Low bidders on ODOT contracts carried a median of $1,950.00 per EACH for this item, over the 24 months to 12 NOV 2026, across 15 low bids. Half of all 40 bids fell between $1,680.00 and $2,105.00.
- Owner
- Ohio DOT
- Item
- 630E89706
- Unit
- EACH
- Data through
- 12 NOV 2026
ODOT prints this item as “REMOVAL OF OVERHEAD SIGN SUPPORT AND DISPOSAL, TYP”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 8 | 8 | $1,410.00 | 27 | $1,390.00 |
| 2021 | 7 | 7 | $1,548.54 | 31 | $1,400.00 |
| 2022 | 8 | 8 | $1,475.00 | 28 | $1,525.49 |
| 2023 | 9 | 9 | $1,500.00 | 31 | $1,700.00 |
| 2024 | 3 | 3 | $1,200.00 | 10 | $1,525.00 |
| 2025 | 8 | 8 | $1,975.00 | 23 | $1,967.93 |
| 2026 | 7 | 7 | $1,850.00 | 17 | $1,820.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 3 | $1,900.00 |
| 1 to 2 | 4 | $1,960.00 |
| 3 to 4 | 4 | $2,225.00 |
| 4 to 6 | 4 | $1,825.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Kokosing Construction Company Inc | 16 | 10 (63%) |
| Complete General Construction Company | 14 | 7 (50%) |
| John R Jurgensen Company | 11 | 7 (64%) |
| Ruhlin Company | 8 | 5 (63%) |
| Sunesis Construction Co | 7 | 5 (71%) |
| Shelly & Sands Inc | 13 | 4 (31%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 07 MAY 2026 | 260167 | ERI | 2 | $2,200.00 | $2,120.00 | 3 | Great Lakes Demolition Company | ODOT |
| 07 MAY 2026 | 260237 | FRA | 5 | $1,800.00 | $1,810.00 | 2 | Shelly & Sands Inc | ODOT |
| 07 MAY 2026 | 260248 | SAN | 1 | $1,750.00 | $1,450.00 | 3 | Great Lakes Demolition Company | ODOT |
| 07 MAY 2026 | 260251 | MOT | 6 | $1,850.00 | $1,850.00 | 2 | John R Jurgensen Company | ODOT |
| 07 MAY 2026 | 260260 | LUC | 1 | $2,170.00 | $2,170.00 | 1 | Miller Bros Const Inc | ODOT |
| 05 FEB 2026 | 260003 | MAH | 6 | $1,680.00 | $1,680.00 | 4 | Shelly & Sands Inc | ODOT |
| 15 JAN 2026 | 260031 | CUY | 1 | $2,350.00 | $2,690.50 | 2 | Karvo Companies Inc | ODOT |
| 25 SEP 2025 | 250439 | MIA | 3 | $3,109.16 | $1,712.50 | 6 | R B Jergens Contractors Inc | ODOT |
| 15 MAY 2025 | 250238 | HAM | 2 | $1,450.00 | $1,450.00 | 2 | John R Jurgensen Company | ODOT |
| 08 MAY 2025 | 250247 | FRA | 4 | $2,200.00 | $2,600.00 | 2 | Lake Erie Construction Company | ODOT |
| 17 APR 2025 | 250151 | FRA | 4 | $2,450.00 | $2,050.00 | 4 | Complete General Construction Company | ODOT |
| 27 FEB 2025 | 250004 | SUM | 3 | $1,950.00 | $1,950.00 | 3 | Kenmore Construction Co Inc | ODOT |
| 27 FEB 2025 | 250076 | FRA | 3 | $2,000.00 | $2,000.00 | 1 | Shelly & Sands Inc | ODOT |
| 27 FEB 2025 | 250130 | MOT | 1 | $1,900.00 | $1,900.00 | 3 | Barrett Paving Materials Inc | ODOT |
| 13 FEB 2025 | 250110 | District 10 | 2 | $1,750.00 | $1,862.50 | 2 | M P Dory Co | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the ODOT letting of 12 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.