TxDOT contract A00080988 bid tabulation
Interstate Designation, US 281 (0.273 MI S OF SH 186 to 0.023 MI N OF FM 490). Let by Texas DOT on January 7, 2025, Hidalgo, Pharr District. 5 bids received; low bid $165,009,689 by Ioc Company LLC, -14% against the engineer's estimate of $191,485,572.
- Owner
- Texas DOT
- Letting
- 07 JAN 2025
- Pay items
- 323
- Data through
- 19 NOV 2026
1 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ioc Company LLC | $165,009,689 | Low | -14% |
Engineer's estimate: $191,485,572.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ioc Company LLC |
|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 410.80 | $25,100 | $12,060 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 2,562 | $30.00 | $18.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 209 | $25.00 | $45.00 |
| 4 | Removing concrete (curb) (104-7016) | LF | 80 | $14.50 | $30.00 |
| 5 | Remove (12") TRT/untrt base & asphalt pavement (105-7091) | CY | 19,445.90 | $16.00 | $10.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 355,076 | $5.00 | $2.00 |
| 7 | Excavation (special) (110-7003) | CY | 80,700 | $70.00 | $5.00 |
| 8 | Embankment (final)(OC)(type A) (132-7001) | CY | 4,200 | $50.00 | $10.00 |
| 9 | Embankment (final)(DC)(type C) (132-7006) | CY | 749,853 | $10.00 | $13.62 |
| 10 | Backfill (type A) (134-7001) | STA | 54 | $350.00 | $275.00 |
| 11 | Road grader work (ord comp) (152-7001) | STA | 1,193.20 | $330.00 | $100.00 |
| 12 | Spec excavation work (hyd excavator) (158-7002) | HR | 380 | $450.00 | $100.00 |
| 13 | Furn & place topsoil (4") (160-7002) | SY | 7,669.62 | $75.00 | $4.00 |
| 14 | Drill seed (permanent_rural_clay) (164-7010) | SY | 766,962 | $0.40 | $0.35 |
| 15 | Drill seed (temporary_warm) (164-7013) | SY | 766,962 | $0.40 | $0.31 |
| 16 | Vegetative watering (168-7001) | TGL | 14,021 | $34.50 | $10.00 |
| 17 | Soil ret BLKT(SL_mod_clay_long_spry) (169-7018) | SY | 111,623 | $3.35 | $2.25 |
| 18 | Trans plant material (type I) (192-7072) | EACH | 117 | $830.77 | $85.00 |
| 19 | Vegetative watering (193-7027) | TGL | 80 | $461.17 | $10.00 |
| 20 | Sprinkling (dust control) (204-7001) | TGL | 3,254.10 | $18.00 | $1.00 |
| 21 | Proof rolling (216-7001) | HR | 481.90 | $75.00 | $50.00 |
| 22 | FL BS (roadway del)(type E GR 4)(final pos) (247-7277) | CY | 205,154.50 | $45.00 | $25.00 |
| 23 | Geogrid base reinforcement (type 2) (250-7002) | SY | 48,003 | $4.00 | $1.25 |
| 24 | Rework BS metal (type B)(6")(ord comp) (251-7025) | SY | 77,202.40 | $2.50 | $2.50 |
| 25 | Rework BS metal (type B)(10")(density control) (251-7030) | SY | 77,309.40 | $8.00 | $3.40 |
| 26 | Rework BS metal (type B)(12")(density control) (251-7032) | SY | 141,650.10 | $8.50 | $3.75 |
| 27 | Rework BS metal (type B)(18")(density control) (251-7084) | SY | 100,264.20 | $10.00 | $5.75 |
| 28 | Lime (com or QK)(slurry) (260-7005) | TON | 15,850 | $287.50 | $215.00 |
| 29 | Lime TRT (existing material)(12") (260-7009) | SY | 801,045 | $2.00 | $2.50 |
| 30 | Cement (275-7001) | TON | 9,910 | $195.00 | $188.00 |
| 31 | Cement TRT (new base)(12") (275-7013) | SY | 368,460 | $5.00 | $2.50 |
| 32 | Cement treat (MX exst metal & NW BS)(17") (275-7021) | SY | 401,980 | $8.00 | $2.75 |
| 33 | Salvage, haul & stockpile reclaimed asphalt PV (1 1/2") (305-7015) | SY | 29,763.20 | $1.77 | $2.00 |
| 34 | Salvage, haul & stockpile reclaimed asphalt PV (3 1/2") (305-7017) | SY | 77,202.40 | $5.00 | $2.25 |
| 35 | Salvage, haul & stockpile reclaimed asphalt PV (4") (305-7022) | SY | 57,952 | $5.00 | $2.50 |
