TDOT contract CNZ315 bid tabulation
The resurfacing (either microsurface or thin mix overlay) on s.r. 96 from near cox road (l.m. 20.62) to the rutherford county line (l.m. 26.94), including bridge deck repairs. Let by Tennessee DOT on December 5, 2025, Williamson County. 6 bids received; low bid $1,497,528 by Eubank Asphalt Paving & Sealing, LLC.
- Owner
- Tennessee DOT
- Letting
- 05 DEC 2025
- Pay items
- 39
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Eubank Asphalt Paving & Sealing, LLC | $1,497,528 | Low |
| 2 | Asphalt Paving Systems, Inc. | $1,534,329 | +2.0% |
| 3 | Vulcan Construction Materials, LLC | $1,698,227 | +13% |
| 4 | Wiregrass Construction Company, Inc | $1,812,469 | +21% |
| 5 | Rogers Group, Inc. | $1,889,073 | +26% |
| 6 | Jones Bros. Contractors, LLC | $1,935,156 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eubank Asphalt Paving & Sealing, LLC | 2. Asphalt Paving Systems, Inc. | 3. Vulcan Construction Materials, LLC | 4. Wiregrass Construction Company, Inc | 5. Rogers Group, Inc. | 6. Jones Bros. Contractors, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Brooming & degrassing shoulders (208-01.05) | LM | 11.80 | $1,100.00 | $1,260.00 | $3,040.00 | $1,950.00 | $2,400.00 | $2,800.00 |
| 2 | Mineral aggregate, type A base, grading D (303-01) | TON | 1,538 | $25.00 | $75.60 | $48.30 | $61.50 | $35.00 | $54.00 |
| 3 | Asphalt concrete mix (PG70-22) (BPMB-HM) grading B-M (307-02.07) | TON | 600 | $110.00 | $250.00 | $135.00 | $190.00 | $160.00 | $165.00 |
| 4 | Bituminous material (BSC) (405-01.01) | TON | 147 | $950.00 | $1,015.10 | $1,060.00 | $1,020.57 | $1,000.00 | $1,015.00 |
| 5 | Mineral aggregate (BSC) (405-01.02) | TON | 1,314 | $40.00 | $54.80 | $35.40 | $55.10 | $65.00 | $54.80 |
| 6 | Scoring for rumble stripe (non-continuous) (4IN width) (411-12.04) | LM | 4.30 | $800.00 | $708.75 | $675.00 | $678.64 | $700.00 | $2,200.00 |
| 7 | Shoulder mumble strip (non-continuous) (8IN width) (411-12.10) | LM | 1.40 | $1,200.00 | $708.75 | $675.00 | $678.64 | $700.00 | $2,200.00 |
| 8 | Edge line mumble stripe (non-continuous) (8IN width) (411-12.11) | LM | 3.80 | $1,200.00 | $708.75 | $675.00 | $678.64 | $700.00 | $2,200.00 |
| 9 | Traffic control (712-01) | LS | 1 | $22,500 | $21,683 | $49,200 | $60,000 | $95,000 | $100,000 |
| 10 | Flexible drums (channelizing) (712-04.01) | EACH | 70 | $1.00 | $26.25 | $37.50 | $31.17 | $26.00 | $31.00 |
| 11 | Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21) | EACH | 605 | $30.00 | $42.00 | $50.00 | $40.22 | $41.25 | $40.00 |
| 12 | Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22) | EACH | 77 | $30.00 | $42.00 | $50.00 | $40.22 | $41.25 | $40.00 |
| 13 | Removal of snowplowable reflective marker (716-01.30) | EACH | 400 | $13.00 | $15.75 | $10.00 | $15.08 | $15.50 | $15.00 |
| 14 | Plastic pavement marking(channelization striping) (716-02.04) | SY | 202 | $35.00 | $36.75 | $35.00 | $35.19 | $36.00 | $35.00 |
