ODOT contract 260142 bid tabulation
MEG-SR 681-03.07. Let by Ohio DOT on April 23, 2026, MEG. 4 bids received; low bid $9,939,659 by Cast & Baker Corporation.
- Owner
- Ohio DOT
- Letting
- 23 APR 2026
- Pay items
- 117
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Cast & Baker Corporation | $9,939,659 | Low |
| 2 | Allard Excavation LLC | $10,025,000 | +1.0% |
| 3 | Alan Stone Co Inc | $12,319,533 | +24% |
| 4 | Ruhlin Company | $12,914,862 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cast & Baker Corporation | 2. Allard Excavation LLC | 3. Alan Stone Co Inc | 4. Ruhlin Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $429,000 | $158,000 | $750,000 | $205,000 |
| 2 | Special - tree removed, 4"-12" (201E20010) | EACH | 15 | $100.00 | $326.00 | $2,200.00 | $545.00 |
| 3 | Tree removed, 30" diameter (201E23000) | EACH | 5 | $450.00 | $1,251.00 | $5,000.00 | $3,994.50 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 280 | $15.00 | $19.00 | $7.00 | $104.00 |
| 5 | Pipe removed, 24" and under, as per plan (202E35101) | FT | 24 | $15.00 | $20.00 | $25.00 | $245.00 |
| 6 | Pipe removed, over 24" diameter (202E35200) | FT | 52 | $18.00 | $36.00 | $20.00 | $130.00 |
| 7 | Guardrail removed for reuse (202E38200) | FT | 56 | $4.00 | $10.00 | $5.00 | $10.00 |
| 8 | Anchor assembly removed, type A (202E42000) | EACH | 1 | $350.00 | $500.00 | $1,200.00 | $500.00 |
| 9 | Mailbox removed (202E53100) | EACH | 1 | $50.00 | $27.00 | $500.00 | $40.00 |
| 10 | Building demolished parcel 170-089-500-3 (202E56100) | EACH | 1 | $12,000 | $6,780.00 | $25,000 | $17,000 |
| 11 | Special - fill and plug existing conduit (202E70000) | FT | 49 | $55.00 | $470.00 | $150.00 | $355.00 |
| 12 | Fence removed (202E75000) | FT | 217 | $5.00 | $1.00 | $5.00 | $10.00 |
| 13 | Removal misc.: barn (202E98100) | EACH | 1 | $6,000.00 | $2,642.00 | $5,000.00 | $1,900.00 |
| 14 | Removal misc.: pile extraction (202E98100) | EACH | 97 | $75.00 | $154.00 | $200.00 | $405.00 |
| 15 | Removal misc.: standpipe (202E98100) | EACH | 1 | $300.00 | $269.00 | $1,000.00 | $5,345.00 |
| 16 | Removal misc.: well/cistern (202E98100) | EACH | 1 | $1,000.00 | $855.00 | $2,000.00 | $885.00 |
| 17 | Removal misc.:landscaping (202E98300) | SY | 32 | $40.00 | $12.00 | $155.00 | $150.00 |
| 18 | Removal misc.:landscaping blocks (202E98300) | SY | 17 | $35.00 | $22.00 | $100.00 | $140.00 |
| 19 | Excavation (203E10000) | CY | 432,627 | $11.30 | $9.77 | $11.00 | $14.50 |
| 20 | Excavation, as per plan (203E10001) | CY | 197 | $18.00 | $10.00 | $25.00 | $23.50 |
| 21 | Embankment (203E20000) | CY | 47,476 | $2.50 | $2.00 | $12.00 | $6.00 |
| 22 | Granular embankment, as per plan (203E35001) | CY | 1,071 | $82.00 | $115.00 | $100.00 | $126.00 |
| 23 | Granular material, type B (203E35110) | CY | 43 | $105.00 | $100.00 | $115.00 | $266.50 |
| 24 | Granular material, type B, as per plan (203E35111) | CY | 2,509 | $85.00 | $114.00 | $115.00 | $20.50 |
| 25 | Subgrade compaction (204E10000) | SY | 8,336 | $2.25 | $4.00 | $3.00 | $2.50 |
