| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Knife River Corporation - South | $18,290,693 | Low | +7.0% |
| 2 | Larry Young Paving, Inc. | $18,459,645 | +1.0% | +8.0% |
| 3 | Big Creek Construction, LTD. | $19,287,262 | +5.0% | +13% |
| 4 | James Construction Group, LLC | $19,669,872 | +8.0% | +15% |
| 5 | A. L. Helmcamp, Inc. | $19,852,633 | +9.0% | +16% |
Engineer's estimate: $17,046,795.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Knife River Corporation - South | 2. Larry Young Paving, Inc. | 3. Big Creek Construction, LTD. | 4. James Construction Group, LLC | 5. A. L. Helmcamp, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 280 | $500.00 | $485.00 | $610.00 | $1,000.00 | $3,397.00 | $1,000.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 97 | $25.00 | $12.00 | $16.00 | $25.00 | $17.15 | $82.00 |
| 3 | Remove (2"-8") TRT/untrt base & asphalt pavement (105-7053) | SY | 83,219 | $8.00 | $1.50 | $2.00 | $3.50 | $2.93 | $3.30 |
| 4 | Excavation (roadway) (110-7001) | CY | 33,864 | $9.00 | $7.65 | $16.00 | $19.00 | $2.93 | $10.00 |
| 5 | Embankment (final)(OC)(type C) (132-7005) | CY | 40,581 | $9.00 | $21.70 | $17.00 | $19.00 | $21.69 | $10.00 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 163,059 | $1.00 | $0.64 | $0.70 | $1.00 | $1.43 | $1.25 |
| 7 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 163,059 | $0.30 | $0.18 | $0.20 | $0.20 | $0.18 | $0.19 |
| 8 | Broadcast seed (temporary_warm) (164-7005) | SY | 81,532 | $0.17 | $0.12 | $0.20 | $0.14 | $0.12 | $0.13 |
| 9 | Broadcast seed (temporary_cool) (164-7006) | SY | 81,532 | $0.17 | $0.12 | $0.20 | $0.14 | $0.12 | $0.13 |
| 10 | Vegetative watering (168-7001) | TGL | 1,631 | $20.00 | $100.00 | $44.00 | $10.00 | $61.91 | $20.00 |
| 11 | Soil ret BLKT(SL_mod_clay_short) (169-7001) | SY | 110,560 | $2.00 | $0.90 | $1.00 | $1.00 | $0.88 | $0.90 |
| 12 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 135,417 | $14.00 | $16.40 | $17.00 | $16.00 | $17.15 | $17.00 |
| 13 | Cement (275-7001) | TON | 3,414 | $230.00 | $210.00 | $230.00 | $220.00 | $217.43 | $200.00 |
| 14 | Cement TRT (new base)(8") (275-7011) | SY | 135,417 | $2.00 | $1.10 | $2.00 | $3.00 | $3.17 | $2.30 |
| 15 | Cement treat (subgrade) (8") (275-7017) | SY | 139,878 | $4.50 | $1.10 | $2.00 | $2.00 | $2.74 | $2.30 |
| 16 | Asphalt (RC-250) (316-7016) | GAL | 28,716 | $4.50 | $5.25 | $4.75 | $4.75 | $5.35 | $5.00 |
| 17 | Aggregate (type-B or L, GR-5) (316-7251) | CY | 1,045 | $130.00 | $170.00 | $150.00 | $135.00 | $186.85 | $200.00 |
| 18 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 21,816 | $130.00 | $133.00 | $140.00 | $112.00 | $135.34 | $150.00 |
| 19 | Cut & restoring pavement (400-7006) | SY | 74 | $250.00 | $55.00 | $65.00 | $50.00 | $61.31 | $205.00 |
| 20 | Cem stabil BKFL (400-7010) | CY | 939 | $185.00 | $137.00 | $100.00 | $300.00 | $121.00 | $196.00 |
| 21 | Flowable backfill (401-7001) | CY | 73 | $395.00 | $595.00 | $270.00 | $350.00 | $247.13 | $360.00 |
| 22 | Trench excavation protection (402-7001) | LF | 177 | $19.00 | $40.00 | $1.75 | $50.00 | $2.98 | $12.00 |
| 23 | Temporary special shoring (403-7001) | SF | 3,475 | $18.00 | $57.00 | $25.00 | $35.00 | $57.83 | $47.00 |
| 24 | Sheet piling (PZ - 27) (407-7002) | SF | 5,340 | $65.00 | $65.00 | $55.00 | $80.00 | $61.87 | $64.00 |
| 25 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 64 | $355.00 | $199.00 | $230.00 | $350.00 | $198.77 | $320.00 |
| 26 | Class A concrete (flume) (420-7006) | CY | 135 | $880.00 | $775.00 | $620.00 | $700.00 | $1,037.02 | $950.00 |
| 27 | Class C concrete (culvert) (420-7152) | CY | 56 | $2,000.00 | $1,040.00 | $1,200.00 | $1,775.00 | $1,609.96 | $3,200.00 |
