ODOT contract 260177 bid tabulation
LIC-SR 37-04.09 (INTERSECTION). Let by Ohio DOT on April 9, 2026, LIC. 2 bids received; low bid $1,607,479 by Shelly Company, +6.0% against the engineer's estimate of $1,517,000.
- Owner
- Ohio DOT
- Letting
- 09 APR 2026
- Pay items
- 125
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $1,607,479 | Low | +6.0% |
| 2 | Complete General Construction Company | $1,752,509 | +9.0% | +16% |
Engineer's estimate: $1,517,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. Complete General Construction Company |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $7,500.00 | $2,200.00 |
| 2 | Pavement removed (202E23000) | SY | 252 | $36.00 | $35.00 |
| 3 | Wearing course removed (202E23500) | SY | 1,977 | $6.00 | $6.00 |
| 4 | Walk removed (202E30000) | SF | 1,560 | $2.15 | $4.00 |
| 5 | Curb removed (202E32000) | FT | 23 | $67.75 | $15.00 |
| 6 | Curb and gutter removed (202E32500) | FT | 138 | $22.50 | $18.00 |
| 7 | Pipe removed, 24" and under (202E35100) | FT | 411 | $51.35 | $40.00 |
| 8 | Catch basin removed (202E58100) | EACH | 2 | $730.00 | $450.00 |
| 9 | Excavation (203E10000) | CY | 284 | $76.50 | $60.00 |
| 10 | Embankment (203E20000) | CY | 106 | $44.50 | $30.00 |
| 11 | Subgrade compaction (204E10000) | SY | 382 | $1.50 | $6.00 |
| 12 | Excavation of subgrade (204E13000) | CY | 50 | $100.00 | $59.00 |
| 13 | Granular material, type C (204E30020) | CY | 50 | $85.00 | $79.00 |
| 14 | Proof rolling (204E45000) | HR | 1 | $270.00 | $350.00 |
| 15 | Geotextile fabric (204E50000) | SY | 150 | $2.65 | $5.00 |
| 16 | 4" concrete walk (608E10000) | SF | 1,698 | $14.25 | $16.00 |
| 17 | Curb ramp (608E52000) | SF | 566 | $29.50 | $15.00 |
| 18 | Curb ramp, as per plan (608E52001) | SF | 274 | $34.25 | $30.00 |
| 19 | Detectable warning (608E53020) | SF | 16 | $82.25 | $60.00 |
| 20 | Combination curb and gutter, type 2 (609E12000) | FT | 607 | $50.50 | $46.00 |
| 21 | Right-of-way monument, type B (623E40520) | EACH | 5 | $485.00 | $650.00 |
| 22 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,000.00 | $1,500.00 |
| 23 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,000.00 | $1,500.00 |
| 24 | Special - mailbox removed and reset (690E50350) | EACH | 2 | $300.00 | $285.00 |
| 25 | Topsoil furnished and placed, as per plan (653E10001) | CY | 87 | $105.00 | $40.00 |
| 26 | Soil analysis test (659E00100) | EACH | 2 | $75.00 | $75.00 |
| 27 | Seeding and mulching, class 1 (659E00500) | SY | 775 | $4.92 | $8.70 |
| 28 | Repair seeding and mulching (659E14000) | SY | 37 | $4.00 | $4.00 |
| 29 | Inter-seeding (659E15000) | SY | 37 | $4.00 | $4.00 |
| 30 | Commercial fertilizer (659E20000) | TON | 0.10 | $700.00 | $700.00 |
| 31 | Lime (659E31000) | ACRE | 0.15 | $10.00 | $10.00 |
| 32 | Water (659E35000) | MGAL | 4 | $1.00 | $1.00 |
| 33 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 |
| 34 | 12" conduit, type B, as per plan (611E04401) | FT | 404 | $111.50 | $325.00 |
| 35 | Catch basin, no. 3A (611E98180) | EACH | 2 | $3,375.00 | $5,500.00 |
| 36 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $3,675.00 | $4,600.00 |
| 37 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 6 | $1,160.00 | $1,300.00 |
| 38 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 1 | $3,095.00 | $2,100.00 |
| 39 | Manhole adjusted to grade (611E99654) | EACH | 8 | $1,075.00 | $1,500.00 |
| 40 | Low strength mortar backfill (type 2) (613E41300) | CY | 25 | $340.00 | $215.00 |
| 41 | Full depth pavement sawing (252E01500) | FT | 2,210 | $2.45 | $2.15 |
