TxDOT contract A00080576 bid tabulation

Construct Bridge, US 385 (AT SOUTH SL 338 to .). Let by Texas DOT on July 1, 2026, Ector, Odessa District. 6 bids received; low bid $53,657,268 by Jones Bros. Dirt & Paving Contractors, Inc., +16% against the engineer's estimate of $46,211,493.

Owner
Texas DOT
Letting
01 JUL 2026
Pay items
255
Data through
19 NOV 2026

5 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Jones Bros. Dirt & Paving Contractors, Inc.$53,657,268Low+16%
2Ragle Construction, Inc.$57,618,435+7.0%+25%
3FNF Construction, Inc.$58,921,034+10%+28%
5Webber, LLC$63,315,500+18%+37%
6Altus Construction LLC$66,505,548+24%+44%
TxDOT contract A00080576: bids by rank

Engineer's estimate: $46,211,493.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Jones Bros. Dirt & Paving Contractors, Inc.2. Ragle Construction, Inc.3. FNF Construction, Inc.4. Webber, LLC5. Altus Construction LLC
1Preparing row (100-7002)STA14$10,000$3,700.00$371,425$100,000$400,000$470,296
2Removing concrete (mowstrip) (104-7003)SY2,652$16.00$29.56$14.00$15.00$18.00$14.94
3Removing concrete (riprap) (104-7006)SY522$30.00$11.84$16.50$30.00$20.00$12.39
4Removing concrete (medians) (104-7008)SY64$13.00$28.00$23.00$50.00$41.50$15.18
5Removing concrete (driveways) (104-7011)SY3,088$16.00$12.50$13.50$30.00$26.60$14.88
6Removing concrete (curb) (104-7016)LF647$12.00$2.33$5.50$14.00$8.00$4.99
7Remove (4"-8") TRT/untrt base & asphalt pavement (105-7004)SY4,745$9.00$9.85$5.50$7.00$4.20$13.36
8Remove (11"-15") TRT/untrt base & asphalt pavement (105-7011)SY42,839$8.00$8.42$7.25$6.00$3.60$7.21
9Remove (12"-16") TRT/untrt base & asphalt pavement (105-7012)SY77,400$10.00$7.60$6.50$7.00$4.30$4.70
10Excavation (roadway) (110-7001)CY66,699$15.00$22.39$24.00$14.00$17.10$6.13
11Embankment (final)(DC)(type C) (132-7006)CY265,703$14.00$18.89$23.50$32.00$11.40$33.34
12Blading (150-7002)HR40$150.00$400.00$158.40$150.00$190.00$132.19
13Drill seed (permanent_rural_sand) (164-7009)SY315,649$0.25$0.20$0.12$0.20$0.20$0.20
14Proof rolling (216-7001)HR40$82.00$150.00$98.00$100.00$282.00$93.57
15FL BS (compacted in place)(type A GR 4)(7") (247-7343)SY197,014$15.00$13.50$9.00$10.00$11.20$8.55
16FL BS (compacted in place)(type A GR 4)(5") (247-7345)SY2,986$8.00$10.98$9.40$12.00$11.20$6.11
17Prime coat (AE-P) (310-7001)GAL39,409$5.00$4.60$4.00$5.00$7.75$3.71
18Asphalt (AC-20-5TR) (316-7007)GAL36,308$4.00$4.80$6.00$5.00$4.95$3.05
19Asphalt (CRS-2P) (316-7012)GAL36,308$4.00$4.97$6.00$5.00$4.95$15.02
20Aggregate (type-B, GR-4)(sac-A) (316-7099)CY873$94.00$131.85$175.00$100.00$210.00$337.10
21Aggregate (type-PB, GR-4)(sac-A) (316-7136)CY873$128.00$167.58$175.00$175.00$210.00$97.74
22SP mixes SP-B sac-B PG70-22 (344-7005)TON85,803$90.00$106.00$108.00$125.00$119.00$143.61
23Tack coat (344-7077)GAL20,251$4.00$4.11$6.00$6.50$3.00$2.61
24Stone-MTRX-asphalt smar-F sac-A (346-7023)TON0$138.00$0.00$0.00$0.00$0.00$0.00
25Plane & text asphalt concrete pavement(0" to 2") (354-7002)SY6,595$3.00$4.97$3.00$3.00$2.60$1.46
26Concrete pavement (CRCP) (11") (360-7005)SY19,378$119.00$148.08$114.00$130.00$125.00$101.67
27Concrete pavement(transition slab) (11") (360-7034)SY656$135.00$198.88$146.00$130.00$222.00$101.66