| 26 | Excavation of subgrade (204E13000) | CY | 2,382 | $4.50 | $11.00 | $30.00 | $16.25 |
| 27 | Embankment (204E20000) | CY | 1,588 | $5.00 | $11.00 | $12.00 | $13.00 |
| 28 | Proof rolling (204E45000) | HR | 5 | $1,000.00 | $259.00 | $2,000.00 | $615.00 |
| 29 | Pre-blast condition survey (208E10000) | LS | 1 | $4,000.00 | $3,200.00 | $25,000 | $3,200.00 |
| 30 | Blasting consultant (208E12000) | LS | 1 | $7,000.00 | $6,500.00 | $12,000 | $6,500.00 |
| 31 | Air blast and noise control (208E13000) | LS | 1 | $2,800.00 | $5,000.00 | $3,000.00 | $6,000.00 |
| 32 | Vibration control and monitoring (208E14000) | LS | 1 | $15,000 | $5,000.00 | $20,000 | $17,500 |
| 33 | Presplitting (208E15000) | SY | 8,954 | $25.50 | $38.00 | $40.00 | $25.75 |
| 34 | Hydrologist (208E16000) | LS | 1 | $25,000 | $50,000 | $35,000 | $88,000 |
| 35 | Guardrail, type MGS (606E15050) | FT | 1,603 | $22.75 | $24.00 | $30.00 | $24.00 |
| 36 | Guardrail, type MGS with long posts (606E15100) | FT | 459 | $30.00 | $26.00 | $40.00 | $26.00 |
| 37 | Guardrail rebuilt, type MGS (606E16050) | FT | 56 | $18.50 | $10.00 | $25.00 | $10.00 |
| 38 | Rounded end section (606E20050) | EACH | 2 | $110.00 | $75.00 | $145.00 | $75.00 |
| 39 | Anchor assembly, MGS type A (606E25550) | EACH | 9 | $1,800.00 | $1,750.00 | $2,500.00 | $1,750.00 |
| 40 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,500.00 | $1,450.00 | $2,000.00 | $1,450.00 |
| 41 | Fence, type 47RA, as per plan (607E15101) | FT | 112 | $43.00 | $60.00 | $60.00 | $60.00 |
| 42 | Reference monument, type A (623E40500) | EACH | 38 | $1,000.00 | $1,219.00 | $600.00 | $275.00 |
| 43 | Special - geotextile fabric, 712.09, type A (690E12010) | SY | 2,903 | $3.50 | $1.00 | $2.00 | $6.00 |
| 44 | Special - mailbox removed and reset (690E50350) | EACH | 1 | $200.00 | $250.00 | $500.00 | $185.00 |
| 45 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 413 | $80.00 | $72.00 | $95.00 | $85.00 |
| 46 | Dumped rock fill, type B, as per plan (601E26001) | CY | 8,225 | $38.00 | $114.53 | $51.00 | $101.00 |
| 47 | Dumped rock fill, type C, as per plan (601E27001) | CY | 405 | $22.50 | $158.00 | $51.00 | $405.00 |
| 48 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 18 | $250.00 | $134.00 | $231.00 | $195.00 |
| 49 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 9 | $150.00 | $158.00 | $288.00 | $435.00 |
| 50 | Bioretention cell (601E45050) | CY | 162 | $83.00 | $260.00 | $220.00 | $250.00 |
| 51 | Water (616E10000) | MGAL | 500 | $95.00 | $1.00 | $1.00 | $120.00 |
| 52 | Seeding and mulching (659E10000) | SY | 83,626 | $0.75 | $0.70 | $1.20 | $0.65 |
| 53 | Commercial fertilizer (659E20000) | TON | 11.18 | $1,400.00 | $1,250.00 | $15.00 | $1,250.00 |
| 54 | Lime (659E31000) | ACRE | 17.10 | $165.00 | $150.00 | $20.00 | $150.00 |
| 55 | Water (659E35000) | MGAL | 223.60 | $1.10 | $1.00 | $1.00 | $1.00 |
| 56 | Ditch erosion protection mat, type B (670E00720) | SY | 649 | $2.25 | $2.00 | $2.00 | $2.00 |
| 57 | Erosion control mat, type A (671E15000) | SY | 719 | $2.25 | $2.00 | $2.00 | $2.00 |
| 58 | Storm water pollution prevention plan (832E15000) | LS | 1 | $6,500.00 | $28,500 | $10,000 | $3,500.00 |
| 59 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $18,000 | $14,700 | $30,000 | $17,600 |
| 60 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $17,000 | $15,600 | $16,000 | $15,531 |
| 61 | Erosion control (832E30000) | EACH | 250,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 62 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 535 | $6.50 | $6.00 | $2.00 | $6.00 |
| 63 | Seeding and erosion control with turf reinforcing mat, type 2 (836E10020) | SY | 152 | $6.50 | $6.00 | $10.00 | $6.00 |
| 64 | Concrete masonry (602E20000) | CY | 7.06 | $3,800.00 | $5,536.00 | $3,500.00 | $5,895.00 |
| 65 | 6" unclassified pipe underdrains (605E13300) | FT | 923 | $16.00 | $15.00 | $20.00 | $15.50 |
| 66 | 6" rock cut underdrains (605E13500) | FT | 3,179 | $17.00 | $22.00 | $35.00 | $21.00 |
| 67 | 6" base pipe underdrains (605E14000) | FT | 4,704 | $13.50 | $15.00 | $20.00 | $19.50 |
| 68 | Underdrains, misc.:4" perforated PVC underdrain, 7 (605E98000) | FT | 191 | $34.00 | $38.00 | $40.00 | $35.00 |
| 69 | 4" conduit, type F, as per plan (611E00407) | FT | 35 | $28.00 | $15.00 | $45.00 | $38.00 |
| 70 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 620 | $26.00 | $15.00 | $20.00 | $83.00 |
| 71 | 6" conduit, type E (611E01400) | FT | 1,866 | $18.00 | $11.00 | $6.00 | $17.00 |
| 72 | 12" conduit, type C, as per plan (611E04601) | FT | 100 | $75.00 | $108.00 | $160.00 | $195.00 |
| 73 | 12" conduit, type D (611E04900) | FT | 93 | $69.00 | $114.00 | $200.00 | $108.50 |
| 74 | 18" conduit, type D (611E07900) | FT | 27 | $122.00 | $117.00 | $150.00 | $109.50 |
| 75 | 24" conduit, type A (611E10200) | FT | 64 | $205.00 | $219.00 | $230.00 | $385.00 |
| 76 | 24" conduit, type B (611E10400) | FT | 127 | $206.00 | $158.00 | $200.00 | $385.00 |
| 77 | 24" conduit, type C, as per plan (611E10601) | FT | 37 | $225.00 | $204.00 | $200.00 | $255.00 |
| 78 | 36" conduit, type B (611E16400) | FT | 60 | $370.00 | $292.00 | $350.00 | $490.00 |
| 79 | 36" conduit, type C (611E16600) | FT | 16 | $445.00 | $290.00 | $350.00 | $445.00 |
| 80 | 66" conduit, type A (611E25000) | FT | 208 | $410.00 | $618.00 | $400.00 | $815.00 |
| 81 | Manhole, no. 3 (611E99574) | EACH | 1 | $5,600.00 | $7,977.00 | $5,500.00 | $7,850.00 |
| 82 | Manhole, no. 3, as per plan (611E99575) | EACH | 1 | $7,000.00 | $6,375.00 | $6,500.00 | $7,250.00 |
| 83 | Precast reinforced concrete outlet (611E99710) | EACH | 31 | $330.00 | $327.00 | $350.00 | $475.00 |
| 84 | Low strength mortar backfill (613E41200) | CY | 369 | $225.00 | $196.00 | $180.00 | $200.00 |
| 85 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 2,604 | $270.00 | $247.00 | $325.00 | $247.00 |
| 86 | Aggregate base (304E20000) | CY | 3,863 | $83.00 | $101.00 | $115.00 | $134.00 |
| 87 | Tack coat (407E10000) | GAL | 846 | $2.75 | $2.50 | $4.00 | $2.50 |
| 88 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 658 | $280.00 | $258.00 | $380.00 | $258.00 |
