00 | $157.83 | $121.32 |
| 91 | Traffic compacted surface, type C (410E13000) | CY | 50 | $240.00 | $157.83 | $129.80 |
| 92 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $85.00 | $106.78 | $126.67 |
| 93 | Increased barrier delineation (614E11630) | FT | 5,328 | $6.00 | $2.59 | $6.21 |
| 94 | Work zone impact attenuator, 24" wide hazards, (unidirectional), as per plan (614E12381) | EACH | 2 | $2,600.00 | $2,281.30 | $2,692.96 |
| 95 | Detour signing (614E12420) | LS | 1 | $22,000 | $22,000 | $22,787 |
| 96 | Work zone speed limit sign (614E12470) | EACH | 4 | $200.00 | $218.38 | $207.15 |
| 97 | Work zone increased penalties sign (614E12484) | EACH | 4 | $200.00 | $218.38 | $207.15 |
| 98 | Work zone crossover lighting system, as per plan (614E12757) | EACH | 2 | $25,110 | $25,110 | $26,008 |
| 99 | Work zone raised pavement marker, as per plan (614E12801) | EACH | 368 | $16.00 | $33.37 | $16.57 |
| 100 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $380.00 | $155.00 | $226.77 |
| 101 | Barrier reflector, type 1, one-way (614E13310) | EACH | 642 | $14.00 | $21.47 | $14.50 |
| 102 | Portable changeable message sign, as per plan (614E18601) | SNMT | 14 | $800.00 | $800.00 | $828.60 |
| 103 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 5.68 | $1,380.00 | $1,380.00 | $1,429.34 |
| 104 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 609 | $1.00 | $1.00 | $1.04 |
| 105 | Work zone dotted line, class I, 6", 642 paint (614E24202) | FT | 925 | $0.75 | $0.75 | $0.78 |
| 106 | Roads for maintaining traffic (615E10000) | LS | 1 | $300,000 | $317,158 | $95,752 |
| 107 | Pavement for maintaining traffic, class A (615E20000) | SY | 4,802 | $52.50 | $45.00 | $59.13 |
| 108 | Water (616E10000) | MGAL | 10 | $50.00 | $100.10 | $148.63 |
| 109 | Portable barrier, 50", as per plan (622E41011) | FT | 5,328 | $31.50 | $29.96 | $32.42 |
| 110 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 28 | $900.00 | $900.00 | $932.18 |
| 111 | Portable non-intrusive traffic sensor, class I (896E00010) | SNMT | 56 | $850.00 | $850.00 | $880.39 |
| 112 | Portable changeable message sign, as per plan (896E00021) | SNMT | 14 | $700.00 | $700.00 | $725.03 |
| 113 | Special - work involving non-regulated materials (690E65000) | TON | 315 | $60.00 | $48.00 | $58.37 |
| 114 | Special - work involving solid waste (690E65010) | TON | 315 | $90.00 | $67.00 | $91.72 |
| 115 | Special - work involving non-regulated water (690E65022) | GAL | 3,150 | $3.00 | $3.50 | $4.91 |
| 116 | Special - work involving regulated water (690E65024) | GAL | 3,150 | $3.00 | $3.50 | $7.24 |
| 117 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,355 | $22,169 | $12,804 |
| 118 | CPM progress schedule short duration projects (108E30000) | LS | 1 | $5,000.00 | $3,900.63 | $10,028 |
| 119 | Maintaining traffic (614E11000) | LS | 1 | $148,750 | $149,049 | $115,683 |
| 120 | Field office, type B (619E16010) | MNTH | 7 | $900.00 | $2,081.33 | $1,583.35 |
| 121 | Construction layout stakes and surveying (623E10000) | LS | 1 | $30,000 | $8,868.76 | $58,002 |
| 122 | Mobilization (624E10000) | LS | 1 | $50,000 | $200,000 | $87,230 |
| 200 | Stabilized crushed aggregate (411E10000) | CY | 178 | $110.00 | $99.62 | $91.48 |
| 201 | Granular material, type B (204E30010) | CY | 2,000 | $85.00 | $74.84 | $58.13 |
| 202 | Compacted aggregate (617E10100) | CY | 126 | $140.00 | $219.97 | $111.33 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.