| 36 | Salvage, haul & stockpile reclaimed asphalt pavement (4"-14") (305-7055) | SY | 231,509 | $9.50 | $7.00 |
| 37 | Prime coat (MC-30) (310-7004) | GAL | 155,679 | $4.75 | $4.50 |
| 38 | SP mixes SP-B sac-B PG64-22 (344-7002) | TON | 114,543 | $109.00 | $110.00 |
| 39 | SP mixes SP-B sac-B PG76-22 (344-7008) | TON | 61,597 | $126.00 | $120.00 |
| 40 | SP mixes SP-D sac-A PG76-22 (344-7064) | TON | 61,597 | $128.00 | $120.00 |
| 41 | SP mixes SP-D sac-B PG76-22 (344-7065) | TON | 45,813 | $140.00 | $115.00 |
| 42 | Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009) | TON | 48,026 | $139.00 | $146.00 |
| 43 | Planing asphalt concrete pavement(1") (354-7050) | SY | 6,602 | $2.50 | $1.00 |
| 44 | Planing asphalt concrete pavement(2") (354-7051) | SY | 20,505 | $1.00 | $1.50 |
| 45 | Full - depth repair CRCP (8") (361-7003) | CY | 95 | $300.00 | $950.00 |
| 46 | Cut & restoring pavement (400-7006) | SY | 409 | $91.46 | $75.00 |
| 47 | Cut & restore asphalt paving (400-7008) | SY | 1,466 | $75.51 | $75.00 |
| 48 | Cut and restore pavement (flex base) (400-7009) | SY | 1,959 | $50.00 | $45.00 |
| 49 | Cem stabil BKFL (400-7010) | CY | 2,595 | $80.00 | $70.00 |
| 50 | Trench excavation protection (402-7001) | LF | 66,731 | $7.16 | $0.10 |
| 51 | Drilled shaft (30 in) (416-7005) | LF | 160 | $275.00 | $288.90 |
| 52 | Drilled shaft (36 in) (416-7006) | LF | 2,940 | $290.50 | $265.00 |
| 53 | Drilled shaft (42 in) (416-7007) | LF | 25 | $330.00 | $698.60 |
| 54 | Drilled shaft (48 in) (416-7008) | LF | 26 | $388.40 | $761.64 |
| 55 | Drilled shaft (54 in) (416-7009) | LF | 1,344 | $500.00 | $550.00 |
| 56 | Drilled shaft (sign mounts) (12 in) (416-7027) | LF | 64 | $150.00 | $463.31 |
| 57 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 320 | $235.00 | $567.18 |
| 58 | Drilled shaft (sign mounts) (54 in) (416-7033) | LF | 401 | $620.00 | $861.44 |
| 59 | Drilled shaft (high mast pole) (60 in) (416-7037) | LF | 404 | $750.00 | $950.73 |
| 60 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 168 | $284.30 | $393.95 |
| 61 | Class A concrete (plug) (420-7009) | EACH | 6 | $2,250.00 | $5,000.00 |
| 62 | Class B concrete (miscellaneous) (420-7011) | CY | 63 | $643.41 | $800.00 |
| 63 | Class C concrete (abutment) (420-7012) | CY | 356.40 | $1,400.00 | $1,000.00 |
| 64 | Class C concrete (cap) (420-7022) | CY | 784.20 | $1,400.00 | $1,750.00 |
| 65 | Class C concrete (column) (420-7038) | CY | 390 | $1,300.00 | $2,300.00 |
| 66 | Class C concrete (rail foundation) (420-7052) | CY | 373 | $750.00 | $750.00 |
| 67 | Reinforced concrete slab (422-7001) | SF | 106,128 | $25.00 | $19.30 |
| 68 | Retaining wall (MSE) (423-7001) | SF | 248,133 | $80.00 | $100.00 |
| 69 | Prestressed concrete girder (TX46) (425-7004) | LF | 12,263.87 | $180.00 | $221.00 |
| 70 | Riprap (concrete)(4 in) (432-7001) | CY | 1,232 | $480.00 | $379.00 |
| 71 | Riprap (concrete)(5 in) (432-7002) | CY | 36 | $550.00 | $389.00 |
| 72 | Riprap (concrete)(CL B) (432-7005) | CY | 138 | $600.00 | $389.00 |
| 73 | Riprap (concrete) (CL B) (4 in) (432-7007) | CY | 8 | $570.00 | $399.00 |
| 74 | Riprap (mow strip)(4 in) (432-7013) | CY | 485.50 | $591.00 | $384.00 |
| 75 | Riprap (mow strip)(5 in) (432-7014) | CY | 452 | $500.00 | $391.00 |
| 76 | Riprap (stone protection)(12 in) (432-7041) | CY | 5,981 | $220.00 | $150.00 |
| 77 | Cleaning and sealing existing joints (438-7001) | LF | 336 | $51.50 | $90.00 |
| 78 | Rail (type SSTR) (450-7024) | LF | 18,866 | $50.00 | $45.00 |
| 79 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 696 | $200.00 | $200.00 |
