TxDOT contract A00036817 bid tabulation
Bridge Replacement, COUNTY ROAD 218 (CR 218 OVER DUFFAU CREEK to .). Let by Texas DOT on February 4, 2026, Erath, Fort Worth District. 9 bids received; low bid $976,095 by THK Construction LLC, -20% against the engineer's estimate of $1,213,920.
- Owner
- Texas DOT
- Letting
- 04 FEB 2026
- Pay items
- 46
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | THK Construction LLC | $976,095 | Low | -20% |
| 2 | Hodges and Son Construction Company, Inc. | $1,003,230 | +3.0% | -17% |
| 3 | Knife River Corporation - South | $1,050,910 | +8.0% | -13% |
| 4 | Scott Tucker Construction Company, LLC | $1,163,366 | +19% | -4.0% |
| 5 | Tucan Contracting, LLC | $1,180,895 | +21% | -3.0% |
| 6 | STX Civil | $1,183,795 | +21% | -2.0% |
| 7 | Garret Shields Infrastructure | $1,244,174 | +27% | +2.0% |
| 8 | Coppell Construction Co., Inc. | $1,510,353 | +55% | +24% |
| 9 | Castillo Aranda LLC | $1,684,605 | +73% | +39% |
Engineer's estimate: $1,213,920.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. THK Construction LLC | 2. Hodges and Son Construction Company, Inc. | 3. Knife River Corporation - South | 4. Scott Tucker Construction Company, LLC | 5. Tucan Contracting, LLC | 6. STX Civil |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 3.95 | $5,000.00 | $7,800.00 | $5,000.00 | $7,850.00 | $5,307.00 | $8,800.00 | $8,000.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 34 | $75.00 | $25.00 | $50.00 | $85.00 | $47.00 | $88.00 | $40.00 |
| 3 | Embankment (final)(DC)(type C2) (132-7010) | CY | 426 | $70.00 | $20.00 | $50.00 | $42.00 | $98.00 | $49.50 | $45.00 |
| 4 | Embankment (final)(DC)(type D) (132-7012) | CY | 34 | $66.00 | $25.00 | $50.00 | $25.00 | $47.00 | $49.50 | $45.00 |
| 5 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 178 | $2.50 | $9.01 | $20.00 | $8.50 | $7.00 | $1.43 | $0.35 |
| 6 | Straw/hay mulch seed (temporary_warm) (164-7029) | SY | 89 | $4.00 | $21.50 | $20.00 | $21.00 | $16.00 | $1.44 | $0.50 |
| 7 | Straw/hay mulch seed (temporary_cool) (164-7030) | SY | 89 | $4.00 | $21.50 | $20.00 | $10.00 | $16.00 | $1.72 | $0.50 |
| 8 | Vegetative watering (168-7001) | TGL | 13 | $400.00 | $10.00 | $1.00 | $85.00 | $711.00 | $126.50 | $75.00 |
| 9 | Soil ret BLKT(chan_temporary_4 PSF) (169-7030) | SY | 137 | $6.00 | $5.38 | $5.00 | $5.50 | $11.00 | $3.44 | $5.00 |
| 10 | FL BS (roadway del)(type A GR 1-2)(final pos) (247-7259) | CY | 73 | $150.00 | $138.00 | $250.00 | $130.00 | $210.00 | $66.00 | $100.00 |
| 11 | Cement (275-7001) | TON | 9 | $550.00 | $400.00 | $350.00 | $430.00 | $585.00 | $429.00 | $350.00 |
| 12 | Cement TRT (existing material & new base)(8") (275-7007) | SY | 598 | $15.00 | $40.00 | $20.00 | $6.50 | $40.00 | $27.50 | $10.00 |
| 13 | Cem stabil BKFL (400-7010) | CY | 48 | $370.00 | $367.00 | $300.00 | $375.00 | $235.00 | $275.00 | $250.00 |
| 14 | Drilled shaft (24 in) (416-7004) | LF | 162 | $300.00 | $355.54 | $280.00 | $395.00 | $409.00 | $418.00 | $300.00 |
| 15 | Class C concrete (abutment)(HPC) (420-7013) | CY | 18.60 | $1,600.00 | $1,100.00 | $1,500.00 | $2,400.00 | $2,749.00 | $1,210.00 | $1,000.00 |
| 16 | Class C concrete (cap)(HPC) (420-7023) | CY | 13.20 | $1,850.00 | $1,500.00 | $2,200.00 | $2,500.00 | $3,141.00 | $1,540.00 | $2,450.00 |
| 17 | Class C concrete (column)(HPC) (420-7039) | CY | 8 | $2,050.00 | $1,500.00 | $2,200.00 | $2,500.00 | $2,813.00 | $1,485.00 | $1,210.00 |
| 18 | Reinforced concrete slab (slab beam)(HPC) (422-7008) | SF | 3,120 | $30.00 | $19.00 | $26.00 | $30.00 | $28.00 | $27.50 | $35.00 |
