TDOT contract CNZ186 bid tabulation
The repair of the bridge on i-75 over branch (l.m. 4.13). Let by Tennessee DOT on June 27, 2025, Hamilton County. 4 bids received; low bid $1,222,732 by Wright Brothers Civil Construction, LLC.
- Owner
- Tennessee DOT
- Letting
- 27 JUN 2025
- Pay items
- 41
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Wright Brothers Civil Construction, LLC | $1,222,732 | Low |
| 2 | Mid-State Construction Company, Inc. | $1,364,087 | +12% |
| 3 | Dement Construction Group, LLC | $1,918,438 | +57% |
| 4 | Southern Constructors, Inc. | $2,318,500 | +90% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Wright Brothers Civil Construction, LLC | 2. Mid-State Construction Company, Inc. | 3. Dement Construction Group, LLC | 4. Southern Constructors, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $4,500.00 | $25,088 | $5,000.00 | $75,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $98,000 | $15,397 | $200,000 | $80,000 |
| 3 | Removal of asphalt pavement (202-03.01) | SY | 1,643 | $17.00 | $18.87 | $30.00 | $32.00 |
| 4 | Road & drainage excavation (unclassified) (203-01) | CY | 548 | $123.00 | $55.35 | $50.00 | $100.00 |
| 5 | Borrow excavation (unclassified) (203-03) | CY | 548 | $102.00 | $146.04 | $40.00 | $100.00 |
| 6 | Sediment removal (209-05) | CY | 17 | $35.00 | $39.00 | $100.00 | $80.00 |
| 7 | Temporary silt fence (with backing) (209-08.02) | LF | 1,538 | $5.25 | $6.11 | $4.70 | $10.00 |
| 8 | Enhanced rock check dam (209-08.08) | EACH | 2 | $1,675.00 | $1,950.00 | $700.00 | $2,000.00 |
| 9 | Sediment filter bag(15' X 10') (209-09.04) | EACH | 1 | $925.00 | $971.75 | $1,000.00 | $1,500.00 |
| 10 | Temporary in stream diversion (209-65.04) | LF | 150 | $335.00 | $181.92 | $60.00 | $500.00 |
| 11 | Mineral aggregate, type A base, grading D (303-01) | TON | 371 | $51.00 | $90.00 | $75.00 | $85.00 |
| 12 | Mineral aggregate (size 57) (303-10.01) | TON | 8 | $70.00 | $70.75 | $250.00 | $85.00 |
| 13 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 163 | $178.00 | $178.00 | $300.00 | $325.00 |
| 14 | Bituminous material for prime coat (PC) (402-01) | TON | 3 | $1,050.00 | $1,050.00 | $1,500.00 | $1,750.00 |
| 15 | Aggregate for cover material (PC) (402-02) | TON | 9 | $200.00 | $200.00 | $100.00 | $125.00 |
| 16 | Bituminous material for tack coat (TC) (403-01) | TON | 2 | $1,025.00 | $1,025.00 | $1,500.00 | $1,250.00 |
| 17 | Acs mix(PG64-22) grading D (411-01.10) | TON | 109 | $240.00 | $240.00 | $350.00 | $375.00 |
| 18 | Bracing repairs (602-10.05) | LS | 1 | $1.00 | $65,526 | $50,000 | $75,000 |
| 19 | Class A concrete (box bridges) (604-02.01) | CY | 41 | $3,125.00 | $5,265.84 | $10,000 | $4,500.00 |
| 20 | Steel bar reinforcement (box bridges) (604-02.02) | LB | 5,271 | $13.45 | $4.10 | $7.00 | $10.00 |
| 21 | Concrete (604-10.05) | SF | 480 | $315.00 | $375.00 | $400.00 | $450.00 |
| 22 | Concrete repairs (604-10.54) | SF | 480 | $280.00 | $375.00 | $400.00 | $450.00 |
| 23 | Earth pad for type 38 GR end treatment (705-04.09) | EACH | 2 | $880.00 | $1,040.00 | $800.00 | $2,000.00 |
| 24 | W beam GR (type 2) MASH TL-3 (705-06.01) | LF | 275 | $32.00 | $39.00 | $30.00 | $45.00 |
| 25 | GR terminaltrailing end (type 13) MASH TL-3 (705-06.10) | EACH | 2 | $1,850.00 | $2,177.50 | $1,675.00 | $2,250.00 |
| 26 | Tangent energy absorbing term MASH TL-3 (705-06.20) | EACH | 2 | $3,750.00 | $4,420.00 | $3,400.00 | $5,000.00 |
| 27 | Guardrail removed (706-01) | LF | 385 | $0.55 | $0.65 | $0.50 | $15.00 |
| 28 | High-visibility construction fence (707-08.11) | LF | 1,400 | $2.80 | $3.25 | $2.50 | $8.00 |
| 29 | Traffic control (712-01) | LS | 1 | $90,000 | $87,259 | $196,281 | $310,000 |
| 30 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 1,540 | $46.00 | $63.90 | $100.00 | $75.00 |
| 31 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 1 | $11,400 | $9,912.50 | $7,625.00 | $11,500 |
| 32 | Flexible drums (channelizing) (712-04.01) | EACH | 50 | $44.50 | $40.30 | $31.00 | $50.00 |
| 33 | Signs (construction) (712-06) | SF | 101 | $8.75 | $9.75 | $7.50 | $25.00 |
| 34 | Arrow board (type C) (712-08.03) | EACH | 1 | $2,000.00 | $1,690.00 | $1,300.00 | $3,000.00 |
| 35 | Plastic pavement marking (24" barrier line) (716-02.07) | LF | 200 | $16.50 | $19.50 | $15.00 | $40.00 |
| 36 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 0.50 | $13,750 | $15,275 | $12,500 | $12,000 |
| 37 | Mobilization (717-01) | LS | 1 | $122,000 | $132,952 | $190,000 | $508,109 |
| 38 | Geotextile (type III)(erosion control) (740-10.03) | SY | 80 | $9.00 | $16.25 | $10.00 | $35.00 |
| 39 | Temporary seeding (with mulch) (801-01.07) | UNIT | 19 | $54.00 | $63.05 | $48.50 | $150.00 |
| 40 | Natve seed MX final stablizatn of slopes (801-01.38) | UNIT | 19 | $111.00 | $130.00 | $100.00 | $200.00 |
| 41 | Water (seeding & sodding) (801-03) | MG | 2 | $130.00 | $162.50 | $125.00 | $250.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of June 27, 2025. Compiled by Mirage Metrics.