| 42 | Pavement repair (253E02000) | CY | 100 | $375.00 | $380.00 |
| 43 | Pavement repair (253E02000) | CY | 200 | $375.00 | $381.00 |
| 44 | Pavement repair (253E02000) | CY | 200 | $349.00 | $354.00 |
| 45 | Pavement planing, asphalt concrete, 1.50" (254E01000) | SY | 25,145 | $3.75 | $3.75 |
| 46 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 99 | $256.00 | $256.00 |
| 47 | Aggregate base (304E20000) | CY | 64 | $175.00 | $100.00 |
| 48 | Non-tracking tack coat (407E20000) | GAL | 2,190 | $4.10 | $4.10 |
| 49 | Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100) | CY | 1,049 | $279.00 | $279.00 |
| 50 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 69 | $450.00 | $450.00 |
| 51 | 10" non-reinforced concrete pavement, class QC MS (452E14050) | SY | 26 | $182.00 | $150.00 |
| 52 | Fire hydrant and gate valve removed and reset, as per plan (638E10601) | EACH | 1 | $5,475.00 | $4,500.00 |
| 53 | Valve box adjusted to grade (638E10800) | EACH | 8 | $380.00 | $500.00 |
| 54 | Special - 3/4" polyethylene water service line (CI (638E20768) | FT | 100 | $215.10 | $130.00 |
| 55 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 33 | $20.61 | $40.00 |
| 56 | Sign attachment assembly (630E75000) | EACH | 6 | $856.36 | $875.00 |
| 57 | Sign, flat sheet (630E80100) | SF | 10 | $24.05 | $45.00 |
| 58 | Sign, street name (630E80510) | EACH | 6 | $292.72 | $195.00 |
| 59 | Removal of ground mounted sign and disposal (630E84900) | EACH | 5 | $17.02 | $15.00 |
| 60 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $88.93 | $70.00 |
| 61 | Removal of ground mounted post support and disposal (630E86002) | EACH | 6 | $22.70 | $20.00 |
| 62 | Edge line, 6" (644E00104) | MI | 1.05 | $6,690.00 | $6,690.00 |
| 63 | Center line (644E00300) | MI | 1.48 | $6,580.00 | $6,580.00 |
| 64 | Channelizing line, 8" (644E00400) | FT | 536 | $2.65 | $2.65 |
| 65 | Stop line (644E00500) | FT | 298 | $8.50 | $8.50 |
| 66 | Crosswalk line, 12" (644E00620) | FT | 1,771 | $5.00 | $5.00 |
| 67 | Transverse/diagonal line (644E00700) | FT | 253 | $8.80 | $8.80 |
| 68 | School symbol marking, 96" (644E01110) | EACH | 2 | $860.00 | $860.00 |
| 69 | Parking lot stall marking (644E01200) | FT | 724 | $2.95 | $2.95 |
| 70 | Lane arrow (644E01300) | EACH | 11 | $100.00 | $100.00 |
| 71 | Word on pavement, 96" (644E01410) | EACH | 3 | $155.00 | $155.00 |
| 72 | Yield line (644E20800) | FT | 110 | $11.55 | $11.55 |
| 73 | Connection, fused pull apart (625E00450) | EACH | 2 | $160.00 | $160.00 |
| 74 | Connection, unfused pull apart (625E00460) | EACH | 2 | $160.00 | $160.00 |
| 75 | Conduit, 2", 725.04 (625E25400) | FT | 129 | $37.00 | $37.00 |
| 76 | Conduit, 3", 725.04 (625E25500) | FT | 56 | $50.00 | $50.00 |
| 77 | Conduit, 4", 725.04 (625E25600) | FT | 19 | $87.00 | $87.00 |
| 78 | Conduit, jacked or drilled, 725.04, 4" (625E25902) | FT | 357 | $90.00 | $90.00 |
| 79 | Trench, 24" deep (625E29002) | FT | 147 | $18.00 | $18.00 |
| 80 | Pull box, 725.08, 24" (625E30706) | EACH | 4 | $1,650.00 | $1,650.00 |
| 81 | Ground rod (625E32000) | EACH | 8 | $300.00 | $300.00 |
| 82 | Arc flash calculations and label (S.R. 37/leafy DE (625E76000) | EACH | 1 | $3,500.00 | $3,500.00 |
| 83 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate, as per plan (632E05007) | EACH | 6 | $1,150.00 | $1,150.00 |
| 84 | Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate, as per plan (632E05087) | EACH | 2 | $1,900.00 | $1,900.00 |
| 85 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 8 | $650.00 | $650.00 |