| 80 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 3,335 | $359.00 | $390.00 |
| 81 | Concrete box culvert (5 FT X 2 FT) (462-7006) | LF | 1,235 | $485.00 | $500.00 |
| 82 | Concrete box culvert (6 FT X 2 FT) (462-7010) | LF | 598 | $725.00 | $575.00 |
| 83 | RC pipe (CL III)(18 in) (464-7003) | LF | 0 | $90.00 | $0.00 |
| 84 | RC pipe (CL III)(24 in) (464-7005) | LF | 0 | $195.00 | $0.00 |
| 85 | RC pipe (CL III)(30 in) (464-7007) | LF | 0 | $215.00 | $0.00 |
| 86 | RC pipe (CL III)(36 in) (464-7009) | LF | 0 | $200.00 | $0.00 |
| 87 | RC pipe (CL V)(18 in) (464-7032) | LF | 0 | $130.00 | $0.00 |
| 88 | RC pipe (CL V)(24 in) (464-7034) | LF | 0 | $139.98 | $0.00 |
| 89 | Inlet (complete)(PSL)(RC)(4FTX4FT) (465-7071) | EACH | 1 | $5,200.00 | $5,500.00 |
| 90 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 2 | $5,250.00 | $4,800.00 |
| 91 | Inl(CMP)(pazd-CZ)(FG)(3FTX3FT-3FTX3FT) (465-7163) | EACH | 32 | $5,000.00 | $4,750.00 |
| 92 | Inl(CMP)(pazd-CZ)(FG)(4FTX4FT-4FTX4FT) (465-7165) | EACH | 2 | $6,600.00 | $5,250.00 |
| 93 | Inlet (complete) (type MSE2) (465-7352) | EACH | 55 | $7,700.00 | $7,500.00 |
| 94 | Headwall (CH - FW - 0) (diameter= 24 in) (466-7005) | EACH | 3 | $8,000.00 | $15,000 |
| 95 | Headwall (CH - FW - 0) (diameter= 30 in) (466-7007) | EACH | 1 | $10,500 | $15,000 |
| 96 | Headwall (CH - FW - 45) (diameter= 24 in) (466-7050) | EACH | 5 | $5,420.00 | $15,000 |
| 97 | Headwall (CH - PW - 0) (diameter= 18 in) (466-7099) | EACH | 2 | $6,200.00 | $15,000 |
| 98 | Headwall (CH - PW - 0) (diameter= 24 in) (466-7101) | EACH | 1 | $10,250 | $15,000 |
| 99 | Wingwall (PW - 1) (HW=3 FT) (466-7173) | EACH | 5 | $10,000 | $16,000 |
| 100 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 1 | $14,000 | $17,000 |
| 101 | Wingwall (SW - 0) (HW=3 FT) (466-7202) | EACH | 15 | $12,000 | $16,000 |
| 102 | Set (type I)(S= 4 FT)(HW= 3 FT)(3:1)(C) (467-7067) | EACH | 2 | $6,700.00 | $16,000 |
| 103 | Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307) | EACH | 1 | $4,287.00 | $2,000.00 |
| 104 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 104 | $1,400.00 | $1,000.00 |
| 105 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 3 | $1,700.00 | $1,500.00 |
| 106 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 23 | $2,150.00 | $1,500.00 |
| 107 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 158 | $1,800.00 | $1,350.00 |
| 108 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 8 | $2,800.00 | $3,500.00 |
| 109 | Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368) | EACH | 4 | $6,000.00 | $8,500.00 |
| 110 | Removing structure (box culvert) (496-7001) | EACH | 80 | $9,750.00 | $100.00 |
| 111 | Removing structure (set) (496-7004) | EACH | 130 | $500.00 | $225.00 |
| 112 | Removing structure (wingwall) (496-7005) | EACH | 32 | $6,000.00 | $1,500.00 |
| 113 | Removing structure (pipe) (496-7007) | LF | 50,973 | $17.77 | $8.50 |
| 114 | Mobilization (500-7001) | LS | 1 | $17,437,375 | $16,900,000 |
| 115 | Barricades, signs and traffic handling (502-7001) | MO | 40 | $19,800 | $5,000.00 |
| 116 | Portable changeable message sign (503-7002) | EACH | 6 | $12,000 | $17,500 |
| 117 | TMA (stationary) (505-7001) | DAY | 576 | $68.51 | $0.10 |
| 118 | TMA (mobile operation) (505-7003) | DAY | 576 | $350.00 | $1.00 |
| 119 | Construction exits (install) (type 2) (506-7021) | SY | 15,988 | $24.00 | $15.00 |
| 120 | Construction exits (remove) (506-7024) | SY | 15,988 | $25.50 | $1.00 |
| 121 | Temporary sediment control fence (install) (506-7039) | LF | 18,984 | $4.25 | $4.25 |