| 15 | Plastic pavement marking (stop line) (716-02.05) | LF | 205 | $22.00 | $26.25 | $25.00 | $25.13 | $26.00 | $25.00 |
| 16 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 17 | $225.00 | $262.50 | $250.00 | $251.35 | $260.00 | $250.00 |
| 17 | Plastic pavement marking (8" dotted line) (716-02.08) | LF | 389 | $3.75 | $4.20 | $4.00 | $4.02 | $4.15 | $4.00 |
| 18 | Plastic pavement marking (6" dotted line) (716-02.11) | LF | 131 | $2.00 | $3.15 | $2.00 | $3.02 | $3.10 | $3.00 |
| 19 | Plastic pavement marking (8IN line) (716-02.12) | LM | 0.30 | $10,000 | $1,575.00 | $12,500 | $15,081 | $15,500 | $15,000 |
| 20 | Plastic pavement marking (lane reduction arrow) (716-04.14) | EACH | 1 | $550.00 | $735.00 | $550.00 | $703.77 | $725.00 | $700.00 |
| 21 | Painted pavement marking (6" line) (716-05.20) | LM | 46.60 | $910.00 | $1,890.00 | $1,500.00 | $1,809.70 | $1,900.00 | $1,800.00 |
| 22 | Removal of pavement marking (channelization striping) (716-08.04) | SY | 202 | $15.00 | $26.25 | $20.00 | $25.13 | $25.75 | $25.00 |
| 23 | Removal of pavement marking (stop line) (716-08.05) | LF | 205 | $8.00 | $10.50 | $10.00 | $10.05 | $10.30 | $10.00 |
| 24 | Removal of pavement marking (turn lane arrow) (716-08.06) | EACH | 17 | $50.00 | $105.00 | $75.00 | $100.54 | $103.00 | $100.00 |
| 25 | Removal of pavement marking (dotted line) (716-08.09) | LF | 520 | $0.75 | $1.05 | $1.00 | $1.01 | $1.00 | $1.00 |
| 26 | Removal of pavement marking (line) (716-08.20) | LM | 23.30 | $1,800.00 | $2,310.00 | $4,000.00 | $2,211.86 | $2,270.00 | $2,200.00 |
| 27 | Contrast pavement marking 6" (716-09.83) | LF | 1,380 | $8.00 | $4.20 | $8.00 | $4.02 | $4.15 | $4.00 |
| 28 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 23.30 | $6,700.00 | $8,400.00 | $7,200.00 | $8,043.12 | $8,300.00 | $8,000.00 |
| 29 | Mobilization (717-01) | LS | 1 | $45,000 | $63,585 | $19,000 | $60,000 | $125,000 | $125,000 |
| 30 | Expansion joint repairs (604-10.44) | LF | 108 | $325.00 | $609.00 | $318.00 | $484.60 | $610.00 | $580.00 |
| 31 | Bridge deck repairs (partial depth of slab) (604-10.50) | SY | 10 | $1,300.00 | $840.00 | $1,264.00 | $866.65 | $840.00 | $800.00 |
| 32 | Concrete repairs (604-10.53) | SY | 15 | $1,300.00 | $945.00 | $1,264.00 | $866.65 | $945.00 | $900.00 |
| 33 | Bituminous material for tack coat (micro-surfacing) (403-01.01) | TON | 15 | $903.73 | |||||
| 34 | Emulsified asphalt for micro-surfacing (414-03.01) | TON | 162 | $1,300.35 | |||||
| 35 | Aggregate for micro surfacing (414-03.02) | TON | 1,343 | $156.85 | |||||
| 36 | Signs (construction) (712-06) | SF | 744 | $8.40 | |||||
| 37 | Bituminous material for tack coat (TC) (403-01) | TON | 36 | $400.00 | $1,090.00 | $1,150.00 | $960.00 | $785.00 | |
| 38 | Acs mix(PG70-22) thin lift asphalt (411-03.08) | TON | 4,752 | $151.00 | $148.00 | $149.50 | $149.00 | $155.00 | |
| 39 | Signs (construction) (712-06) | SF | 1,224 | $6.00 | $7.00 | $7.04 | $8.25 | $7.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of December 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.