| 28 | Retaining wall (spread footing) (423-7015) | SF | 27,347 | $76.00 | $123.00 | $100.00 | $107.00 | $84.80 | $106.00 |
| 29 | Riprap (concrete)(4 in) (432-7001) | CY | 2,050 | $550.00 | $575.00 | $640.00 | $700.00 | $451.21 | $690.00 |
| 30 | Riprap (mow strip)(4 in) (432-7013) | CY | 653 | $650.00 | $920.00 | $620.00 | $700.00 | $675.00 | $890.00 |
| 31 | Riprap (stone protection)(18 in) (432-7043) | CY | 152 | $200.00 | $215.00 | $210.00 | $190.00 | $123.94 | $260.00 |
| 32 | RC pipe (CL III)(18 in) (464-7003) | LF | 880 | $70.00 | $70.00 | $76.00 | $95.00 | $104.60 | $64.00 |
| 33 | RC pipe (CL III)(24 in) (464-7005) | LF | 245 | $125.00 | $92.00 | $100.00 | $120.00 | $117.64 | $150.00 |
| 34 | RC pipe (CL III)(30 in) (464-7007) | LF | 28 | $150.00 | $100.00 | $130.00 | $130.00 | $114.68 | $200.00 |
| 35 | RC pipe (CL III)(60 in) (464-7013) | LF | 12 | $400.00 | $700.00 | $470.00 | $400.00 | $579.86 | $425.00 |
| 36 | RC pipe (CL IV)(18 in) (464-7019) | LF | 200 | $100.00 | $80.00 | $120.00 | $135.00 | $105.37 | $71.00 |
| 37 | RC pipe (CL IV)(24 in) (464-7021) | LF | 8 | $197.00 | $400.00 | $180.00 | $180.00 | $210.23 | $158.00 |
| 38 | RC pipe (CL IV)(36 in) (464-7024) | LF | 29 | $247.00 | $475.00 | $180.00 | $350.00 | $283.31 | $260.00 |
| 39 | RC pipe (CL V)(30 in) (464-7036) | LF | 3 | $200.00 | $600.00 | $670.00 | $1,085.00 | $391.27 | $220.00 |
| 40 | Headwall (CH - PW - 0) (diameter= 36 in) (466-7105) | EACH | 2 | $11,550 | $17,000 | $11,000 | $10,000 | $16,973 | $11,000 |
| 41 | Headwall (CH - PW - 0) (diameter= 60 in) (466-7109) | EACH | 1 | $18,150 | $26,000 | $29,000 | $22,900 | $34,703 | $23,000 |
| 42 | Headwall (CH - PW - S) (diameter= 24 in) (466-7116) | EACH | 1 | $10,000 | $16,000 | $8,300.00 | $8,200.00 | $12,519 | $6,000.00 |
| 43 | Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305) | EACH | 2 | $1,500.00 | $1,400.00 | $1,200.00 | $1,100.00 | $2,395.24 | $950.00 |
| 44 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 54 | $1,400.00 | $1,475.00 | $1,500.00 | $1,450.00 | $3,228.09 | $1,000.00 |
| 45 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 3 | $1,650.00 | $1,940.00 | $1,600.00 | $1,650.00 | $2,762.02 | $2,200.00 |
| 46 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $1,850.00 | $2,000.00 | $1,800.00 | $1,710.00 | $3,920.67 | $2,200.00 |
| 47 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 6 | $2,200.00 | $1,900.00 | $2,000.00 | $2,160.00 | $3,918.76 | $2,600.00 |
| 48 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 2 | $3,700.00 | $2,800.00 | $3,200.00 | $3,070.00 | $4,875.57 | $3,600.00 |
| 49 | Jack bor or tun pipe(18 in)(RC)(CL III) (476-7010) | LF | 56 | $1,000.00 | $1,540.00 | $1,700.00 | $1,470.00 | $1,439.80 | $1,600.00 |
| 50 | Jack bor or tun pipe(36 in)(RC)(CL III) (476-7013) | LF | 75 | $1,700.00 | $1,980.00 | $2,300.00 | $1,900.00 | $1,851.96 | $2,000.00 |
| 51 | Jack bor or tun pipe(24 in)(RC)(CL IV) (476-7021) | LF | 72 | $1,200.00 | $1,600.00 | $1,800.00 | $1,550.00 | $1,512.14 | $1,600.00 |
| 52 | Jack bor or tun pipe(36 in)(RC)(CL IV) (476-7023) | LF | 116 | $1,800.00 | $2,000.00 | $2,300.00 | $1,900.00 | $1,984.14 | $2,200.00 |
| 53 | Jack bor or tun pipe(30 in)(RC)(CL V) (476-7032) | LF | 72 | $1,600.00 | $1,700.00 | $2,000.00 | $1,700.00 | $1,748.72 | $2,000.00 |
| 54 | Clean existing culverts (480-7001) | EACH | 2 | $5,000.00 | $12,500 | $3,000.00 | $2,100.00 | $3,834.75 | $2,200.00 |
| 55 | Removing structure (set) (496-7004) | EACH | 28 | $600.00 | $575.00 | $430.00 | $375.00 | $143.01 | $780.00 |
