NBG Constructors, Inc.: TxDOT bid record
NBG Constructors, Inc. submitted 15 bids on Texas DOT contracts in the data, from 13 MAR 2020 to 28 JUN 2023, and was the low bidder on 5 of them (33%). When it was not low, its total sat a median +16% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $20,046,279
- Latest bid
- 28 JUN 2023
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 3 | 0 | 0% |
| 2021 | 6 | 1 | 17% |
| 2022 | 3 | 2 | 67% |
| 2023 | 3 | 2 | 67% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Houston District | 14 | 4 | 29% |
| Yoakum District | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Cem stabil BKFL | 400-7010 | CY | 10 | 5 (50%) | $72.50 | $200.00 |
| Excavation (roadway) | 110-7001 | CY | 9 | 5 (56%) | $12.00 | $20.00 |
| Barricades, signs and traffic handling | 502-7001 | MO | 15 | 4 (27%) | $3,000.00 | $5,000.00 |
| TMA (stationary) | 505-7001 | DAY | 10 | 4 (40%) | $175.00 | $230.00 |
| Temporary sediment control fence (remove) | 506-7041 | LF | 8 | 4 (50%) | $0.60 | $1.00 |
| Removing concrete (riprap) | 104-7006 | SY | 6 | 4 (67%) | $11.00 | $25.00 |
| Install delineator assembly (D-SW)SZ (BRF)CTB (BI) | 658-6014 | EACH | 5 | 4 (80%) | $22.00 | $25.00 |
| Removing structure (bridge 100 - 499 FT length) | 496-7010 | EACH | 5 | 4 (80%) | $125,000 | $95,000 |
| Block sodding | 162-7002 | SY | 9 | 3 (33%) | $4.50 | $6.20 |
| Portable concrete traffic barrier (move)(single slope)(type 1) | 512-7025 | LF | 7 | 3 (43%) | $8.00 | $11.00 |
| Biodegradable erosion control logs (remove) | 506-7046 | LF | 5 | 3 (60%) | $1.00 | $1.40 |
| Portable changeable message sign | 503-7001 | DAY | 9 | 2 (22%) | $60.00 | $100.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Ragle Construction, Inc. | 9 | 4 of 9 |
| Isi Contracting, Inc. | 7 | 6 of 7 |
| Harper Brothers Construction LLC | 5 | 4 of 5 |
| James Construction Group, LLC | 5 | 3 of 5 |
| Forde Construction Company, Inc. | 4 | 1 of 4 |
| SCR Civil Construction, LLC | 4 | 3 of 4 |
| Southern Road & Bridge, LLC | 3 | 0 of 3 |
| Main Lane Industries LTD. | 3 | 2 of 3 |
| Sefbo Pipeline Bridge, Incorporated | 3 | 1 of 3 |
| R Construction Civil, LLC | 2 | 1 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 28 JUN 2023 | 06233617 | Houston District | FM 2403 Bridge replacement from AT DRAINAGE DITCH | 5 of 7 | $7,027,379 | +16% |
| 28 JUN 2023 | 06233641 | Houston District | CS Bridge replacement from BACA STREET AT HCFCD DITCH | 1 of 3 | $824,264 | Low, 7.0% under the second |
| 09 MAR 2023 | 03231201 | Houston District | SL0008 Concrete structure repair from PRESIDENTS DRIVE to FM 865 (CULLEN BLVD) | 1 of 5 | $87,820 | Low, 22% under the second |
| 08 SEP 2022 | 09223211 | Houston District | IH 69 Bridge replacement from AT OYSTER CREEK | 1 of 5 | $5,893,967 | Low, 15% under the second |
| 03 AUG 2022 | 08223020 | Houston District | IH 610 Bridge replacement from IH 610 SB FRONTAGE RD AT BRAYS BAYO | 2 of 3 | $3,277,738 | +5.0% |
| 04 FEB 2022 | 02223203 | Yoakum District | FM 109 Bridge replacement from AT CUMMINS CR. & CUMMINS CR. RELIEF to STR # 0716-02-015 & 016 | 1 of 3 | $6,985,517 | Low, 5.0% under the second |
| 03 NOV 2021 | 11213005 | Houston District | IH 10 Construct pedestrian infrastructure from AT POST OAK RD | 1 of 2 | $6,254,712 | Low, 10% under the second |
| 08 OCT 2021 | 10213206 | Houston District | CS Replace bridge & approaches from HILLCROFT AVE SB to AT WILLOW WATERHOLE BAYOU | 3 of 4 | $3,380,387 | +3.0% |
| 03 JUN 2021 | 06213014 | Houston District | VA Highway improvement from VARIOUS LOCATIONS | 6 of 8 | $3,197,347 | +34% |
| 04 MAR 2021 | 03213030 | Houston District | FM 518 Bridge repairs from AT CHIGGER CREEK & COWART CREEK | 4 of 8 | $2,193,242 | +15% |
| 08 JAN 2021 | 01213203 | Houston District | FM 2611 Replace bridge and approaches from AT SAN BERNARD | 8 of 9 | $16,185,965 | +33% |
| 07 JAN 2021 | 01213022 | Houston District | IH 610 Rehabilitate bridge from IH 610, AT HOLMES RD/UPRR BRIDGE | 4 of 10 | $968,619 | +50% |
| 03 SEP 2020 | 09203012 | Houston District | FM 1314 Construct drainage culverts&replace concrete pvmn from 0.125 MILES SOUTH OF CALHOUN RD to 0.528 MILES SOUTH OF CALHOUN RD | 10 of 13 | $4,310,307 | +28% |
| 03 SEP 2020 | 09203030 | Houston District | FM 2759 Construct noise barrier from MIDDLE BAYOU TO SANSBURY BLVD | 8 of 13 | $1,434,185 | +12% |
| 13 MAR 2020 | 03201204 | Houston District | IH0010 Repair steel bridge members from HOUSTON AVE BRIDGE to OVER IH-10 EB | 3 of 5 | $193,518 | +11% |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.