| 122 | Temporary sediment control fence (remove) (506-7041) | LF | 18,984 | $1.43 | $1.25 |
| 123 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 19,844 | $6.00 | $5.25 |
| 124 | Biodegradable erosion control logs (remove) (506-7046) | LF | 19,844 | $1.80 | $1.25 |
| 125 | Constructing detours (508-7001) | SY | 62,446 | $46.00 | $45.00 |
| 126 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 34,700 | $40.00 | $50.00 |
| 127 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 2,640 | $40.00 | $60.00 |
| 128 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 36,600 | $7.00 | $7.00 |
| 129 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 700 | $9.00 | $7.00 |
| 130 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 34,700 | $10.00 | $8.00 |
| 131 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 2,640 | $10.00 | $8.00 |
| 132 | PCTB (fur&inst)(F-shape or SNGL SLP)type 1 (512-7089) | LF | 44,160 | $25.00 | $38.00 |
| 133 | PCTB (move)(F-shape or SNGL SLP)type 1 (512-7090) | LF | 44,700 | $15.00 | $7.00 |
| 134 | PCTB (remove)(F-shape or SNGL SLP)type 1 (512-7092) | LF | 44,160 | $10.00 | $7.00 |
| 135 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 35,801.10 | $65.00 | $60.00 |
| 136 | Permanent CTB (tran SSCB to SSTR) (mod) (514-7038) | LF | 40 | $634.00 | $250.00 |
| 137 | Landscape pavers (528-7001) | SY | 9,042 | $90.00 | $95.50 |
| 138 | Concrete curb (type II) (529-7002) | LF | 1,962 | $4.00 | $15.50 |
| 139 | Concrete curb & gutter (type II) (529-7009) | LF | 2,685 | $35.00 | $15.50 |
| 140 | Concrete curb (doweled) (529-7012) | LF | 80 | $60.00 | $17.00 |
| 141 | Intersections (ACP) (530-7002) | SY | 2,329 | $46.00 | $95.00 |
| 142 | Driveways (concrete) (530-7006) | SY | 334.20 | $97.50 | $100.00 |
| 143 | Driveways (ACP) (530-7010) | SY | 28,929 | $50.00 | $57.00 |
| 144 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 331,340 | $0.35 | $0.10 |
| 145 | Metal W-beam guard fence (timber post) (540-7001) | LF | 7,937.50 | $28.24 | $29.49 |
| 146 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 7 | $2,500.00 | $2,249.21 |
| 147 | Downstream anchor terminal section (540-7015) | EACH | 39 | $1,490.21 | $2,149.21 |
| 148 | Metal beam guard fence (long span system) (540-7027) | EACH | 100 | $36.00 | $1,749.21 |
| 149 | Remove metal beam guard fence (542-7001) | LF | 1,552 | $3.50 | $2.49 |
| 150 | Remove terminal anchor section (542-7002) | EACH | 2 | $750.00 | $195.49 |
| 151 | Remove downstream anchor terminal (542-7003) | EACH | 2 | $195.50 | $195.49 |
| 152 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 5 | $222.61 | $249.21 |
| 153 | Cable barrier (remove) (543-7037) | LF | 2,370 | $4.25 | $5.49 |
| 154 | Cable barrier terminal section (remove) (543-7038) | EACH | 2 | $470.00 | $549.21 |
| 155 | Guardrail end treatment (install) (544-7001) | EACH | 40 | $3,500.00 | $3,549.21 |
| 156 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 23 | $737.50 | $1,949.21 |
| 157 | Crash cushion attenuator (remove) (545-7004) | EACH | 32 | $655.00 | $749.21 |
| 158 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 6 | $28,000 | $32,749 |
| 159 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 32 | $11,500 | $9,149.21 |
| 160 | Chain link fence (remove) (550-7007) | LF | 4,169 | $7.50 | $5.49 |
| 161 | Wire fence (remove) (552-7011) | LF | 23,450 | $5.00 | $1.00 |
| 162 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 43 | $303.75 | $249.21 |
| 163 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 10 | $350.00 | $349.21 |