| 56 | Removing structure (wingwall) (496-7005) | EACH | 2 | $2,700.00 | $2,600.00 | $2,600.00 | $3,200.00 | $3,141.62 | $1,600.00 |
| 57 | Removing structure (headwall) (496-7006) | EACH | 2 | $2,700.00 | $2,300.00 | $2,600.00 | $2,400.00 | $3,141.62 | $1,600.00 |
| 58 | Removing structure (pipe) (496-7007) | LF | 280 | $35.00 | $69.00 | $35.00 | $20.00 | $19.04 | $53.00 |
| 59 | Remove STR (driveway culvert) (496-7038) | EACH | 31 | $500.00 | $1,500.00 | $630.00 | $450.00 | $507.31 | $1,600.00 |
| 60 | Mobilization (500-7001) | LS | 1 | $1,262,755 | $906,000 | $1,350,000 | $1,900,000 | $1,900,000 | $1,750,000 |
| 61 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $12,000 | $25,000 | $16,000 | $5,000.00 | $29,002 | $25,000 |
| 62 | Portable changeable message sign (503-7002) | EACH | 4 | $12,000 | $4,700.00 | $8,000.00 | $7,750.00 | $12,152 | $15,000 |
| 63 | TMA (stationary) (505-7001) | DAY | 148 | $225.00 | $550.00 | $250.00 | $400.00 | $781.50 | $300.00 |
| 64 | TMA (mobile operation) (505-7003) | DAY | 17 | $600.00 | $1,000.00 | $990.00 | $800.00 | $1,193.79 | $300.00 |
| 65 | Rock filter dams (install) (type 2) (506-7002) | LF | 4,200 | $40.00 | $34.00 | $42.00 | $40.00 | $34.00 | $36.00 |
| 66 | Rock filter dams (remove) (506-7011) | LF | 4,200 | $16.00 | $10.00 | $12.00 | $5.00 | $10.00 | $11.00 |
| 67 | Construction exits (install) (type 1) (506-7020) | SY | 223 | $30.00 | $28.00 | $35.00 | $30.00 | $28.00 | $28.00 |
| 68 | Construction exits (remove) (506-7024) | SY | 223 | $10.00 | $12.00 | $15.00 | $5.00 | $12.00 | $12.00 |
| 69 | Temporary sediment control fence (install) (506-7039) | LF | 6,540 | $4.00 | $3.25 | $4.00 | $4.00 | $3.25 | $3.30 |
| 70 | Temporary sediment control fence (remove) (506-7041) | LF | 6,540 | $1.20 | $1.00 | $1.25 | $1.00 | $1.00 | $1.10 |
| 71 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 3,330 | $7.60 | $6.25 | $7.75 | $7.00 | $6.25 | $6.50 |
| 72 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,330 | $1.40 | $1.00 | $1.25 | $1.00 | $1.00 | $1.00 |
| 73 | Constructing detours (508-7001) | SY | 1,170 | $65.00 | $146.00 | $93.00 | $150.00 | $170.07 | $120.00 |
| 74 | One-way traffic control (port traffic signal) (510-7003) | MO | 2 | $5,500.00 | $5,000.00 | $6,100.00 | $6,000.00 | $7,063.32 | $12,000 |
| 75 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 160 | $40.00 | $50.00 | $51.00 | $27.00 | $84.27 | $136.00 |
| 76 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 800 | $19.00 | $15.00 | $17.00 | $15.00 | $24.72 | $75.00 |
| 77 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 160 | $17.00 | $40.00 | $21.00 | $25.00 | $29.00 | $140.00 |
| 78 | Driveways (concrete) (530-7006) | SY | 77 | $130.00 | $160.00 | $110.00 | $140.00 | $107.04 | $220.00 |
| 79 | Driveways (ACP) (530-7010) | SY | 2,854 | $50.00 | $80.00 | $62.00 | $50.00 | $86.45 | $100.00 |
| 80 | Metal W-beam guard fence (timber post) (540-7001) | LF | 10,775 | $20.00 | $20.50 | $29.00 | $30.00 | $23.00 | $22.00 |
| 81 | Downstream anchor terminal section (540-7015) | EACH | 22 | $1,500.00 | $1,175.00 | $2,000.00 | $1,700.00 | $1,500.00 | $1,200.00 |
| 82 | Guardrail end treatment (install) (544-7001) | EACH | 16 | $3,500.00 | $2,875.00 | $3,800.00 | $3,250.00 | $3,900.00 | $3,000.00 |
| 83 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 10 | $2,000.00 | $1,500.00 | $2,300.00 | $2,000.00 | $2,200.00 | $1,000.00 |
| 84 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,500.00 | $1,500.00 | $1,100.00 | $1,500.00 | $1,250.00 | $1,000.00 |
| 85 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $9,500.00 | $7,000.00 | $10,000 | $10,000 | $8,750.00 | $9,700.00 |