| 89 | Asphalt concrete intermediate course, type 1, (448) (441E50200) | CY | 494 | $320.00 | $292.00 | $375.00 | $292.00 |
| 90 | Compacted aggregate (617E10100) | CY | 240 | $300.00 | $113.00 | $130.00 | $174.00 |
| 91 | RPM (621E00100) | EACH | 131 | $55.00 | $50.00 | $75.00 | $50.00 |
| 92 | Raised pavement marker removed (621E54000) | EACH | 132 | $28.00 | $6.00 | $15.00 | $10.50 |
| 93 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 46 | $45.00 | $13.00 | $20.00 | $10.00 |
| 94 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4 | $80.00 | $25.00 | $100.00 | $12.00 |
| 95 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $265.00 | $250.00 | $100.00 | $75.00 |
| 96 | Edge line, 6", type 1 (642E00104) | MI | 1.97 | $1,200.00 | $1,025.00 | $1,500.00 | $1,025.00 |
| 97 | Center line, type 1 (642E00300) | MI | 0.98 | $1,500.00 | $1,295.00 | $2,000.00 | $1,295.00 |
| 98 | Traffic compacted surface, type B (410E11000) | CY | 27 | $100.00 | $106.00 | $200.00 | $135.00 |
| 99 | Traffic compacted surface, type B, as per plan (410E11001) | CY | 172 | $85.00 | $128.00 | $150.00 | $120.00 |
| 100 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 7 | $3,000.00 | $2,200.00 | $4,000.00 | $2,600.00 |
| 101 | Detour signing (614E12420) | LS | 1 | $7,000.00 | $6,500.00 | $15,000 | $6,500.00 |
| 102 | Work zone lighting system (614E12740) | EACH | 4 | $11,000 | $2,572.00 | $750.00 | $3,600.00 |
| 103 | Asphalt concrete for maintaining traffic (614E13000) | CY | 84 | $380.00 | $321.00 | $300.00 | $500.00 |
| 104 | Barrier reflector, type 1, bidirectional (614E13310) | EACH | 51 | $30.00 | $30.00 | $40.00 | $26.00 |
| 105 | Object marker, two way (614E13360) | EACH | 51 | $35.00 | $32.00 | $45.00 | $32.00 |
| 106 | Work zone edge line, class I, 6" (614E22010) | MI | 1.03 | $1,800.00 | $1,625.00 | $2,358.00 | $1,625.00 |
| 107 | Work zone stop line, class I (614E26000) | FT | 60 | $16.00 | $14.00 | $20.00 | $14.00 |
| 108 | Roads for maintaining traffic (615E10000) | LS | 1 | $30,000 | $13,610 | $80,000 | $80,000 |
| 109 | Pavement for maintaining traffic, class B (615E25000) | SY | 833 | $100.00 | $111.00 | $140.00 | $72.25 |
| 110 | Portable barrier, unanchored (622E41100) | FT | 2,420 | $28.00 | $21.00 | $25.00 | $30.00 |
| 111 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $545.00 | $25,000 | $100.00 | $75,000 |
| 112 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $60,000 | $45,650 | $70,000 | $55,955 |
| 113 | Maintaining traffic (614E11000) | LS | 1 | $250,000 | $227,985 | $450,000 | $140,000 |
| 114 | Field office, type B (619E16010) | MNTH | 18 | $2,500.00 | $2,500.00 | $1,200.00 | $4,840.00 |
| 115 | Construction layout stakes and surveying (623E10000) | LS | 1 | $75,000 | $125,571 | $300,000 | $118,760 |
| 116 | Mobilization (624E10000) | LS | 1 | $200,000 | $300,000 | $500,000 | $635,000 |
| 200 | Renovating existing soil (654E10000) | MSF | 5.10 | $600.00 | $4,722.00 | $1,200.00 | $9,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 23, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.