| 19 | Approach slab (HPC) (422-7014) | CY | 38.50 | $1,000.00 | $800.00 | $900.00 | $850.00 | $918.00 | $935.00 | $1,225.00 |
| 20 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 592.50 | $250.00 | $368.52 | $275.00 | $360.00 | $310.00 | $215.05 | $350.00 |
| 21 | Riprap (concrete)(4 in) (432-7001) | CY | 12 | $2,000.00 | $800.00 | $950.00 | $850.00 | $887.00 | $770.00 | $765.00 |
| 22 | Riprap (mow strip)(4 in) (432-7013) | CY | 32 | $1,000.00 | $800.00 | $750.00 | $830.00 | $746.00 | $770.00 | $850.00 |
| 23 | Riprap (stone protection)(12 in) (432-7041) | CY | 390 | $235.00 | $160.00 | $200.00 | $130.00 | $162.00 | $165.00 | $210.00 |
| 24 | Riprap (stone protection)(24 in) (432-7045) | CY | 638 | $200.00 | $160.00 | $190.00 | $130.00 | $163.00 | $187.00 | $190.00 |
| 25 | Rail (type SSTR)(HPC) (450-7025) | LF | 264 | $150.00 | $190.00 | $150.00 | $150.00 | $191.00 | $187.00 | $205.00 |
| 26 | Armor joint (sealed) (454-7003) | LF | 44 | $200.00 | $150.00 | $175.00 | $160.00 | $77.00 | $165.00 | $175.00 |
| 27 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $50,000 | $20,000 | $22,000 | $25,000 | $35,167 | $22,000 | $65,000 |
| 28 | Mobilization (500-7001) | LS | 1 | $106,134 | $100,000 | $90,000 | $100,000 | $116,324 | $198,000 | $107,400 |
| 29 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $10,000 | $1,641.53 | $2,000.00 | $1,500.00 | $3,130.00 | $3,300.00 | $5,000.00 |
| 30 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $10,000 | $10,000 | $7,500.00 | $7,240.00 | $8,800.00 | $10,000 |
| 31 | Construction exits (install) (type 1) (506-7020) | SY | 156 | $25.00 | $10.00 | $1.00 | $3.00 | $35.00 | $37.26 | $55.00 |
| 32 | Construction exits (remove) (506-7024) | SY | 156 | $20.00 | $5.00 | $1.00 | $1.00 | $15.00 | $15.41 | $15.00 |
| 33 | Temporary sediment control fence (install) (506-7039) | LF | 831 | $6.00 | $3.77 | $1.00 | $8.00 | $5.00 | $4.81 | $5.00 |
| 34 | Temporary sediment control fence (remove) (506-7041) | LF | 831 | $2.00 | $1.08 | $1.00 | $1.10 | $2.00 | $1.78 | $1.00 |
| 35 | Metal W-beam guard fence (timber post) (540-7001) | LF | 100 | $40.00 | $36.02 | $25.00 | $24.00 | $29.00 | $33.00 | $35.00 |
| 36 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 2 | $2,500.00 | $1,290.00 | $1,200.00 | $1,300.00 | $1,296.00 | $1,567.50 | $1,500.00 |
| 37 | Metal beam guard fence trans (non - sym) (540-7016) | EACH | 2 | $1,500.00 | $833.13 | $1,500.00 | $700.00 | $746.00 | $990.00 | $815.00 |
| 38 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $4,500.00 | $3,225.00 | $3,200.00 | $3,000.00 | $3,188.00 | $3,355.00 | $3,750.00 |
| 39 | Wire fence (type C) (552-7003) | LF | 508 | $30.00 | $25.00 | $20.00 | $24.00 | $20.00 | $22.00 | $50.00 |
| 40 | Wire fence (remove) (552-7011) | LF | 508 | $10.00 | $1.00 | $5.00 | $3.50 | $5.00 | $3.30 | $5.00 |
| 41 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 10 | $11.00 | $19.35 | $20.00 | $25.00 | $20.00 | $22.00 | $25.00 |
| 42 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 12 | $30.00 | $26.88 | $20.00 | $30.00 | $25.00 | $33.00 | $55.00 |
| 43 | Install object marker assembly (OM-2Y)(WC)GND(BI) (658-7057) | EACH | 4 | $85.00 | $75.25 | $300.00 | $75.00 | $65.00 | $115.50 | $150.00 |
| 44 | Relocate existing truss bridge (4005-7001) | LS | 1 | $100,000 | $10,000 | $45,000 | $51,000 | $57,578 | $132,000 | $40,000 |
| 45 | Install FTB (5002-7001) | LF | 22 | $60.00 | $50.00 | $20.00 | $5.00 | $22.00 | $55.00 | $200.00 |
| 46 | Remove FTB (5002-7002) | LF | 22 | $20.00 | $1.00 | $10.00 | $1.00 | $10.00 | $5.50 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 4, 2026. Compiled by Mirage Metrics.