28Cut & restore asphalt paving (400-7008)SY22$130.00$75.00$142.00$250.00$174.00$108.63
29Cem stabil BKFL (400-7010)CY1,482$225.00$299.02$111.00$220.00$132.00$133.22
30Cement stab backfill (inlet or MH) (400-7011)CY40$180.00$322.50$151.00$220.00$303.00$99.62
31Drilled shaft (18 in) (416-7002)LF200$150.00$258.00$211.20$250.00$175.00$216.74
32Drilled shaft (36 in) (416-7006)LF1,280$300.00$338.63$282.00$400.00$291.00$282.16
33Drilled shaft (42 in) (416-7007)LF878$325.00$575.70$396.00$525.00$324.00$326.74
34Drilled shaft (sign mounts) (12 in) (416-7027)LF28$130.00$193.50$180.00$110.00$100.00$114.85
35Drilled shaft (sign mounts) (24 in) (416-7028)LF98$260.00$247.25$230.00$210.00$200.00$183.76
36Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF418$300.00$483.75$275.00$300.00$275.00$252.67
37Drilled shaft (traffic signal pole) (36 in) (416-7044)LF84$462.00$645.00$400.00$450.00$400.00$367.52
38Class C concrete (abutment) (420-7012)CY116$1,400.00$1,075.00$886.00$1,800.00$1,760.00$934.89
39Class C concrete (cap)(HPC) (420-7023)CY94.80$1,700.00$1,026.63$1,470.00$1,900.00$1,590.00$1,257.28
40Class C concrete (column) (420-7038)CY81.20$1,700.00$1,075.00$1,065.00$1,200.00$1,220.00$1,144.10
41Class C concrete (vehicle defl wall) (420-7062)CY175.40$450.00$602.00$1,109.00$770.00$1,320.00$539.28
42Reinforced concrete slab (HPC) (422-7002)SF24,000$33.00$29.03$29.00$30.00$28.30$28.19
43Approach slab (HPC) (422-7014)CY122$935.00$731.00$676.00$1,000.00$980.00$569.10
44Retaining wall (MSE) (ashlar stone fin) (423-7002)SF91,546$75.00$93.23$40.00$49.09$116.00$53.22
45Prestressed concrete girder (TX54) (425-7005)LF3,220.02$300.00$295.62$240.00$300.00$250.00$203.77
46Riprap (concrete)(4 in) (432-7001)CY471$700.00$866.50$670.00$600.00$490.00$410.16
47Riprap (concrete)(CL A) (432-7004)CY182$515.00$1,290.00$680.00$700.00$473.00$313.26
48Riprap (mow strip)(4 in) (432-7013)CY1,107$700.00$687.33$522.00$700.00$558.00$524.39
49STR steel (miscellaneous non-bridge) (442-7007)LB1,000$27.00$27.95$25.00$50.00$29.20$23.06
50Rail (type SSTR)(HPC) (450-7025)LF4,973$136.00$111.80$60.00$100.00$101.00$58.07
51Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF160$235.00$275.20$190.00$300.00$282.00$162.22
52Concrete box culvert (3 FT X 2 FT) (462-7001)LF418$430.00$639.63$433.00$400.00$330.00$328.01
53Concrete box culvert (4 FT X 2 FT) (462-7003)LF1,145$360.00$671.88$520.00$450.00$308.00$429.71
54Concrete box culvert (5 FT X 2 FT) (462-7006)LF32$450.00$768.63$743.00$900.00$453.00$348.25
55RC pipe (CL III)(24 in) (464-7005)LF2,173$100.00$139.75$115.00$200.00$134.00$99.07
56Manh (complete)(PRM)(72IN) (465-7004)EACH3$11,570$13,438$9,120.00$13,000$11,100$8,787.28
57Junction box(complete)(PJB)(3FTX3FT) (465-7005)EACH2$6,900.00$7,202.50$4,900.00$8,000.00$6,270.00$5,768.24
58Junction box(complete)(PJB)(4FTX4FT) (465-7006)EACH1$9,000.00$11,019$6,050.00$9,000.00$7,410.00$5,582.62
59Inlet (complete)(pco)(3FT)(right) (465-7015)EACH2$5,400.00$12,363$7,000.00$7,000.00$17,140$5,359.14
60Inlet(complete)(pazd)(FG)(5FTX5FT-3FTX3FT) (465-7161)EACH1$8,000.00$13,438$7,300.00$8,000.00$11,501$3,858.92
61Inlet(complete)(type MSE1) (465-7362)EACH19$7,800.00$5,912.50$7,700.00$5,000.00$14,040$8,303.83