| 86 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 15 | $366.00 | $385.00 | $480.00 | $500.00 | $230.00 | $310.00 |
| 87 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 8 | $5,500.00 | $4,950.00 | $5,600.00 | $6,500.00 | $4,931.09 | $5,900.00 |
| 88 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 605 | $15.00 | $13.75 | $9.25 | $20.00 | $13.62 | $17.00 |
| 89 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 495 | $20.00 | $19.50 | $17.00 | $35.00 | $19.42 | $30.00 |
| 90 | Electrical conductor (no.6) insulated (620-7010) | LF | 3,300 | $2.50 | $3.00 | $1.50 | $3.00 | $2.97 | $3.00 |
| 91 | Ground box type D (162922)W/apron (624-7008) | EACH | 16 | $1,500.00 | $1,325.00 | $1,900.00 | $2,000.00 | $1,316.53 | $1,800.00 |
| 92 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 4 | $8,500.00 | $7,970.00 | $6,600.00 | $10,000 | $7,963.85 | $9,000.00 |
| 93 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 30 | $720.00 | $550.00 | $690.00 | $650.00 | $710.00 | $700.00 |
| 94 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 7 | $720.00 | $655.00 | $820.00 | $750.00 | $845.00 | $800.00 |
| 95 | Install small roadside sign support and assembly type 10BWG(1)SA(T-2EXT) (644-7005) | EACH | 2 | $800.00 | $765.00 | $950.00 | $850.00 | $900.00 | $830.00 |
| 96 | Remove SM RD SN sup&AM (644-7073) | EACH | 35 | $110.00 | $115.00 | $140.00 | $150.00 | $100.00 | $110.00 |
| 97 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 237 | $40.00 | $35.00 | $44.00 | $40.00 | $30.00 | $33.00 |
| 98 | Install object marker assembly (OM-2Z)(WFLX)SRF (658-7060) | EACH | 70 | $110.00 | $115.00 | $140.00 | $150.00 | $84.00 | $135.00 |
| 99 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 216 | $5.00 | $10.00 | $12.00 | $12.00 | $10.00 | $11.00 |
| 100 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 111,596 | $0.40 | $0.50 | $0.60 | $0.60 | $0.50 | $0.52 |
| 101 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 144 | $7.00 | $10.00 | $12.00 | $12.00 | $10.00 | $11.00 |
| 102 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,395 | $1.50 | $1.00 | $1.00 | $1.50 | $2.00 | $1.10 |
| 103 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 100 | $2.00 | $2.00 | $2.50 | $2.50 | $2.00 | $2.10 |
| 104 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,640 | $1.50 | $2.00 | $2.50 | $2.50 | $2.00 | $2.10 |
| 105 | Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265) | LF | 55,305 | $1.00 | $1.00 | $1.25 | $1.20 | $0.99 | $1.05 |
| 106 | Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269) | LF | 13,615 | $1.25 | $1.00 | $1.25 | $1.20 | $0.99 | $1.05 |
| 107 | Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273) | LF | 6,230 | $1.30 | $1.00 | $1.25 | $1.20 | $0.99 | $1.05 |
| 108 | PRFB rumble strip (BLK)(1')(centerline) (668-7002) | LF | 25,640 | $3.50 | $1.00 | $1.25 | $1.50 | $1.00 | $1.05 |
| 109 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 140 | $20.00 | $20.00 | $25.00 | $25.00 | $20.00 | $21.00 |
| 110 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 8 | $309.00 | $330.00 | $410.00 | $350.00 | $330.00 | $350.00 |
| 111 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 8 | $385.00 | $380.00 | $470.00 | $400.00 | $380.00 | $400.00 |
| 112 | Reflectorized pavement marker type I-C (672-7002) | EACH | 88 | $6.00 | $10.00 | $12.00 | $12.00 | $10.00 | $11.00 |
| 113 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 698 | $5.00 | $10.00 | $12.00 | $12.00 | $10.00 | $11.00 |
| 114 | Bonding course (3007-7001) | GAL | 13,208 | $4.00 | $5.40 | $6.25 | $4.70 | $5.45 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.