| 164 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 2 | $875.00 | $749.21 |
| 165 | Remove RD IL asm (trans-base) (610-7009) | EACH | 47 | $410.45 | $892.95 |
| 166 | In RD IL (U/P) (type 1) (150W EQ) LED (610-7014) | EACH | 24 | $1,365.00 | $1,423.47 |
| 167 | In RD IL (type SP) 38S-12-12(250W EQ)LED (610-7105) | EACH | 7 | $4,500.00 | $6,775.94 |
| 168 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 4 | $4,625.00 | $4,853.47 |
| 169 | In RD IL (type SA) 40T-12 (250W EQ) LED (610-7128) | EACH | 16 | $4,000.00 | $4,911.25 |
| 170 | HI MST IL pole (150 FT)(100 MPH) (613-7006) | EACH | 16 | $51,000 | $82,099 |
| 171 | LED HI MST IL asm (6 fixt) (type B) (614-7003) | EACH | 16 | $39,485 | $46,948 |
| 172 | Replace LED HI MST IL(6 fixt) (type B) (614-7007) | EACH | 2 | $9,000.00 | $8,982.07 |
| 173 | Temporary RD IL setup and remove (617-7001) | EACH | 8 | $6,350.00 | $11,031 |
| 174 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 22,240 | $15.35 | $10.51 |
| 175 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 37,962 | $29.75 | $22.06 |
| 176 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 1,485 | $10.44 | $10.51 |
| 177 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 1,445 | $29.50 | $27.31 |
| 178 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 2,888 | $33.50 | $24.16 |
| 179 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 1,170 | $43.00 | $47.27 |
| 180 | Fiber optic cable road marker (619-7013) | LF | 123 | $226.00 | $31.52 |
| 181 | Electrical conductor (no.14) insulated (620-7002) | LF | 42,100 | $0.80 | $1.47 |
| 182 | Electrical conductor (no.10) insulated (620-7006) | LF | 324 | $1.70 | $2.00 |
| 183 | Electrical conductor (no.8) bare (620-7007) | LF | 775 | $1.88 | $2.10 |
| 184 | Electrical conductor (no.8) insulated (620-7008) | LF | 39,624 | $1.65 | $1.68 |
| 185 | Electrical conductor (no.6) bare (620-7009) | LF | 90 | $1.76 | $2.21 |
| 186 | Electrical conductor (no.6) insulated (620-7010) | LF | 120 | $2.30 | $2.31 |
| 187 | Electrical conductor (no.4) bare (620-7011) | LF | 495 | $2.60 | $3.05 |
| 188 | Electrical conductor (no.4) insulated (620-7012) | LF | 990 | $3.00 | $3.26 |
| 189 | Electrical conductor (no.2) bare (620-7015) | LF | 1,365 | $3.43 | $3.68 |
| 190 | Electrical conductor (no.2) insulated (620-7016) | LF | 3,235 | $4.00 | $4.10 |
| 191 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 637 | $3.46 | $2.73 |
| 192 | ITS GND box(pcast) type 1 (243648)W/aprn (623-7004) | EACH | 123 | $5,000.00 | $6,565.84 |
| 193 | ITS GND box(pcast) type 2 (366048)W/aprn (623-7010) | EACH | 5 | $11,600 | $9,706.93 |
| 194 | Ground box type A (122311)W/apron (624-7002) | EACH | 128 | $928.00 | $1,418.22 |
| 195 | Remove ground box (624-7013) | EACH | 18 | $350.00 | $682.85 |
| 196 | Remove electrical services (628-7002) | EACH | 3 | $241.11 | $325.67 |
| 197 | Elc SRV type A 240/480 060(SS)SS(E)TP(O) (628-7059) | EACH | 18 | $8,000.00 | $6,581.59 |
| 198 | Elc SRV type D 120/240 060(NS)SS(N)TP(O) (628-7157) | EACH | 4 | $8,000.00 | $4,491.03 |
| 199 | Elc SRV type T 120/240 000(NS)GS(L)TS(O) (628-7322) | EACH | 1 | $2,495.00 | $1,943.49 |
| 200 | Elc SRV type T 120/240 000(NS)GS(N)TP(O) (628-7328) | EACH | 2 | $4,000.00 | $2,258.65 |
| 201 | Aluminum signs (type A) (636-7001) | SF | 81 | $30.00 | $35.49 |
| 202 | Aluminum signs (type G) (636-7002) | SF | 2,739 | $26.00 | $28.28 |
| 203 | Aluminum signs (type O) (636-7003) | SF | 1,759 | $23.50 | $46.19 |
| 204 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 118 | $750.00 | $775.49 |
| 205 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 109 | $821.49 | $879.49 |
| 206 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 1 | $925.00 | $1,335.00 |
| 207 | Install small roadside sign support and assembly TYS80(1)SA(U-2EXT) (644-7033) | EACH | 2 | $975.00 | $1,192.49 |
| 208 | Install small roadside sign support and assembly TYS80(1)SB(P) (644-7037) | EACH | 3 | $731.00 | $898.49 |
| 209 | Install small roadside sign support and assembly TYS80(1)SB(T) (644-7040) | EACH | 4 | $825.00 | $1,398.49 |
| 210 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 12 | $2,462.50 | $3,211.49 |
| 211 | Remove SM RD SN sup&AM (644-7073) | EACH | 234 | $132.50 | $49.21 |
| 212 | Install LRSS (struct steel) (647-7001) | LB | 20,480 | $5.35 | $5.56 |
| 213 | Remove lrsa (647-7003) | EACH | 7 | $1,400.00 | $631.31 |
| 214 | Install overhead sign support(35 FT bal tee) (650-7035) | EACH | 2 | $48,750 | $76,531 |
| 215 | Install overhead sign support(35 FT cant) (650-7038) | EACH | 13 | $45,000 | $79,263 |
| 216 | Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003) | EACH | 13 | $60.00 | $49.21 |
| 217 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 30 | $14.50 | $19.49 |
| 218 | Install delineator assembly (D-SY)SZ 1(yflx)GND (658-7023) | EACH | 36 | $75.15 | $49.21 |
| 219 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 14 | $14.50 | $19.49 |
| 220 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 350 | $20.50 | $19.49 |
| 221 | Install delineator assembly (D-DW)SZ 1(WFLX)GND (658-7045) | EACH | 54 | $50.00 | $49.21 |
| 222 | Install delineator assembly (D-DW)SZ 1(BRF)GF2 (658-7048) | EACH | 138 | $10.50 | $24.49 |
| 223 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 46 | $62.50 | $49.21 |
| 224 | Remove delin & object marker assms (658-7078) | EACH | 103 | $17.25 | $9.49 |
| 225 | Work zone pavement marking non-removing (W)4"(broken) (662-7001) | LF | 22,624 | $0.65 | $0.38 |
| 226 | Work zone pavement marking non-removing (W)4"(DOT) (662-7002) | LF | 1,220 | $0.19 | $0.38 |
| 227 | Work zone pavement marking non-removing (W)4"(solid) (662-7004) | LF | 125,425 | $0.40 | $0.38 |
| 228 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 27,264.60 | $1.20 | $0.58 |
| 229 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 141,014.20 | $0.58 | $0.38 |
| 230 | Work zone pavement marking removing (W)4"(broken) (662-7061) | LF | 17,472.80 | $0.55 | $0.72 |
| 231 | Work zone pavement marking removing (W)4"(solid) (662-7064) | LF | 161,358.10 | $0.32 | $0.38 |
| 232 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 16,747.40 | $0.48 | $0.48 |
| 233 | Work zone pavement marking removing (W)12"(DOT) (662-7073) | LF | 570 | $4.50 | $3.50 |
| 234 | Work zone pavement marking removing (Y)4"(solid) (662-7097) | LF | 150,272.90 | $0.32 | $0.38 |
| 235 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 20,688 | $1.70 | $1.34 |
| 236 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 8,546 | $1.25 | $1.44 |
| 237 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 361 | $3.06 | $0.68 |
| 238 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 6,818 | $1.22 | $0.88 |
| 239 | Reflectorized pavement marking type I (W)12"(lane drop)(100MIL) (666-7027) | LF | 1,388 | $4.27 | $1.10 |
| 240 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 2,400 | $3.88 | $1.10 |
| 241 | Reflectorized pavement marking type I(W)(entr gore)(100MIL) (666-7069) | EACH | 16 | $1,500.00 | $1,500.00 |
