TxDOT contract A00133456 bid tabulation

Bridge Replacement, FM 636 (At Willow Creek to .). Let by Texas DOT on September 5, 2025, Navarro, Dallas District. 8 bids received; low bid $9,649,382 by Indus Road & Bridge, Inc., -8.0% against the engineer's estimate of $10,486,887.

Owner
Texas DOT
Letting
05 SEP 2025
Pay items
107
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Indus Road & Bridge, Inc.$9,649,382Low-8.0%
2Skyline Bridge LLC$9,894,124+3.0%-6.0%
3Highway 19 Construction LLC$9,974,224+3.0%-5.0%
4Hodges and Son Construction Company, Inc.$11,175,915+16%+7.0%
5A. L. Helmcamp, Inc.$11,812,159+22%+13%
6Talbert Companies LLC$11,932,161+24%+14%
7Grey Sky Construction LLC$11,996,385+24%+14%
8Harper Brothers Construction LLC$12,490,379+29%+19%
TxDOT contract A00133456: bids by rank

Engineer's estimate: $10,486,887.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Indus Road & Bridge, Inc.2. Skyline Bridge LLC3. Highway 19 Construction LLC4. Hodges and Son Construction Company, Inc.5. A. L. Helmcamp, Inc.6. Talbert Companies LLC
1Preparing row (100-7002)STA28$8,000.00$14,000$2,000.00$5,000.00$4,000.00$250.00$3,300.00
2Removing concrete (riprap) (104-7006)SY871$32.00$15.00$10.00$25.00$14.00$60.00$33.00
3Excavation (roadway) (110-7001)CY5,740$25.00$18.00$18.00$20.00$10.00$11.00$22.00
4Embankment (final)(DC)(type C1) (132-7008)CY13,045$25.00$26.00$27.00$30.00$25.00$35.00$33.00
5Embankment (final)(DC)(type C2) (132-7010)CY801$75.00$327.00$40.00$50.00$25.00$110.00$33.00
6Compost manuf topsoil (4") (161-7002)SY22,220$3.00$2.20$4.00$2.00$2.00$2.00$1.08
7Drill seed (permanent_rural_clay) (164-7010)SY22,220$0.50$0.40$0.75$0.45$0.50$0.90$0.42
8Drill seed (temporary_warm_cool) (164-7015)SY22,220$0.50$0.40$0.75$0.45$0.50$0.80$0.40
9Vegetative watering (168-7001)TGL6,610.90$20.00$1.00$0.25$10.00$1.00$3.00$17.60
10FL BS (compacted in place)(type D GR 1-2) (10") (247-7102)SY2,102$35.00$55.00$35.00$60.00$31.00$38.50
11FL BS (compacted in place)(type D GR 1-2) (12") (247-7125)SY7,651$30.00$36.00$45.00$36.00$60.00$37.00$38.50
12FL BS (roadway del)(type D GR 1-2)(final pos) (247-7271)CY1,110$100.00$96.00$100.00$85.00$85.00$120.00$289.30
13Rework BS metal (type C)(6")(ord comp) (251-7049)SY2,218$3.00$6.00$14.00$10.00$25.00$9.00$22.00
14Rework BS metal (type C)(8")(ord comp) (251-7051)SY5,433$7.00$10.00$5.00$25.00$4.00$33.00
15Lime (com or QK)(slurry) or QK(dry) (260-7001)TON57.22$360.00$400.00$350.00$350.00$450.00$375.22
16Lime TRT (existing material)(8") (260-7007)SY2,102$10.00$30.00$10.00$15.00$15.00$22.00
17Cement (275-7001)TON63.80$250.00$260.00$350.00$320.00$400.00$290.00$254.84
18Cement TRT (existing material & new base)(6") (275-7006)SY2,218$2.50$5.00$24.00$10.00$15.00$18.00$22.00
19Cement TRT (existing material & new base)(8") (275-7007)SY5,433$5.50$22.00$7.00$15.00$18.00$27.50
20Salvage, haul & stockpile reclaimed asphalt PV (3") (305-7016)SY1,724$6.50$15.00$15.00$25.00$8.00$4.40
