ODOT contract 250517 bid tabulation
CLE-Culverts FY26. Let by Ohio DOT on November 13, 2025, CLE. 10 bids received; low bid $293,757 by BCC Ohio Inc.
- Owner
- Ohio DOT
- Letting
- 13 NOV 2025
- Pay items
- 40
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | BCC Ohio Inc | $293,757 | Low |
| 2 | JTM Smith Construction Inc | $306,993 | +5.0% |
| 3 | Fillmore Construction | $343,911 | +17% |
| 4 | Rack & Ballauer Excavating Co Inc | $357,393 | +22% |
| 5 | Axis Civil Construction LLC | $368,308 | +25% |
| 6 | Barrett Paving Materials Inc | $372,099 | +27% |
| 7 | Sunesis Construction Co | $429,078 | +46% |
| 8 | Eagle Bridge Co | $440,099 | +50% |
| 9 | Prus Construction Company | $467,979 | +59% |
| 10 | John R Jurgensen Company | $528,636 | +80% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. BCC Ohio Inc | 2. JTM Smith Construction Inc | 3. Fillmore Construction | 4. Rack & Ballauer Excavating Co Inc | 5. Axis Civil Construction LLC | 6. Barrett Paving Materials Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,096.00 | $4,200.00 | $7,000.00 | $19,000 | $12,000 | $25,000 |
| 2 | Structure removed (202E11000) | LS | 1 | $5,385.00 | $8,000.00 | $5,000.00 | $8,200.00 | $12,000 | $5,000.00 |
| 3 | Headwall removed (202E20010) | EACH | 2 | $774.00 | $3,000.00 | $2,500.00 | $1,000.00 | $1,800.00 | $2,000.00 |
| 4 | Pavement removed (202E23000) | SY | 75 | $13.76 | $30.00 | $10.00 | $30.00 | $18.50 | $25.00 |
| 5 | Special - pipe cleanout over 48" (202E70130) | FT | 68 | $28.46 | $100.00 | $120.00 | $80.00 | $100.00 | $100.00 |
| 6 | Excavation (203E10000) | CY | 98 | $12.90 | $42.00 | $52.00 | $40.00 | $38.00 | $60.00 |
| 7 | Embankment (203E20000) | CY | 347 | $48.87 | $48.00 | $68.00 | $40.00 | $42.00 | $40.00 |
| 8 | Subgrade compaction (204E10000) | SY | 82 | $3.87 | $20.00 | $10.00 | $7.00 | $4.00 | $25.00 |
| 9 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $2,641.50 | $1,500.00 | $10,000 | $500.00 | $6,500.00 | $8,000.00 |
| 10 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $3,241.50 | $1,500.00 | $10,000 | $1,000.00 | $12,000 | $12,000 |
| 11 | Right-of-way monument, type B (623E40520) | EACH | 4 | $761.25 | $1,050.00 | $500.00 | $780.00 | $500.00 | $1,100.00 |
| 12 | Riprap, type D (601E11000) | SY | 18.50 | $516.30 | $114.00 | $100.00 | $315.00 | $275.00 | $225.00 |
| 13 | Rock channel protection, type B with filter (601E32100) | CY | 38.30 | $174.13 | $210.00 | $140.00 | $270.00 | $190.00 | $150.00 |
| 14 | Topsoil (659E00300) | CY | 279 | $17.69 | $50.00 | $50.00 | $80.00 | $55.00 | $68.00 |
| 15 | Seeding and mulching (659E10000) | SY | 2,510 | $3.62 | $3.50 | $1.45 | $3.60 | $2.35 | $1.73 |
| 16 | Commercial fertilizer (659E20000) | TON | 0.34 | $341.26 | $600.00 | $1,400.00 | $1,140.00 | $1,500.00 | $900.00 |
| 17 | Lime (659E31000) | ACRE | 0.52 | $26.25 | $400.00 | $450.00 | $200.00 | $200.00 | $100.00 |
| 18 | Water (659E35000) | MGAL | 13.60 | $1.05 | $1.00 | $1.00 | $1.00 | $1.00 | $13.60 |
| 19 | Ditch erosion protection mat, type B (670E00720) | SY | 102 | $4.41 | $31.00 | $2.00 | $4.55 | $2.75 | $5.75 |
| 20 | Erosion control (832E30000) | EACH | 6,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 21 | Concrete masonry (602E20000) | CY | 34 | $1,559.82 | $1,152.00 | $1,500.00 | $1,850.00 | $1,850.00 | $1,800.00 |
| 22 | 66" conduit, type A, 707.02 aluminized, 706.02, 70 (611E25000) | FT | 90 | $708.87 | $814.00 | $500.00 | $650.00 | $770.00 | $650.00 |
| 23 | Field paving of existing pipe, as per plan, 73"X55 (611E96551) | FT | 68 | $207.97 | $520.00 | $500.00 | $225.00 | $195.00 | $295.00 |
| 24 | Conduit, misc.: CMP repair method A (611E97700) | SF | 68 | $44.40 | $118.00 | $500.00 | $95.00 | $155.00 | $100.00 |
| 25 | Conduit, misc.: CMP repair method B (611E97700) | SF | 12 | $42.76 | $125.00 | $1,000.00 | $123.00 | $480.00 | $150.00 |
| 26 | Pavement planing, asphalt concrete, 3" (254E01000) | SY | 125 | $29.11 | $21.00 | $50.00 | $30.00 | $35.60 | $50.00 |
| 27 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 20 | $630.00 | $435.00 | $400.00 | $365.00 | $500.00 | $1,225.00 |
| 28 | Aggregate base (304E20000) | CY | 14 | $220.71 | $170.00 | $200.00 | $168.00 | $195.00 | $150.00 |
| 29 | Tack coat (407E10000) | GAL | 23 | $1.05 | $24.00 | $10.00 | $4.00 | $6.00 | $4.00 |
| 30 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 17 | $735.00 | $511.00 | $500.00 | $645.00 | $600.00 | $1,250.00 |
| 31 | RPM (621E00100) | EACH | 1 | $241.50 | $900.00 | $935.00 | $1,500.00 | $850.00 | $500.00 |
| 32 | Raised pavement marker removed (621E54000) | EACH | 1 | $20.64 | $100.00 | $25.00 | $20.00 | $50.00 | $10.00 |
| 33 | Edge line, 6", type 1 (642E00104) | MI | 0.02 | $67,200 | $70,000 | $70,400 | $30,000 | $64,000 | $75,000 |
| 34 | Center line, type 1 (642E00300) | MI | 0.01 | $96,600 | $120,000 | $101,200 | $30,000 | $92,000 | $150,000 |
| 35 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 20 | $89.25 | $100.00 | $100.00 | $75.00 | $65.00 | $90.00 |
| 36 | Detour signing (614E12420) | LS | 1 | $5,916.00 | $3,300.00 | $6,600.00 | $10,000 | $7,700.00 | $6,595.00 |
| 37 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,626.68 | $4,850.00 | $5,000.00 | $4,000.00 | $3,500.00 | $1,905.74 |
| 38 | Maintaining traffic (614E11000) | LS | 1 | $11,746 | $4,850.00 | $7,500.00 | $20,000 | $15,000 | $12,500 |
| 39 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,865.00 | $4,200.00 | $3,500.00 | $6,000.00 | $8,000.00 | $4,000.00 |
| 40 | Mobilization (624E10000) | LS | 1 | $21,592 | $4,600.00 | $5,000.00 | $30,000 | $25,000 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.