TxDOT contract A00189999 bid tabulation
Bridge Replacement, ARTESIAN PARK RD (ON CR 830 (ARTESIAN PARK LANE, F-CR 419) to AT EAST FORK OF MILL CREEK). Let by Texas DOT on April 7, 2026, Washington, Bryan District. 9 bids received; low bid $732,054 by Garret Shields Infrastructure, -8.5% against the engineer's estimate of $800,383.
- Owner
- Texas DOT
- Letting
- 07 APR 2026
- Pay items
- 50
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Garret Shields Infrastructure | $732,054 | Low | -9.0% |
| 2 | Skyline Bridge LLC | $770,647 | +5.0% | -4.0% |
| 3 | R Construction Civil, LLC | $779,787 | +7.0% | -3.0% |
| 4 | Trevway, Inc. | $798,536 | +9.0% | 0.0% |
| 5 | Knife River Corporation - South | $927,210 | +27% | +16% |
| 6 | E-Z Bel Construction, LLC | $928,308 | +27% | +16% |
| 7 | Hodges and Son Construction Company, Inc. | $932,970 | +27% | +17% |
| 8 | Larry Young Paving, Inc. | $941,452 | +29% | +18% |
| 9 | Tucan Contracting, LLC | $1,061,625 | +45% | +33% |
Engineer's estimate: $800,383.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Garret Shields Infrastructure | 2. Skyline Bridge LLC | 3. R Construction Civil, LLC | 4. Trevway, Inc. | 5. Knife River Corporation - South | 6. E-Z Bel Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 2.75 | $2,000.00 | $5,000.00 | $300.00 | $4,300.00 | $3,000.00 | $242.00 | $750.00 |
| 2 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 6 | $700.00 | $500.00 | $424.00 | $800.00 | $300.00 | $445.00 | $950.00 |
| 3 | Tree protection (install) (100-7013) | EACH | 2 | $600.00 | $100.00 | $500.00 | $300.00 | $743.49 | $2,702.00 | $750.00 |
| 4 | Tree protection (remove) (100-7015) | EACH | 2 | $175.00 | $100.00 | $100.00 | $100.00 | $200.00 | $1,021.00 | $300.00 |
| 5 | Remove (6"-10") TRT/untrt base & asphalt pavement (105-7006) | SY | 475 | $10.00 | $20.00 | $9.00 | $10.00 | $9.00 | $5.00 | $8.88 |
| 6 | Excavation (roadway) (110-7001) | CY | 70 | $30.00 | $30.00 | $28.00 | $74.00 | $42.48 | $16.00 | $22.86 |
| 7 | Excavation (channel) (110-7002) | CY | 510 | $30.00 | $30.00 | $15.00 | $27.00 | $9.00 | $8.00 | $13.61 |
| 8 | Embankment (final)(DC)(type C) (132-7006) | CY | 153 | $30.00 | $30.00 | $35.00 | $37.00 | $50.00 | $12.00 | $17.14 |
| 9 | Furn & place topsoil (4") (160-7002) | SY | 902 | $5.00 | $4.00 | $3.55 | $9.00 | $5.00 | $3.50 | $1.65 |
| 10 | Bond fiber MTRX seed (temporary)(warm) (164-7077) | SY | 451 | $1.25 | $0.30 | $1.90 | $4.25 | $3.00 | $1.60 | $1.50 |
| 11 | Bond fiber MTRX seed (temporary)(cool) (164-7078) | SY | 451 | $1.25 | $0.30 | $1.90 | $4.25 | $3.00 | $1.60 | $1.50 |
| 12 | Bond fiber MTRX seed (permanent)(rural)(clay) (164-7083) | SY | 902 | $2.00 | $0.40 | $2.75 | $3.10 | $3.00 | $2.00 | $1.75 |
| 13 | Vegetative watering (168-7001) | TGL | 9 | $270.00 | $100.00 | $1.00 | $250.00 | $300.00 | $56.00 | $113.11 |
| 14 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 709 | $35.00 | $25.00 | $40.00 | $19.00 | $40.20 | $36.00 | $44.94 |
| 15 | Asphalt (RC-250) (316-7016) | GAL | 177 | $10.00 | $8.00 | $40.00 | $9.00 | $50.00 | $25.00 | $27.00 |
| 16 | Aggregate (type-B or L, GR-5) (316-7251) | CY | 5 | $170.00 | $1,000.00 | $2,500.00 | $1,350.00 | $1,642.00 | $627.00 | $2,300.00 |
| 17 | SP mixes SP-C sac-A PG64-22 (344-7010) | TON | 78 | $200.00 | $230.00 | $450.00 | $425.00 | $511.58 | $209.00 | $352.88 |
| 18 | Cem stabil BKFL (400-7010) | CY | 128 | $220.00 | $200.00 | $265.00 | $88.00 | $120.00 | $224.00 | $235.14 |
| 19 | Temporary special shoring (403-7001) | SF | 557 | $38.00 | $60.00 | $27.00 | $87.00 | $91.00 | $82.00 | $24.00 |
| 20 | Drilled shaft (36 in) (416-7006) | LF | 200 | $365.00 | $300.00 | $278.00 | $380.00 | $376.00 | $347.00 | $350.41 |
| 21 | Class C concrete (abutment) (420-7012) | CY | 47.60 | $1,440.00 | $1,000.00 | $915.00 | $650.00 | $777.00 | $1,718.00 | $2,082.41 |
| 22 | Reinforced concrete slab (422-7001) | SF | 2,700 | $30.00 | $25.00 | $28.00 | $27.00 | $22.00 | $53.00 | $46.33 |
| 23 | Prestressed concrete girder (TX28) (425-7001) | LF | 447.02 | $270.00 | $250.00 | $310.00 | $193.00 | $238.00 | $279.00 | $333.30 |
| 24 | Riprap (mow strip)(4 in) (432-7013) | CY | 13 | $700.00 | $600.00 | $720.00 | $531.00 | $500.00 | $817.00 | $756.29 |
| 25 | Riprap (stone protection)(18 in) (432-7043) | CY | 493 | $170.00 | $150.00 | $158.00 | $210.00 | $190.00 | $135.00 | $302.64 |
| 26 | Rail (type T223) (450-7008) | LF | 198 | $154.00 | $100.00 | $105.00 | $200.00 | $86.59 | $172.00 | $198.06 |
| 27 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 71 | $230.00 | $180.00 | $225.00 | $190.00 | $256.00 | $247.00 | $434.80 |
| 28 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $25,000 | $10,000 | $17,000 | $12,500 | $20,000 | $8,014.00 | $16,550 |
| 29 | Mobilization (500-7001) | LS | 1 | $80,000 | $50,000 | $65,000 | $27,000 | $80,000 | $149,125 | $27,791 |
| 30 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $2,500.00 | $5,000.00 | $1,600.00 | $6,500.00 | $1,010.00 | $1,420.00 | $598.00 |
| 31 | Rock filter dams (install) (type 2) (506-7002) | LF | 50 | $45.00 | $30.00 | $45.25 | $80.00 | $22.00 | $55.00 | $50.00 |
| 32 | Rock filter dams (remove) (506-7011) | LF | 50 | $11.00 | $10.00 | $10.50 | $1.75 | $2.00 | $11.00 | $10.00 |
| 33 | Construction exits (install) (type 1) (506-7020) | SY | 78 | $35.00 | $25.00 | $10.00 | $29.00 | $9.00 | $40.00 | $36.00 |
| 34 | Construction exits (remove) (506-7024) | SY | 78 | $15.00 | $10.00 | $1.00 | $10.00 | $1.00 | $13.00 | $12.00 |
| 35 | Temporary sediment control fence (install) (506-7039) | LF | 794 | $5.00 | $5.00 | $4.00 | $1.80 | $3.00 | $5.00 | $4.50 |
| 36 | Temporary sediment control fence (remove) (506-7041) | LF | 794 | $2.00 | $1.00 | $1.50 | $0.65 | $1.00 | $1.00 | $1.00 |
| 37 | Constructing detours (508-7001) | SY | 80 | $80.00 | $100.00 | $60.00 | $250.00 | $150.00 | $82.00 | $38.04 |
| 38 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 60 | $50.00 | $180.00 | $135.00 | $100.00 | $110.00 | $33.00 | $19.58 |
| 39 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 80 | $50.00 | $140.00 | $120.00 | $97.00 | $99.00 | $54.00 | $25.21 |
| 40 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 40 | $20.00 | $60.00 | $26.00 | $11.00 | $37.17 | $9.00 | $5.67 |
| 41 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 60 | $15.00 | $40.00 | $50.00 | $5.00 | $129.00 | $28.00 | $19.58 |
| 42 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 80 | $15.00 | $30.00 | $50.00 | $5.00 | $120.00 | $21.00 | $25.21 |
| 43 | Driveways (ACP) (530-7010) | SY | 104 | $55.00 | $120.00 | $150.00 | $165.00 | $100.00 | $102.00 | $161.41 |
| 44 | Metal W-beam guard fence (timber post) (540-7001) | LF | 75 | $29.00 | $30.00 | $30.00 | $29.00 | $42.00 | $30.00 | $37.64 |
| 45 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 4 | $1,350.00 | $1,000.00 | $1,300.00 | $1,450.00 | $1,277.43 | $1,500.00 | $1,397.00 |
| 46 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,380.00 | $1,500.00 | $1,500.00 | $1,600.00 | $1,880.33 | $1,667.00 | $1,580.00 |
| 47 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,200.00 | $3,500.00 | $4,135.00 | $3,500.00 | $3,901.00 | $3,661.00 | $3,547.00 |
| 48 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 6 | $50.00 | $10.00 | $20.00 | $27.00 | $6.32 | $28.00 | $36.06 |
| 49 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 6 | $75.00 | $25.00 | $27.00 | $35.00 | $13.90 | $39.00 | $29.00 |
| 50 | Bonding course (3007-7001) | GAL | 71 | $6.00 | $5.00 | $30.00 | $7.00 | $8.21 | $20.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 7, 2026. Compiled by Mirage Metrics.