21Prime coat (multi option) (310-7015)GAL411$24.00$29.00$22.00$20.00$16.00$24.20
22Emuls asphalt (prime)(AE-P) (314-7017)GAL1,531$7.00$28.00$31.00$25.00$15.00$14.00$27.50
23Asphalt (CRS-2P) (316-7012)GAL4,642$6.50$30.00$29.50$27.00$10.00$6.00$30.25
24Asphalt (RC-250) (316-7016)GAL714$4.50$56.00$55.00$51.00$15.00$13.00$56.10
25Asphalt (AC-15P, AC-20-5TR or AC-20XP) (316-7071)GAL3,826$5.50$28.00$30.00$25.00$15.00$7.00$27.50
26Aggregate (type-B, GR-3)(sac-B) (316-7171)CY48$150.00$1,200.00$1,400.00$1,100.00$1,500.00$555.00$1,210.00
27Aggregate (type-B, GR-5)(sac-B) (316-7175)CY21$120.00$1,400.00$1,500.00$1,220.00$1,500.00$1,100.00$1,342.00
28Aggregate (type-PB, GR-4)(sac-B) (316-7211)CY65$150.00$1,490.00$1,600.00$1,325.00$1,000.00$1,200.00$1,457.50
29SP mixes SP-C sac-B PG64-22 (344-7011)TON339$266.00$325.00$244.00$250.00$270.00$268.40
30Tack coat (344-7077)GAL123$1.70$5.00$2.00$10.00$12.00$1.65
31Cem stabil BKFL (400-7010)CY151$250.00$273.00$325.00$350.00$300.00$350.00$330.00
32Trench excavation protection (402-7001)LF1,871$10.00$9.00$8.00$10.00$5.00$13.00$9.90
33Temporary special shoring (403-7001)SF8,106$40.00$33.00$12.50$55.00$25.00$75.00$49.50
34Drilled shaft (24 in) (416-7004)LF2,235$225.00$184.00$275.00$300.00$155.00$300.00$108.94
35Drilled shaft (30 in) (416-7005)LF320$216.00$300.00$350.00$175.00$420.00$117.02
36Class C concrete (abutment)(HPC) (420-7013)CY115.20$1,500.00$1,220.00$1,400.00$1,300.00$2,000.00$4,000.00$1,705.00
37Class C concrete (cap)(HPC) (420-7023)CY101.70$1,500.00$1,430.00$1,800.00$1,550.00$2,200.00$4,200.00$1,925.00
38Class C concrete (column)(HPC) (420-7039)CY57.60$2,000.00$1,700.00$2,000.00$1,200.00$2,200.00$3,200.00$1,925.00
39Reinforced concrete slab (HPC) (422-7002)SF16,770$26.00$31.00$28.00$25.00$24.00$48.00$29.70
40Approach slab (422-7013)CY277$800.00$922.00$800.00$800.00$1,000.00$1,200.00$935.00
41Retaining wall (MSE) (423-7001)SF3,537$70.00$125.00$85.00$120.00$150.00$141.90
42Prestressed concrete slab beam (4SB12) (425-7016)LF1,726.02$250.00$214.00$240.00$250.00$290.00$240.00$190.07
43Prestressed concrete slab beam (5SB12) (425-7017)LF1,844.52$270.00$221.00$240.00$250.00$290.00$240.00$190.07
44Riprap (mow strip)(4 in) (432-7013)CY111.20$750.00$630.00$750.05$500.00$700.00$750.00$880.00
45Riprap (stone common)(dry)(18 in) (432-7033)CY322$132.00$130.00$130.00$160.00$130.00$220.00
46Riprap (stone protection)(24 in) (432-7045)CY2,146$127.00$130.00$130.00$180.00$120.00$231.00
47Riprap (stone protection)(30 in) (432-7047)CY5,929$220.00$127.00$141.00$135.00$242.00$120.00$231.00
48Riprap (stone protection)(36 in) (432-7048)CY2,761$127.00$150.00$140.00$300.00$120.00$231.00
49Rail (type T221) (450-7004)LF332$120.00$165.00$180.00$170.00$180.00$209.00
50Rail (type T223)(HPC) (450-7009)LF850$150.00$125.00$175.00$220.00$170.00$240.00$220.00
51Type A joint (454-7001)LF413$165.00$55.00$95.00$180.00$100.00$52.00$132.00
52RC pipe (CL III)(24 in) (464-7005)LF80$115.00$135.00$100.00$110.00$120.00$110.00$143.00
53RC pipe (CL III)(30 in) (464-7007)LF30$175.00$150.00$170.00$125.00$225.00$176.00
54Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH4$1,700.00$2,600.00$3,500.00$2,690.00$3,500.00$1,300.00$2,420.00
55Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348)EACH1$5,000.00$6,000.00$5,870.00$3,500.00$2,900.00$6,050.00
56Removing structure (set) (496-7004)EACH2$1,000.00$500.00$500.00$500.00$1,600.00$660.00
57Removing structure (pipe) (496-7007)LF65$25.00$30.00$20.00$50.00$10.00$95.00$30.80
58Removing structure (bridge 0 - 99 FT length) (496-7009)EACH3$35,000$23,000$30,000$50,000$36,000$95,000$44,000
59Removing structure (bridge 100 - 499 FT length) (496-7010)EACH1$40,000$50,000$50,000$50,000$150,000$55,000
60Mobilization (500-7001)LS1$930,000$961,039$800,000$400,000$1,015,000$1,100,000$1,171,733
61Barricades, signs and traffic handling (502-7001)MO35$6,500.00$7,700.00$2,000.00$5,000.00$2,500.00$5,050.00$5,500.00
62TMA (stationary) (505-7001)DAY4$215.00$400.00$400.00$1,000.00$350.00$450.00$300.06
63TMA (mobile operation) (505-7003)DAY4$200.00$800.00$150.00$1,000.00$350.00$780.00$434.13
64Rock filter dams (install) (type 2) (506-7002)LF709$45.00$40.00$40.00$45.00$1.00$41.00$47.94
65Rock filter dams (install) (type 3) (506-7003)LF260$80.00$90.00$55.00$65.00$1.00$80.00$94.90
66Rock filter dams (remove) (506-7011)LF969$15.00$12.00$5.00$15.00$1.00$13.00$22.65
67Construction exits (install) (type 1) (506-7020)SY1,956$35.00$40.00$15.00$25.00$1.00$35.00$39.37
68Construction exits (remove) (506-7024)SY1,956$12.00$12.00$5.00$15.00$1.00$10.00$15.31
69Temporary sediment control fence (install) (506-7039)LF7,230$4.00$4.00$3.50$4.00$1.00$4.30$5.49
70Temporary sediment control fence (remove) (506-7041)LF7,230$1.00$1.20$1.00$1.00$1.00$1.00$1.76
71Biodegradable erosion control logs (install) (12") (506-7044)LF440$6.00$7.00$12.00$10.00$5.00$6.50$8.11
72Biodegradable erosion control logs (remove) (506-7046)LF440$1.50$1.40$6.00$1.00$1.00$2.20$2.43
73Constructing detours (508-7001)SY1,565$125.00$115.00$135.00$180.00$100.00$110.00$110.00
74One-way traffic control (port traffic signal) (510-7003)MO35$5,500.00$3,300.00$3,000.00$7,500.00$4,000.00$5,500.00$6,285.72
75Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005)LF4,560$45.00$40.00$49.00$75.00$80.00$62.00$59.16
76Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029)LF2,250$15.00$8.00$50.00$25.00$20.00$22.00$18.46
77Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053)LF4,560$15.00$14.00$11.00$25.00$35.00$25.00$25.45
78Driveways (ACP) (530-7010)SY240$60.00$156.00$150.00$70.00$50.00$125.00$104.50
79Mill rumble strips (asphalt) (centerline) (533-7002)LF450$14.00$10.00$6.00$30.00$9.00$9.35
80Right of way markers (538-7001)EACH25$400.00$230.00$500.00$100.00$80.00$900.00$476.15