| 86 | Covering of vehicular signal head, as per plan (632E25001) | EACH | 8 | $40.00 | $40.00 |
| 87 | Pedestrian pushbutton, as per plan (632E26001) | EACH | 8 | $425.00 | $425.00 |
| 88 | Signal cable, 2 conductor, no. 14 AWG (632E40200) | FT | 1,101 | $2.60 | $2.60 |
| 89 | Signal cable, 4 conductor, no. 14 AWG (632E40400) | FT | 314 | $3.60 | $3.60 |
| 90 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 1,559 | $3.25 | $3.25 |
| 91 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 374 | $4.00 | $4.00 |
| 92 | Signal support foundation (632E64010) | EACH | 2 | $18,000 | $18,000 |
| 93 | Pedestal foundation (632E64020) | EACH | 5 | $1,500.00 | $1,500.00 |
| 94 | Test hole performed, as per plan (632E64951) | EACH | 2 | $2,750.00 | $2,750.00 |
| 95 | Power cable, 3 conductor, no. 8 AWG (632E67300) | FT | 170 | $6.25 | $6.25 |
| 96 | Power service, as per plan (632E70001) | EACH | 1 | $4,250.00 | $4,250.00 |
| 97 | Pedestal, 10', transformer base, as per plan (632E89905) | EACH | 5 | $1,250.00 | $1,250.00 |
| 98 | Cabinet, type TS-2, as per plan (633E65511) | EACH | 1 | $26,000 | $26,000 |
| 99 | Cabinet foundation, as per plan (633E67101) | EACH | 1 | $6,000.00 | $6,000.00 |
| 100 | Controller work pad, as per plan (633E67201) | EACH | 1 | $3,500.00 | $3,500.00 |
| 101 | Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001) | EACH | 1 | $9,000.00 | $9,000.00 |
| 102 | ITS device, misc.: high speed ethernet radio (iter (809E65990) | EACH | 1 | $6,000.00 | $6,000.00 |
| 103 | Atc controller, as per plan (809E69123) | EACH | 1 | $5,500.00 | $5,500.00 |
| 104 | Video detection system, as per plan (816E30001) | EACH | 1 | $45,000 | $45,000 |
| 108 | Bracket arm, 8', as per plan (625E17961) | EACH | 2 | $1,000.00 | $1,000.00 |
| 109 | Luminaire, teardrop, solid state (LED), as per plan (625E27507) | EACH | 2 | $2,000.00 | $2,000.00 |
| 110 | Combination signal support, type TC-12.31, design 10, as per plan (632E78111) | EACH | 2 | $36,000 | $36,000 |
| 111 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 350 | $80.00 | $90.00 |
| 112 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 2 | $2,145.28 | $3,300.00 |
| 113 | Work zone marking sign (614E12460) | EACH | 8 | $100.00 | $100.00 |
| 114 | Barrier reflector, type 2 (bidirectional) (614E13312) | EACH | 8 | $50.00 | $28.42 |
| 115 | Object marker, two way (614E13360) | EACH | 8 | $50.00 | $36.00 |
| 116 | Portable changeable message sign, as per plan (614E18601) | SNMT | 9 | $1,700.00 | $1,050.00 |
| 117 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.30 | $3,000.00 | $12,250 |
| 118 | Work zone center line, class III, 642 paint (614E21550) | MI | 1.35 | $1,650.00 | $6,325.00 |
| 119 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.60 | $1,800.00 | $13,995 |
| 120 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 523 | $1.15 | $2.50 |
| 121 | Work zone stop line, class III, 642 paint (614E26610) | FT | 134 | $3.50 | $10.00 |
| 122 | Water (616E10000) | MGAL | 9 | $1.00 | $900.00 |
| 123 | Portable barrier, unanchored (622E41100) | FT | 390 | $41.26 | $40.00 |
| 124 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,500.00 | $12,000 |
| 125 | Maintaining traffic (614E11000) | LS | 1 | $90,000 | $56,000 |
| 126 | Field office, type C (619E16020) | MNTH | 18 | $2,000.00 | $3,700.00 |
| 127 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,500.00 | $40,000 |
| 128 | Mobilization (624E10000) | LS | 1 | $50,000 | $85,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.