TDOT contract CNZ092 bid tabulation
The resurfacing (either microsurface or thin lift overlay) on s.r. 13 from west of jim johnson road (l.m. 28.67) to the kentucky state line (l.m. 31.99). Let by Tennessee DOT on March 21, 2025, Montgomery County. 3 bids received; low bid $744,519 by Eubank Asphalt Paving & Sealing, LLC.
- Owner
- Tennessee DOT
- Letting
- 21 MAR 2025
- Pay items
- 38
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Eubank Asphalt Paving & Sealing, LLC | $744,519 | Low |
| 2 | Vulcan Construction Materials, LLC | $813,900 | +9.0% |
| 3 | Jones Bros. Contractors, LLC | $838,611 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eubank Asphalt Paving & Sealing, LLC | 2. Vulcan Construction Materials, LLC | 3. Jones Bros. Contractors, LLC |
|---|---|---|---|---|---|---|
| 1 | Brooming & degrassing shoulders (208-01.05) | LM | 6.60 | $1,000.00 | $1,200.00 | $1,500.00 |
| 2 | Mineral aggregate, type A base, grading D (303-01) | TON | 794 | $38.00 | $45.00 | $36.00 |
| 3 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 93 | $100.00 | $235.00 | $245.00 |
| 4 | Scoring for rumble stripe (non-continuous) (8IN width) (411-12.03) | LM | 5.10 | $700.00 | $1,875.00 | $1,875.00 |
| 5 | Scoring for rumble stripe (non-continuous) (4IN width) (411-12.04) | LM | 0.20 | $700.00 | $1,875.00 | $1,875.00 |
| 6 | Cold planing bituminous pavement (415-01.01) | TON | 47 | $85.00 | $325.00 | $331.00 |
| 7 | Guardrail transition 27IN to 31IN (705-02.10) | EACH | 1 | $210.00 | $200.00 | $210.00 |
| 8 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 1 | $4,833.00 | $4,000.00 | $4,833.00 |
| 9 | Guardrail removed (706-01) | LF | 50 | $2.50 | $3.00 | $2.50 |
| 10 | Traffic control (712-01) | LS | 1 | $7,500.00 | $24,000 | $35,000 |
| 11 | Flexible drums (channelizing) (712-04.01) | EACH | 135 | $5.00 | $40.00 | $36.00 |
| 12 | Signs (construction) (712-06) | SF | 744 | $7.50 | $8.50 | $7.90 |
| 13 | Sign post delineation enhancement (713-02.21) | LF | 10 | $53.84 | $7.50 | $8.00 |
| 14 | Remove and replace sign (W10-1) (713-16.50) | EACH | 2 | $336.00 | $315.00 | $320.00 |
| 15 | Remove and replace sign (TN-17B) (713-16.51) | EACH | 2 | $336.00 | $175.00 | $225.00 |
| 16 | Remove and replace sign (TN-7A) (713-16.52) | EACH | 1 | $311.00 | $350.00 | $235.00 |
| 17 | Remove and replace sign (TN-13) (713-16.53) | EACH | 1 | $311.00 | $275.00 | $260.00 |
| 18 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 214 | $30.00 | $32.00 | $32.00 |
| 19 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 34 | $30.00 | $32.00 | $32.00 |
| 20 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 63 | $35.00 | $25.00 | $25.00 |
| 21 | Plastic pavement marking (stop line) (716-02.05) | LF | 102 | $20.00 | $25.00 | $25.00 |
| 22 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 5 | $225.00 | $250.00 | $250.00 |
| 23 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 153 | $2.00 | $4.00 | $4.00 |
| 24 | Plastic pavement marking (8IN line) (716-02.12) | LM | 0.10 | $15,000 | $15,000 | $15,000 |
| 25 | Plastic word pavement marking (RXR) (716-03.02) | EACH | 2 | $600.00 | $700.00 | $700.00 |
| 26 | Painted pavement marking (4" line) (716-05.01) | LM | 23.40 | $1,400.00 | $1,200.00 | $1,200.00 |
| 27 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 11.70 | $7,200.00 | $7,200.00 | $7,200.00 |
| 28 | Mobilization (717-01) | LS | 1 | $18,000 | $35,000 | $35,000 |
| 29 | Bituminous material (BSC) (405-01.01) | TON | 88 | $1,325.00 | $850.00 | $1,167.20 |
| 30 | Mineral aggregate (BSC) (405-01.02) | TON | 771 | $65.00 | $110.00 | $59.15 |
| 31 | Removal of pavement marking (channelization striping) (716-08.04) | SY | 515 | $10.00 | $12.00 | $12.00 |
| 32 | Removal of pavement marking (stop line) (716-08.05) | LF | 102 | $10.00 | $10.00 | $10.00 |
| 33 | Removal of pavement marking (turn lane arrow) (716-08.06) | EACH | 5 | $85.00 | $100.00 | $100.00 |
| 34 | Removal of pavement marking (dotted line) (716-08.09) | LF | 528 | $1.75 | $2.00 | $2.00 |
| 35 | Removal of word pavement marking (RXR) (716-08.11) | EACH | 2 | $300.00 | $300.00 | $300.00 |
| 36 | Removal of pavement marking (line) (716-08.20) | LM | 11.70 | $3,000.00 | $5,000.00 | $5,000.00 |
| 37 | Bituminous material for tack coat (TC) (403-01) | TON | 21 | $300.00 | $900.00 | $795.00 |
| 38 | Acs mix(PG64-22) thin lift D asphalt (411-03.12) | TON | 2,239 | $135.00 | $121.00 | $135.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of March 21, 2025. Compiled by Mirage Metrics.