| 242 | Reflectorized pavement marking type I(W)(exit gore)(100MIL) (666-7072) | EACH | 16 | $1,500.00 | $1,500.00 |
| 243 | Reflectorized pavement marking type I (Y)8"(solid)(100MIL) (666-7114) | LF | 5,433 | $2.45 | $0.94 |
| 244 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 698 | $3.50 | $1.10 |
| 245 | Reflectorized pavement marking type I (W)6"(broken)(090MIL)(callout) (666-7144) | LF | 35,646 | $0.62 | $0.88 |
| 246 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 166,569 | $0.65 | $0.92 |
| 247 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 164,771 | $0.82 | $0.92 |
| 248 | Pavement sler 6" (666-7347) | LF | 38,807 | $0.95 | $0.42 |
| 249 | Pavement sler 8" (666-7348) | LF | 2,724 | $1.56 | $1.10 |
| 250 | Pavement sler 12" (666-7350) | LF | 698 | $1.00 | $2.00 |
| 251 | Pavement sler 24" (666-7352) | LF | 457 | $4.00 | $2.50 |
| 252 | Pavement sler (arrow) (666-7353) | EACH | 14 | $15.00 | $20.00 |
| 253 | Pavement sler (word) (666-7354) | EACH | 8 | $15.00 | $25.00 |
| 254 | Pavement sler (uturn arrow) (666-7358) | EACH | 22 | $90.00 | $25.00 |
| 255 | Prefabricated PM type B (W)(6")(broken)contrast (668-7012) | LF | 1,110 | $9.00 | $20.00 |
| 256 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 726 | $18.00 | $16.00 |
| 257 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 35 | $225.00 | $185.00 |
| 258 | Prefabricated PM type C (W)(uturn arrow) (668-7096) | EACH | 21 | $500.00 | $325.00 |
| 259 | Prefabricated PM type C (W)(number) (668-7102) | EACH | 8 | $336.00 | $325.00 |
| 260 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 54 | $285.00 | $275.00 |
| 261 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 54 | $48.78 | $35.00 |
| 262 | Reflectorized pavement marker type I-A (672-7001) | EACH | 276 | $6.75 | $7.50 |
| 263 | Reflectorized pavement marker type I-C (672-7002) | EACH | 102 | $5.00 | $7.50 |
| 264 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 441 | $5.85 | $7.50 |
| 265 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 4,495 | $6.70 | $5.00 |
| 266 | Eliminating existing PM & markers (4") (677-7001) | LF | 73,302.10 | $0.35 | $0.35 |
| 267 | Eliminating existing PM & markers (8") (677-7004) | LF | 2,725 | $0.85 | $0.65 |
| 268 | Eliminating existing PM & markers (12") (677-7006) | LF | 1,250 | $1.00 | $0.85 |
| 269 | Eliminating existing PM & markers (24") (677-7008) | LF | 695 | $6.70 | $5.00 |
| 270 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 25 | $200.00 | $50.00 |
| 271 | Eliminating existing PM & markers (word) (677-7015) | EACH | 15 | $225.00 | $50.00 |
| 272 | Pavement surface preparation for marking (6") (678-7002) | LF | 38,807 | $0.20 | $0.20 |
| 273 | Pavement surface preparation for marking (8") (678-7004) | LF | 2,724 | $0.57 | $0.30 |
| 274 | Pavement surface preparation for marking (12") (678-7006) | LF | 698 | $1.35 | $0.60 |
| 275 | Pavement surface preparation for marking (24") (678-7008) | LF | 457 | $2.70 | $1.00 |
| 276 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 14 | $50.00 | $50.00 |
| 277 | Pavement surface preparation for marking (uturn arr) (678-7012) | EACH | 8 | $40.00 | $50.00 |
| 278 | Pavement surface preparation for marking (word) (678-7016) | EACH | 22 | $50.00 | $50.00 |
| 279 | Install highway traffic signal (flash beacon) (680-7001) | EACH | 3 | $2,500.00 | $2,573.81 |
| 280 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 12 | $193.00 | $330.92 |
| 281 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 18 | $290.00 | $330.92 |
| 282 | Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010) | LF | 1,515 | $2.83 | $2.89 |
| 283 | Remove RDSD flash beacon assembly (685-7003) | EACH | 1 | $1,177.00 | $1,575.80 |
| 284 | Ins traffic signal PL AM (S)STR(type D) (686-7019) | EACH | 8 | $8,172.00 | $8,824.48 |
| 285 | Ins traffic signal PL AM (S)STR(type D)lum (686-7020) | EACH | 4 | $10,783 | $12,449 |
| 286 | Remove conductor (690-7150) | LF | 8,449 | $1.15 | $1.89 |
| 287 | Full - width mowing (730-7022) | ACRE | 72 | $80.00 | $350.00 |
| 288 | Litter removal (734-7002) | CYC | 6 | $3,500.00 | $3,000.00 |
| 289 | Bridge joint repair (armor) (785-7004) | LF | 336 | $1,000.00 | $150.00 |
| 290 | Bonding course (3007-7001) | GAL | 135,750 | $5.00 | $3.00 |
| 291 | Bird exclusion method (5029-7001) | SF | 155,250 | $10.00 | $1.00 |
| 292 | Install DMS (pole MTD cabinet) (6004-7001) | EACH | 2 | $13,700 | $1,943.49 |
| 293 | ITS pole MNT cab (type 2) (conf 2) (6011-7011) | EACH | 2 | $6,000.00 | $5,840.97 |
| 294 | ITS pole(40 FT)(110 MPH)(W/stiff) (6011-7015) | EACH | 1 | $14,000 | $13,289 |
| 295 | ITS pole(55 FT)(140 MPH)(W/stiff) (6011-7016) | EACH | 1 | $19,750 | $24,005 |
| 296 | Installation of cellular modem (6015-7001) | EACH | 4 | $2,000.00 | $787.90 |
| 297 | CCTV field equipment (digital) (6018-7002) | EACH | 2 | $9,150.00 | $8,714.18 |
| 298 | ITS com CBL (ethernet) (6018-7004) | LF | 155 | $3.40 | $3.36 |
| 299 | Remove high mast lighting assembly (6019-7001) | EACH | 1 | $15,300 | $22,586 |
| 300 | FO splice enclosure (type 2) (6027-7003) | EACH | 5 | $2,500.00 | $2,468.75 |
| 301 | ITS system support equipment (6037-7001) | LS | 1 | $31,331 | $19,435 |
| 302 | 16IN steel casing (open cut) (7025-7001) | LF | 310 | $180.00 | $175.00 |
| 303 | 24IN steel casing (open cut) (7025-7002) | LF | 72 | $200.00 | $275.00 |
| 304 | Blow off valve (2IN) (7025-7003) | EACH | 33 | $6,500.00 | $3,000.00 |
| 305 | Connect to existing water line (7025-7004) | EACH | 15 | $4,000.00 | $2,500.00 |
| 306 | Cutting and capping abandoned waterline (7025-7005) | EACH | 15 | $1,966.35 | $1,500.00 |
| 307 | Fire hydrant assembly (7025-7006) | EACH | 37 | $6,500.00 | $8,500.00 |
| 308 | Gate valve wbox (8IN) (7025-7007) | EACH | 52 | $4,500.00 | $2,900.00 |
| 309 | Gate valve wbox (12IN) (7025-7008) | EACH | 24 | $7,012.50 | $5,500.00 |
| 310 | JCK tun bor or aug CSG (steel) (24IN) (7025-7009) | LF | 1,786 | $505.07 | $375.00 |
| 311 | Service line (long side) (1-1/2IN to 2) (7025-7010) | EACH | 1 | $4,799.01 | $17,000 |
| 312 | Service line (SHRT side) (1-1/2IN to 2) (7025-7011) | EACH | 77 | $2,074.71 | $2,500.00 |
| 313 | Water main pipe (PVC)(8IN)(DR18)(C900) (7025-7012) | LF | 47,237 | $73.83 | $37.00 |
| 314 | Water main pipe (PVC)(12IN)(DR18)(C900) (7025-7013) | LF | 16,072 | $132.09 | $65.00 |
| 315 | Wet connection (7025-7014) | EACH | 3 | $5,000.00 | $8,500.00 |
| 316 | Connect to existing water meter (7025-7015) | EACH | 20 | $2,196.00 | $1,500.00 |
| 317 | Removing & relocate water meter and vault (7025-7016) | EACH | 63 | $2,530.28 | $3,500.00 |
| 318 | Removing asbestos cement waterline (7025-7017) | LF | 15,053 | $30.00 | $15.95 |
| 319 | Water main pipe (PVC)(2IN)(DR18)(C900) (7025-7018) | LF | 26 | $50.00 | $225.00 |
| 320 | Thermoplastic pipe (PP) (18") (468-7001) | LF | 2,466 | $93.76 | $85.00 |
| 321 | Thermoplastic pipe (PP) (24") (468-7002) | LF | 7,256 | $193.73 | $80.00 |
| 322 | Thermoplastic pipe (PP) (30") (468-7003) | LF | 561 | $215.00 | $105.00 |
| 323 | Thermoplastic pipe (PP) (36") (468-7004) | LF | 72 | $200.00 | $200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.