62Set (type I)(S= 3 FT)(HW= 2 FT)(4:1)(C) (467-7037)EACH4$8,900.00$9,406.25$11,000$7,000.00$7,220.00$744.22
63Set (type I)(S= 3 FT)(HW= 2 FT)(6:1)(P) (467-7039)EACH2$4,200.00$13,438$11,000$13,000$10,750$10,336
64Set (type I)(S= 4 FT)(HW= 2 FT)(4:1)(C) (467-7064)EACH4$9,000.00$9,137.50$11,550$9,000.00$8,770.00$6,221.73
65Set (type I)(S= 4 FT)(HW= 2 FT)(6:1)(P) (467-7066)EACH8$12,000$13,330$11,400$13,000$12,080$8,269.12
66Set (type I)(S= 5 FT)(HW= 3 FT)(6:1)(P) (467-7098)EACH2$13,700$15,426$15,000$18,000$12,520$9,420.21
67Set (type II) (18 in) (TP) (3: 1) (C) (467-7309)EACH2$2,200.00$1,773.75$1,800.00$2,000.00$1,530.00$1,075.91
68Set (type II) (18 in) (TP) (6: 1) (P) (467-7312)EACH24$2,750.00$2,956.25$1,900.00$2,200.00$1,880.00$979.47
69Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325)EACH2$2,200.00$2,580.00$2,200.00$2,300.00$1,570.00$1,376.12
70Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326)EACH28$2,400.00$3,225.00$2,200.00$2,500.00$1,910.00$1,397.03
71Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327)EACH1$2,750.00$3,225.00$2,200.00$3,000.00$3,361.00$1,668.08
72Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH3$2,750.00$3,493.75$2,200.00$3,200.00$2,510.00$1,285.84
73Set (type II) (24 in) (TP) (6: 1) (P) (467-7332)EACH40$2,870.00$3,493.75$2,400.00$3,200.00$2,510.00$1,942.68
74Set (type II) (30 in) (TP) (6: 1) (P) (467-7352)EACH2$5,885.00$4,837.50$5,100.00$6,000.00$3,810.00$3,849.52
75Thermoplastic pipe (PP) (18") (468-7001)LF1,072$93.00$118.25$80.00$75.00$71.00$51.28
76Thermoplastic pipe (PP) (24") (468-7002)LF1,144$95.00$136.53$110.00$90.00$87.00$80.65
77Thermoplastic pipe (PP) (30") (468-7003)LF36$144.00$193.50$144.00$130.00$126.00$109.57
78Removing structure (pipe) (496-7007)LF402$20.00$16.13$14.00$40.00$45.00$15.47
79Removing structure(driveway culvert) (496-7039)EACH10$370.00$5,375.00$560.00$3,000.00$2,700.00$253.25
80Mobilization (500-7001)LS1$2,590,109$2,570,000$5,500,000$5,914,000$6,212,000$6,617,396
81Barricades, signs and traffic handling (502-7001)MO24$13,000$20,000$134,500$30,000$35,415$138,555
82Portable changeable message sign (503-7002)EACH4$10,000$19,250$13,200$15,000$22,660$6,776.51
83TMA (stationary) (505-7001)DAY88$100.00$110.00$1,100.00$250.00$122.00$146.89
84TMA (mobile operation) (505-7003)DAY34$500.00$935.00$650.00$500.00$836.00$146.38
85Rock filter dams (install) (type 3) (506-7003)LF270$95.00$23.45$95.00$100.00$95.00$90.96
86Rock filter dams (remove) (506-7011)LF270$18.00$7.65$18.00$20.00$18.00$11.94
87Construction exits (install) (type 1) (506-7020)SY2,016$31.00$9.56$26.00$55.00$26.00$32.16
88Construction exits (remove) (506-7024)SY2,016$8.00$5.57$13.50$7.00$13.50$8.27
89Temporary sediment control fence (install) (506-7039)LF1,000$6.00$6.45$5.85$7.00$5.85$2.86
90Temporary sediment control fence (remove) (506-7041)LF1,000$1.75$1.08$1.25$1.25$1.25$0.86
91Biodegradable erosion control logs (install) (18") (506-7045)LF5,510$11.00$9.68$10.00$10.00$10.00$5.60
92Biodegradable erosion control logs (remove) (506-7046)LF5,510$1.50$1.34$1.25$1.00$1.25$0.86
93Constructing detours (508-7001)SY28,467$45.00$56.00$90.00$82.00$98.25$152.72
94Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF4,204$35.00$16.13$47.00$75.00$42.50$8.01
95Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF3,063$12.00$15.59$12.00$6.00$6.10$5.54
96Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF4,204$35.00$16.66$22.00$14.00$29.90$8.80
97Landscape pavers (528-7001)SY2,986$75.00$164.48$108.00$125.00$295.00$77.04
98Concrete curb (type II) (529-7002)LF6,795$40.00$12.36$30.00$20.00$46.00$14.14
99Concrete curb & gutter (type II) (529-7009)LF4,548$40.00$39.78$24.00$60.00$59.00$25.82
100Driveways (concrete) (530-7006)SY5,667$125.00$130.64$88.00$115.00$159.00$78.77
101Driveways (ACP) (530-7010)SY3,301$56.00$80.00$82.00$65.00$53.75$275.99
102Concrete sidewalks (4") (531-7001)SY1,810$80.00$83.85$58.00$80.00$109.00$48.82
103Curb ramps (type 1) (531-7005)EACH20$3,000.00$3,010.00$2,055.00$3,000.00$3,610.00$1,950.60
104Curb ramps (type 21) (531-7023)SY41$230.00$306.38$218.00$225.00$358.00$157.15
105Mill rumble strips (asphalt) (shoulder) (533-7001)LF54,781$0.25$0.24$0.18$0.20$0.60$0.17
106Metal W-beam guard fence (steel post) (540-7002)LF1,656$34.00$40.85$40.06$40.00$36.25$23.39
107Metal beam guard fence trans (thrie-beam) (540-7005)EACH6$2,600.00$3,117.50$2,678.00$3,250.00$3,360.00$1,557.39
108Downstream anchor terminal section (540-7015)EACH3$1,200.00$1,746.88$1,634.00$2,000.00$1,580.00$858.48
109Cable barrier sys (install)(TL-4)(10'-0") (543-7006)LF10,275$8.00$25.80$36.83$26.00$27.00$8.28
110Cable barrier terminal sec (install)(TL-4) (543-7018)EACH15$3,250.00$6,450.00$4,767.25$7,000.00$4,290.00$2,387.82
111Cable barrier system (relocate)(TL-4) (543-7020)LF6,267$13.00$16.13$25.95$16.00$22.00$8.83
112Cable barrier terminal sec (reloc)(TL-4) (543-7036)EACH10$3,320.00$6,450.00$4,250.00$7,000.00$2,600.00$2,285.56
113Cable barrier (remove) (543-7037)LF900$3.00$6.45$6.85$8.00$9.00$3.27
114Guardrail end treatment (install) (544-7001)EACH9$4,000.00$3,547.50$3,858.00$3,500.00$3,880.00$2,300.19
115Crash cushion attenuator (move & reset) (545-7002)EACH8$1,000.00$3,225.00$1,100.00$200.00$1,800.00$1,041.41
116Crash cushion attenuator (remove) (545-7004)EACH8$1,000.00$2,150.00$1,000.00$1,500.00$950.00$723.28
117Crash cushion attenuator (install)(L)(N)(TL3) (545-7006)EACH6$30,000$40,850$34,500$30,000$25,980$17,911
118Cca (install)(N)(TL3)(work zone) (545-7018)EACH10$8,000.00$10,213$7,200.00$10,000$9,300.00$5,296.83
119Pipe underdrains (type 6) (6") (556-7006)LF4,005$25.00$10.75$30.00$32.00$27.30$24.76
120Remove RD IL asm (trans-base) (610-7009)EACH4$675.00$537.50$600.00$750.00$600.00$551.27
121In RD IL (U/P) (type 1) (150W EQ) LED (610-7014)EACH8$1,900.00$2,795.00$800.00$1,000.00$800.00$735.03
122In RD IL (type SA) 40T-10 (250W EQ) LED (610-7126)EACH36$5,400.00$6,181.25$5,200.00$6,500.00$5,200.00$4,777.72
123In RD IL (type SA) 50T-10-10(400W EQ)LED (610-7199)EACH13$6,500.00$9,137.50$7,500.00$9,500.00$7,500.00$6,890.94
124Conduit (PVC) (schedule 40) (2") (618-7030)LF405$13.00$7.53$15.00$19.00$15.00$13.78
125Conduit (PVC) (schedule 40) (3") (618-7036)LF60$18.00$16.13$15.00$19.00$15.00$13.78
126Conduit (PVC) (schedule 40) (3") (bore) (618-7037)LF960$34.00$48.38$20.00$25.00$20.00$18.38
127Conduit (PVC) (schedule 80) (2") (618-7054)LF10,820$16.00$7.53$15.00$19.00$15.00$13.78
128Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF1,890$30.00$21.50$25.00$31.00$25.00$22.97
129Conduit (PVC) (schedule 80) (2") (concrete encse) (618-7057)LF80$20.00$16.13$22.00$27.00$22.00$20.21
130Conduit (PVC) (schedule 80) (3") (618-7060)LF195$45.00$37.63$16.00$20.00$16.00$14.70
131Conduit (PVC) (schedule 80) (3") (bore) (618-7061)LF470$32.00$53.75$25.00$31.00$25.00$22.97
132Conduit (PVC) (schedule 80) (4") (618-7064)LF215$33.00$43.00$20.00$25.00$20.00$18.38
133Conduit (PVC) (schedule 80) (4") (bore) (618-7065)LF70$37.00$64.50$35.00$44.00$35.00$32.16
134Conduit (RM) (1") (618-7072)LF120$37.00$69.88$30.00$38.00$30.00$27.56
135Electrical conductor (no.12) insulated (620-7004)LF480$1.30$1.61$2.00$2.50$2.00$1.84
136Electrical conductor (no.8) insulated (620-7008)LF2,230$3.00$2.15$2.50$3.00$2.50$2.30
137Electrical conductor (no.6) bare (620-7009)LF15,680$2.50$2.69$2.60$3.25$2.60$2.39
138Electrical conductor (no.6) insulated (620-7010)LF29,830$3.00$2.96$2.90$3.50$2.90$2.66
139Electrical conductor (no.4) bare (620-7011)LF1,650$2.50$5.38$3.50$4.00$3.50$3.22
140Electrical conductor (no.4) insulated (620-7012)LF825$3.00$5.91$3.75$4.50$3.75$3.45
141Electrical conductor (no.2) bare (620-7015)LF1,160$2.00$7.53$5.00$6.00$5.00$4.59
142Electrical conductor (no.2) insulated (620-7016)LF580$3.00$8.06$5.25$6.50$5.25$4.82
143Ground box type A (122311)W/apron (624-7002)EACH31$1,500.00$2,150.00$1,300.00$1,500.00$1,300.00$1,194.43
144Ground box type D (162922)W/apron (624-7008)EACH13$1,900.00$2,956.25$1,350.00$1,600.00$1,350.00$1,240.37
145Remove ground box (624-7013)EACH6$400.00$537.50$500.00$600.00$500.00$459.40
146Elc SRV type A 240/480 100(NS)SS(E)SP(U) (628-7080)EACH3$5,500.00$11,825$7,000.00$8,000.00$7,000.00$6,431.54
147Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148)EACH2$11,000$11,825$7,000.00$8,000.00$7,000.00$6,431.54
148Elc SRV type D 120/240 060(SS)SS(E)SP(O) (628-7161)EACH1$8,000.00$13,438$8,000.00$9,000.00$8,000.00$7,350.33
149Aluminum signs (type A) (636-7001)SF125$45.00$59.13$40.00$45.00$25.50$36.75
150Aluminum signs (type G) (636-7002)SF1,150$30.00$40.85$38.00$40.00$39.75$34.91
151Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH49$750.00$732.08$681.00$800.00$68.75$150.88
152Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH60$825.00$842.80$784.00$1,000.00$769.00$717.58
153Install small roadside sign support and assembly type 10BWG(1)SA(T-2EXT) (644-7005)EACH7$815.00$989.00$920.00$1,100.00$850.00$849.88
154Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH2$1,000.00$1,019.10$948.00$1,150.00$800.00$874.69
155Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009)EACH6$875.00$781.53$727.00$800.00$725.00$667.04
156Install small roadside sign support and assembly type 10BWG(1)SB(P-BM) (644-7010)EACH2$850.00$781.53$727.00$800.00$775.00$795.67
157Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012)EACH2$990.00$942.78$877.00$1,000.00$775.00$795.67
158Install small roadside sign support and assembly type 10BWG(1)SB(U) (644-7015)EACH1$1,000.00$1,054.58$981.00$1,200.00$850.00$856.31
159Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025)EACH1$1,000.00$994.38$925.00$1,100.00$775.00$856.31
160Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH2$1,100.00$1,093.28$1,017.00$1,200.00$875.00$941.76
161Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035)EACH8$1,200.00$1,340.53$1,247.00$1,500.00$975.00$1,154.00
162Install small roadside sign support and assembly TYS80(1)SB(U) (644-7042)EACH3$1,300.00$1,231.95$1,146.00$1,300.00$950.00$1,056.95
163Install small roadside sign support and assembly TYS80(1)SB(U-WC) (644-7046)EACH4$1,200.00$1,263.13$1,175.00$1,500.00$1,250.00$1,079.58
164Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH1$300.00$683.70$636.00$800.00$475.00$577.92
165Relocate SM RD SN sup&AM(sign only) (644-7072)EACH10$350.00$185.98$173.00$200.00$75.00$121.28
166Remove SM RD SN sup&AM (644-7073)EACH64$100.00$141.00$150.00$200.00$100.00$86.56
167Install LRSS (struct steel) (647-7001)LB7,926$9.00$8.92$8.30$10.00$12.00$7.63
168Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003)EACH11$75.00$77.40$72.00$28.00$80.00$66.15
169Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH6$23.00$53.75$25.00$52.00$80.00$17.50
170Install delineator assembly (D-SW)SZ 1(BRF)CTB (BR) (658-7014)EACH38$5.00$53.75$39.00$52.00$80.00$19.98
171Install delineator assembly (D-SY)SZ 1(BRF)CTB (BR) (658-7033)EACH6$6.00$53.75$40.00$52.00$80.00$19.40
172Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036)EACH12$33.00$43.00$60.00$45.00$80.00$35.19
173Install delineator assembly (D-DW)SZ 1(WFLX)GND (658-7045)EACH22$100.00$78.48$73.00$28.00$80.00$67.07
174Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH125$70.00$83.85$78.00$85.00$90.00$71.67
175Install OM SM RD sign (1-OM-PW)Y (658-7317)EACH111$24.00$13.98$13.00$14.00$90.00$11.94
176Install OM SM RD sign (1-OM-PW)R (658-7318)EACH36$20.00$13.98$13.00$14.00$90.00$11.94
177Install OM LG RD sign (2-OM-PW)Y (658-7321)EACH11$24.00$19.35$18.00$19.00$90.00$16.54
178Work zone pavement marking removing (W)6"(broken) (662-7065)LF28,444$1.00$0.38$0.35$0.65$0.35$0.32
179Work zone pavement marking removing (W)6"(solid) (662-7068)LF119,911$1.00$0.38$0.35$0.65$0.35$0.32
180Work zone pavement marking removing (W)8"(DOT) (662-7070)LF5,251$1.75$0.43$0.40$1.00$0.40$0.37
181Work zone pavement marking removing (W)24"(solid) (662-7077)LF1,373$14.00$5.91$5.50$7.00$5.50$5.05
182Work zone pavement marking removing (Y)6"(broken) (662-7098)LF15,573$1.00$0.38$0.35$0.65$0.35$0.32
183Work zone pavement marking removing (Y)6"(solid) (662-7100)LF65,519$1.00$0.38$0.35$0.65$0.35$0.32
184Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF1,596$1.25$0.91$0.85$0.65$0.85$0.78
185Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF809$1.50$1.08$1.00$1.00$1.00$0.92
186Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF14,888$0.75$0.81$0.75$1.00$0.75$0.69
187Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF1,931$13.00$10.75$10.00$10.00$10.00$9.19
188Reflectorized pavement marking type I(W)(entr gore)(100MIL) (666-7069)EACH2$900.00$1,075.00$1,000.00$1,100.00$1,000.00$918.79
189Reflectorized pavement marking type I(W)(exit gore)(100MIL) (666-7072)EACH2$1,300.00$1,612.50$1,500.00$1,100.00$1,500.00$1,378.19
190Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090)EACH14$30.00$69.88$65.00$45.00$65.00$59.72
191Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123)LF2,028$6.00$10.75$10.00$9.00$10.00$9.19
192Pavement sler 6" (666-7347)LF6,475$0.50$0.38$0.35$0.25$0.35$0.32
193Pavement sler 8" (666-7348)LF3,545$0.50$0.43$0.40$0.45$0.40$0.37
194Pavement sler 24" (666-7352)LF674$1.75$4.30$4.00$3.10$4.00$3.68
195Pavement sler (arrow) (666-7353)EACH9$30.00$86.00$80.00$80.00$80.00$73.50
196Pavement sler (word) (666-7354)EACH11$34.00$107.50$100.00$85.00$100.00$91.88
197Pavement sler (double arrow) (666-7356)EACH4$36.00$172.00$160.00$105.00$160.00$147.01
198Pavement sler (uturn arrow) (666-7358)EACH2$60.00$150.50$140.00$125.00$140.00$128.63
199Pavement sler (yld tri) (666-7365)EACH14$20.00$21.50$20.00$40.00$20.00$18.38
200Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF9,367$0.75$0.70$0.65$0.70$0.65$0.60
201Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF48,680$0.75$0.70$0.65$0.70$0.65$0.37
202Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF53,159$0.75$0.70$0.65$0.70$0.65$0.60
203Prefabricated PM type C (W)(24")(solid) (668-7089)LF438$15.00$16.13$15.00$13.00$15.00$13.78
204Prefabricated PM type C (W)(arrow) (668-7091)EACH34$180.00$258.00$240.00$200.00$240.00$220.51
205Prefabricated PM type C (W)(double arrow) (668-7093)EACH6$300.00$430.00$400.00$400.00$400.00$367.52
206Prefabricated PM type C (W)(uturn arrow) (668-7096)EACH8$340.00$483.75$450.00$600.00$450.00$413.46
207Prefabricated PM type C (W)(U-LT arrow) (668-7098)EACH4$400.00$483.75$450.00$625.00$450.00$413.46
208Prefabricated PM type C (W)(LN reduct arrow) (668-7100)EACH4$510.00$564.38$525.00$625.00$525.00$482.37
209Prefabricated PM type C (W)(word) (668-7103)EACH43$240.00$365.50$340.00$300.00$340.00$312.39
210Reflectorized pavement marker type I-C (672-7002)EACH682$4.00$5.38$5.00$5.25$5.00$4.59
211Reflectorized pavement marker type II-A-A (672-7004)EACH281$4.50$5.38$5.00$5.25$5.00$4.59
212Reflectorized pavement marker type II-C-R (672-7006)EACH800$4.00$5.38$5.00$5.25$5.00$4.59
213Pavement surface preparation for marking (6") (678-7002)LF6,475$0.50$0.38$0.35$0.30$0.35$0.32
214Pavement surface preparation for marking (8") (678-7004)LF3,545$0.15$0.43$0.40$0.35$0.40$0.37
215Pavement surface preparation for marking (24") (678-7008)LF674$3.00$3.76$3.50$2.10$3.50$3.22
216Pavement surface preparation for marking (arrow) (678-7009)EACH9$20.00$80.63$75.00$64.00$75.00$68.91
217Pavement surface preparation for marking (double arrow) (678-7010)EACH4$22.00$193.50$180.00$76.00$180.00$165.38
218Pavement surface preparation for marking (uturn arr) (678-7012)EACH2$4.00$193.50$180.00$190.00$180.00$165.38
219Pavement surface preparation for marking (word) (678-7016)EACH11$20.00$96.75$90.00$65.00$90.00$82.69
220Pavement surface preparation for marking (36")(yld tri) (678-7023)EACH14$12.00$19.35$18.00$40.00$18.00$16.54
221Install highway traffic signal (isolated) (680-7002)EACH1$32,000$67,188$50,000$55,000$50,000$45,940
222Removing traffic signals (680-7004)EACH1$10,000$13,438$4.00$5,000.00$4,000.00$3,675.17
223Temporary traffic signals (681-7001)EACH1$105,000$456,875$50,000$55,000$50,000$45,940
224Vehicle signal section (12")LED(green) (682-7001)EACH20$355.00$430.00$350.00$400.00$350.00$321.58
225Vehicle signal section (12")LED(green arrow) (682-7002)EACH8$375.00$430.00$350.00$400.00$350.00$321.58
226Vehicle signal section (12")LED(yel) (682-7003)EACH20$345.00$430.00$350.00$400.00$350.00$321.58
227Vehicle signal section (12")LED(yel arrow) (682-7004)EACH4$470.00$430.00$350.00$400.00$350.00$321.58
228Vehicle signal section (12")LED(red) (682-7005)EACH20$345.00$430.00$350.00$400.00$350.00$321.58
229Vehicle signal section (12")LED(red arrow) (682-7006)EACH8$400.00$430.00$350.00$400.00$350.00$321.58
230Pedestrian signal section (LED)(countdown) (682-7018)EACH16$1,000.00$967.50$675.00$700.00$675.00$620.18
231Backplate W/reflectorized border(3 sec)aluminum (682-7039)EACH16$210.00$188.13$180.00$200.00$180.00$165.38
232Backplate W/reflectorized border(4 sec)aluminum (682-7040)EACH8$275.00$215.00$190.00$210.00$190.00$174.57
233Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031)LF730$4.00$4.30$2.85$3.00$2.85$2.62
234Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033)LF470$5.00$5.38$3.50$4.00$3.50$3.22
235Traffic signal CBL (type A)(14 AWG)(10 conductor) (684-7036)LF2,250$6.00$6.45$3.75$4.00$3.75$3.45
236Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046)LF1,690$8.00$10.75$9.00$10.00$9.00$8.27
237Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079)LF4,000$3.00$3.23$3.00$3.50$3.00$2.76
238Ins traffic signal PL AM(S)1 arm(40')lum (686-7043)EACH2$18,900$19,888$16,000$18,000$16,000$14,701
239Ins traffic signal PL AM(S)1 arm(48')lum (686-7051)EACH4$21,200$24,188$20,000$22,000$20,000$18,376
240Pedestrian pole assembly (687-7001)EACH8$4,600.00$4,138.75$3,500.00$4,000.00$3,500.00$3,215.77
241Pedestrian detect push button (APS) (688-7001)EACH14$1,100.00$1,290.00$725.00$800.00$725.00$666.12
242Pedestrian detector controller unit (688-7003)EACH1$5,000.00$6,987.50$3,500.00$4,000.00$3,500.00$3,215.77
243Post and cable fence (removal) (772-7001)LF2,938$3.00$5.38$5.00$6.00$5.10$3.54
244Carbon fiber reinforced polymer protection (786-7001)SF1,044.30$60.00$47.30$40.00$98.00$44.00$62.13
245Bonding course (3007-7001)GAL23,686$3.00$2.76$6.00$6.00$3.00$2.29
246Install DMS (pole MTD cabinet) (6004-7001)EACH2$15,000$37,625$15,000$16,000$15,000$13,782
247Bbu system (external battery cabinet) (6007-7001)EACH1$10,800$13,438$10,000$12,000$10,000$9,187.91
248RVDS (presence detection only) (6008-7001)EACH6$10,400$8,600.00$6,000.00$7,000.00$6,000.00$5,512.75
249RVDS (advance detection only) (6008-7002)EACH4$7,500.00$8,600.00$7,000.00$8,000.00$7,000.00$6,431.54
250ITS pole (50 FT) (90 MPH) (6011-7005)EACH2$25,000$18,813$15,000$17,000$15,000$13,782
251CCTV field equip (digital) (install only) (6018-7001)EACH1$3,500.00$10,213$2,500.00$3,000.00$2,500.00$2,296.98
252CCTV field equipment (digital) (6018-7002)EACH2$8,000.00$19,888$12,500$14,000$12,500$11,485
253CCTV mount (pole) (6018-7003)EACH3$1,300.00$2,150.00$300.00$350.00$300.00$275.64
254ITS com CBL (ethernet) (6018-7004)LF570$4.00$18.81$1.75$2.00$1.75$1.61
255Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009)TON16,235$138.00$142.00$137.00$200.14$185.00$193.58
TxDOT contract A00080576: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of July 1, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy