TxDOT contract A00190176 bid tabulation
Bridge Replacement, COUNTY ROAD 308 (AA03-08 Agua Dulce Creek to 1.10 MI S of FM 624). Let by Texas DOT on June 3, 2026, Jim Wells, Corpus Christi District. 8 bids received; low bid $877,585 by CK Newberry, LLC, -4.1% against the engineer's estimate of $915,015.
- Owner
- Texas DOT
- Letting
- 03 JUN 2026
- Pay items
- 45
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | CK Newberry, LLC | $877,585 | Low | -4.0% |
| 2 | STX Civil | $892,628 | +2.0% | -2.0% |
| 3 | Delgado'S Contractors, LLC | $911,000 | +4.0% | 0.0% |
| 4 | J. Carroll Weaver, Inc. | $935,814 | +7.0% | +2.0% |
| 5 | Presidio Contracting, LLC | $980,494 | +12% | +7.0% |
| 6 | E-Z Bel Construction, LLC | $998,818 | +14% | +9.0% |
| 7 | Acme Bridge Company, Inc. | $1,051,570 | +20% | +15% |
| 8 | Foremost Paving, Inc. | $1,234,781 | +41% | +35% |
Engineer's estimate: $915,015.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. CK Newberry, LLC | 2. STX Civil | 3. Delgado'S Contractors, LLC | 4. J. Carroll Weaver, Inc. | 5. Presidio Contracting, LLC | 6. E-Z Bel Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 4.10 | $2,000.00 | $5,000.00 | $1,800.00 | $750.00 | $1,906.83 | $5,690.00 | $4,450.00 |
| 2 | Remove (0"-11") TRT/untrt base & asphalt pavement (105-7051) | SY | 843 | $18.00 | $10.00 | $15.00 | $15.00 | $9.92 | $12.95 | $7.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 598 | $25.00 | $15.00 | $10.00 | $20.00 | $9.92 | $25.50 | $22.00 |
| 4 | Embankment (final)(DC)(type C) (132-7006) | CY | 267 | $22.00 | $25.00 | $50.00 | $40.00 | $26.20 | $14.95 | $12.00 |
| 5 | Furn & place topsoil (4") (160-7002) | SY | 1,630 | $3.00 | $3.00 | $3.00 | $9.00 | $3.97 | $2.55 | $1.00 |
| 6 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 1,630 | $1.00 | $2.00 | $0.25 | $1.38 | $3.15 | $1.30 | $1.50 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 815 | $0.75 | $2.00 | $0.25 | $2.48 | $3.15 | $2.25 | $2.25 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 815 | $0.75 | $2.00 | $0.25 | $2.48 | $3.15 | $2.25 | $2.25 |
| 9 | Vegetative watering (168-7001) | TGL | 57 | $75.00 | $20.00 | $45.00 | $25.00 | $18.90 | $70.00 | $65.00 |
| 10 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 297 | $110.00 | $175.00 | $115.00 | $135.00 | $130.08 | $137.40 | $170.00 |
| 11 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 153 | $6.50 | $15.00 | $11.00 | $10.00 | $7.35 | $15.35 | $15.00 |
| 12 | D-GR HMA type-B PG64-22 (341-7001) | TON | 252 | $130.00 | $125.00 | $150.00 | $250.00 | $237.81 | $337.55 | $172.00 |
| 13 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 81 | $150.00 | $200.00 | $170.00 | $250.00 | $237.81 | $358.00 | $185.00 |
| 14 | Tack coat (341-7082) | GAL | 148 | $5.00 | $10.00 | $8.00 | $10.00 | $7.35 | $9.20 | $9.00 |
| 15 | Cem stabil BKFL (400-7010) | CY | 24 | $220.00 | $350.00 | $280.00 | $175.00 | $169.21 | $450.00 | $250.00 |
| 16 | Drilled shaft (24 in) (416-7004) | LF | 240 | $290.00 | $250.00 | $290.00 | $250.00 | $258.46 | $253.00 | $255.00 |
| 17 | Class C concrete (abutment) (420-7012) | CY | 19 | $1,500.00 | $1,500.00 | $1,200.00 | $1,400.00 | $1,943.01 | $1,390.00 | $1,450.00 |
| 18 | Class C concrete (cap) (420-7022) | CY | 13.80 | $1,780.00 | $1,000.00 | $1,500.00 | $1,400.00 | $1,660.85 | $1,675.00 | $2,050.00 |
| 19 | Class C concrete (column) (420-7038) | CY | 6.40 | $1,500.00 | $1,200.00 | $1,400.00 | $1,400.00 | $2,195.02 | $2,455.00 | $1,225.00 |
| 20 | Reinforced concrete slab (slab beam) (422-7007) | SF | 3,120 | $24.00 | $25.00 | $32.00 | $29.00 | $26.11 | $26.70 | $22.50 |
| 21 | Approach slab (422-7013) | CY | 44 | $800.00 | $750.00 | $750.00 | $900.00 | $829.42 | $685.00 | $1,100.00 |
| 22 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 592.42 | $240.00 | $275.00 | $265.00 | $275.00 | $279.99 | $251.50 | $285.95 |
| 23 | Riprap (mow strip)(4 in) (432-7013) | CY | 35 | $700.00 | $750.00 | $750.00 | $650.00 | $683.81 | $750.00 | $750.00 |
| 24 | Riprap (stone protection)(18 in) (432-7043) | CY | 380 | $200.00 | $155.00 | $230.00 | $195.00 | $159.75 | $195.60 | $275.00 |
| 25 | Rail (type T223) (450-7008) | LF | 264 | $130.00 | $150.00 | $165.00 | $145.00 | $160.35 | $160.00 | $275.00 |
| 26 | Armor joint (sealed) (454-7003) | LF | 53 | $160.00 | $175.00 | $165.00 | $150.00 | $144.35 | $192.00 | $250.00 |
| 27 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $45,000 | $30,000 | $25,000 | $18,000 | $48,782 | $29,400 | $35,000 |
| 28 | Mobilization (500-7001) | LS | 1 | $90,000 | $85,000 | $72,000 | $70,000 | $90,934 | $96,300 | $95,000 |
| 29 | Barricades, signs and traffic handling (502-7001) | MO | 7 | $10,000 | $3,000.00 | $1,350.00 | $2,250.00 | $1,260.00 | $2,000.00 | $1,200.00 |
| 30 | Construction exits (install) (type 1) (506-7020) | SY | 100 | $30.00 | $25.00 | $45.00 | $48.73 | $41.99 | $45.30 | $44.50 |
| 31 | Construction exits (remove) (506-7024) | SY | 100 | $10.00 | $10.00 | $10.00 | $20.13 | $16.17 | $18.70 | $18.25 |
| 32 | Temporary sediment control fence (install) (506-7039) | LF | 839 | $4.00 | $5.00 | $3.00 | $5.50 | $5.25 | $5.15 | $5.00 |
| 33 | Temporary sediment control fence (remove) (506-7041) | LF | 839 | $1.00 | $2.00 | $1.00 | $1.10 | $0.53 | $1.00 | $1.00 |
| 34 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 144 | $6.50 | $7.00 | $8.00 | $8.80 | $16.80 | $8.20 | $8.00 |
| 35 | Biodegradable erosion control logs (remove) (506-7046) | LF | 144 | $1.50 | $2.00 | $1.00 | $1.10 | $2.10 | $1.00 | $1.00 |
| 36 | Metal W-beam guard fence (timber post) (540-7001) | LF | 287.50 | $30.00 | $40.00 | $35.00 | $35.00 | $34.65 | $34.50 | $34.00 |
| 37 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,100.00 | $2,200.00 | $2,750.00 | $2,500.00 | $2,940.00 | $3,020.00 | $2,076.00 |
| 38 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,500.00 | $1,800.00 | $1,650.00 | $1,500.00 | $2,310.00 | $1,645.00 | $1,605.00 |
| 39 | Guardrail end treatment (install) (544-7001) | EACH | 3 | $3,500.00 | $4,500.00 | $3,800.00 | $4,000.00 | $3,454.50 | $4,150.00 | $4,054.00 |
| 40 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 1 | $730.00 | $2,000.00 | $1,650.00 | $1,554.00 | $1,575.00 | $1,535.00 | $1,500.00 |
| 41 | Remove SM RD SN sup&AM (644-7073) | EACH | 1 | $125.00 | $600.00 | $300.00 | $275.00 | $262.50 | $100.00 | $250.00 |
| 42 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 12 | $35.00 | $35.00 | $150.00 | $126.50 | $120.75 | $25.00 | $115.00 |
| 43 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 23 | $35.00 | $45.00 | $150.00 | $126.50 | $120.75 | $50.00 | $115.00 |
| 44 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 840 | $1.00 | $5.00 | $12.00 | $9.90 | $9.45 | $9.20 | $9.00 |
| 45 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 11 | $8.00 | $15.00 | $350.00 | $275.00 | $9.45 | $256.00 | $250.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 3, 2026. Compiled by Mirage Metrics.