81Metal W-beam guard fence (steel post) (540-7002)LF1,525$26.00$32.00$34.00$27.00$30.00$30.00$31.35
82Metal beam guard fence trans (thrie-beam) (540-7005)EACH13$2,300.00$2,500.00$2,000.00$1,850.00$2,000.00$2,300.00$2,420.00
83Short radius (28") (540-7013)LF42$50.00$34.00$150.00$55.00$35.00$32.00$33.00
84Downstream anchor terminal section (540-7015)EACH2$1,500.00$1,300.00$2,000.00$2,100.00$1,500.00$1,300.00$1,320.00
85Remove metal beam guard fence (542-7001)LF1,600$3.50$4.50$5.00$3.00$2.00$4.00$4.40
86RM metal beam guard fence trans (thrie-beam) (542-7004)EACH16$350.00$255.00$250.00$2,750.00$100.00$270.00$275.00
87Guardrail end treatment (install) (544-7001)EACH13$3,200.00$3,000.00$3,400.00$3,200.00$3,000.00$3,100.00$3,245.00
88Guardrail end treatment (remove) (544-7003)EACH16$350.00$255.00$500.00$350.00$500.00$260.00$275.00
89Crash cushion attenuator (move & reset) (545-7002)EACH8$1,700.00$1,250.00$2,000.00$2,000.00$2,500.00$1,300.00$1,320.00
90Crash cushion attenuator (remove) (545-7004)EACH10$900.00$900.00$1,000.00$2,500.00$1,000.00$900.00$935.00
91Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH11$9,000.00$9,000.00$9,250.00$7,500.00$9,000.00$8,000.00$8,250.00
92Pipe underdrains (type 7) (6") (556-7007)LF358$42.00$100.00$35.00$40.00$42.00$66.00
93Mailbox install-S (TWW-post) type 4 (560-7008)EACH1$312.00$750.00$350.00$2,500.00$980.00$341.00
94Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH8$725.00$660.00$1,200.00$850.00$2,000.00$1,300.00$825.00
95Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH33$25.00$42.00$30.00$35.00$45.00$45.00$44.00
96Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH37$30.00$46.00$30.00$35.00$45.00$48.00$44.00
97Work zone pavement marking removing (reflectorized) type II-A-A (662-7051)EACH217$5.50$7.00$6.00$8.00$10.00$5.50$4.79
98Work zone pavement marking removing (W)4"(solid) (662-7064)LF17,739$1.50$1.50$1.50$2.50$2.50$1.10$0.92
99Work zone pavement marking removing (W)24"(solid) (662-7077)LF120$12.00$10.00$15.00$10.00$15.00$8.00$6.99
100Work zone pavement marking removing (Y)4"(solid) (662-7097)LF16,500$1.00$1.40$1.50$2.50$2.50$1.10$0.92
101Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH4,644$1.50$1.40$1.50$1.00$2.00$4.00$4.40
102Pavement sler 4" (666-7346)LF10,776$0.50$0.50$0.75$0.50$0.60$0.40$0.33
103Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF5,388$1.00$1.30$1.50$3.00$3.00$1.00$0.87
104Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF5,388$1.00$1.30$1.50$3.00$3.00$1.00$0.87
105Reflectorized pavement marker type II-A-A (672-7004)EACH73$5.50$17.00$20.00$10.00$15.00$13.00$11.00
106Eliminating existing PM & markers (4") (677-7001)LF23,966$0.50$1.10$0.90$0.70$1.00$0.70$0.66
107Full - width mowing (730-7022)ACRE1.53$35.00$4,000.00$1,000.00$5,000.00$100.00$6,000.00$4,400.00
TxDOT contract A00133456: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of September 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy