TxDOT contract A00190177 bid tabulation

Bridge Replacement, COUNTY ROAD 230 (AA02-30 Draw to 0.5 MI SE of CR 237). Let by Texas DOT on June 2, 2026, Karnes, Corpus Christi District. 10 bids received; low bid $817,325 by C & W Southern LLC, -27% against the engineer's estimate of $1,115,075.

Owner
Texas DOT
Letting
02 JUN 2026
Pay items
42
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1C & W Southern LLC$817,325Low-27%
2Presidio Contracting, LLC$862,084+5.0%-23%
3E-Z Bel Construction, LLC$879,775+8.0%-21%
4CK Newberry, LLC$919,223+12%-18%
5Acme Bridge Company, Inc.$934,780+14%-16%
6Delgado'S Contractors, LLC$975,500+19%-13%
7Trevway, Inc.$984,379+20%-12%
8STX Civil$995,516+22%-11%
9Garret Shields Infrastructure$1,033,607+26%-7.0%
10J. Carroll Weaver, Inc.$1,037,493+27%-7.0%
TxDOT contract A00190177: bids by rank

Engineer's estimate: $1,115,075.

Bid tabulation

LinePay itemUnitQuantityEstimate1. C & W Southern LLC2. Presidio Contracting, LLC3. E-Z Bel Construction, LLC4. CK Newberry, LLC5. Acme Bridge Company, Inc.6. Delgado'S Contractors, LLC
1Preparing row (100-7002)STA6$8,000.00$1,300.00$2,625.00$3,750.00$1,000.00$830.00$750.00
2Preparation row (tree remove) (0"-12" diameter) (100-7003)EACH7$900.00$200.00$750.00$1,100.00$1,000.00$1,150.00$400.00
3Removing concrete (wingwall) (104-7028)CY9$400.00$100.00$500.00$655.00$500.00$235.00$250.00
4Remove (9"-13") TRT/untrt base & asphalt pavement (105-7009)SY1,224$12.00$10.00$15.25$7.50$7.00$7.00$15.00
5Excavation (roadway) (110-7001)CY282$30.00$10.00$33.10$20.00$20.00$35.30$25.00
6Excavation (channel) (110-7002)CY864$23.00$8.00$33.10$17.00$25.00$23.42$25.00
7Embankment (final)(DC)(type C) (132-7006)CY47$25.00$10.00$10.90$12.00$50.00$45.90$65.00
8Furn & place topsoil (4") (160-7002)SY1,174$7.00$5.00$2.60$1.50$3.00$3.40$9.00
9Broadcast seed (permanent_rural_sand) (164-7001)SY1,174$3.00$0.50$1.55$1.50$2.00$1.60$1.50
10Vegetative watering (168-7001)TGL21.40$50.00$10.00$89.00$115.00$55.00$60.80$30.00
11Soil retention blankets (CL 1) (type B) (169-7043)SY73$2.00$20.00$3.10$3.00$10.00$3.20$6.00
12FL BS (cip)(type A GR 1-2 or 5) final pos (247-7348)CY397$110.00$115.00$75.00$125.00$115.00$118.00$130.00
13Prime coat (MC-30) (310-7004)GAL230$11.00$11.00$11.25$11.00$10.00$16.70$10.00
14Asphalt(AC-15P, HFRS-2P or CRS-2P) (316-7070)GAL368$10.00$4.00$4.10$4.00$6.00$11.40$20.00
15Aggregate (type-PB, GR-3 or 3S)(sac-B) (316-7209)CY12$500.00$1,050.00$1,075.00$1,050.00$350.00$870.00$350.00
16Aggregate (type-PB, GR-4S or 4)(sac-B) (316-7212)CY10$500.00$1,050.00$1,075.00$1,050.00$400.00$1,010.00$350.00
17Asphalt (multi option) (316-7263)GAL425$10.00$4.00$4.10$4.00$6.00$11.20$20.00
18Cem stabil BKFL (400-7010)CY75$200.00$300.00$280.00$225.00$250.00$335.00$175.00
19Drilled shaft (18 in) (416-7002)LF90$240.00$75.00$111.15$106.00$300.00$103.00$180.00
20Drilled shaft (36 in) (416-7006)LF240$270.00$235.00$310.15$330.00$400.00$316.00$325.00
21Class C concrete (abutment) (420-7012)CY48.80$1,500.00$1,100.00$1,085.00$1,125.00$1,450.00$1,470.00$1,400.00
22Reinforced concrete slab (422-7001)SF2,100$30.00$30.00$35.30$26.50$35.00$35.04$28.00
23Approach slab (422-7013)CY53.40$1,100.00$850.00$595.00$650.00$725.00$797.00$900.00
24Prestressed concrete girder (TX28) (425-7001)LF277.93$260.00$320.00$270.75$250.00$275.00$316.00$315.00
25Riprap (mow strip)(4 in) (432-7013)CY29$650.00$300.00$795.00$625.00$550.00$932.00$650.00
26Riprap (stone protection)(12 in) (432-7041)CY116$590.00$170.00$180.00$240.00$175.00$200.00$220.00
27Riprap (stone protection)(24 in) (432-7045)CY893$250.00$185.00$152.00$170.00$155.00$181.00$220.00
28Rail (type T223) (450-7008)LF216$120.00$150.00$133.20$250.00$175.00$155.00$150.00
29Type A joint (454-7001)LF62$80.00$20.00$34.35$50.00$175.00$54.00$100.00
30Removing structure (bridge 0 - 99 FT length) (496-7009)EACH1$25,000$10,000$18,600$24,000$25,000$13,100$25,000
31Mobilization (500-7001)LS1$101,400$90,000$86,400$85,000$90,000$90,000$95,000
32Barricades, signs and traffic handling (502-7001)MO7$7,200.00$1,150.00$2,675.00$1,000.00$2,000.00$2,550.00$2,000.00
33Temporary sediment control fence (install) (506-7039)LF1,181$5.00$2.00$4.35$4.50$4.25$4.50$6.00
34Temporary sediment control fence (remove) (506-7041)LF1,181$3.00$1.00$1.00$1.00$1.00$1.05$1.50
35Metal W-beam guard fence (timber post) (540-7001)LF100$50.00$25.50$24.65$34.50$38.00$28.70$35.00
36Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$3,500.00$1,800.00$2,785.00$2,223.00$2,500.00$2,110.00$2,500.00
37Guardrail end treatment (install) (544-7001)EACH4$4,000.00$3,400.00$3,735.00$3,726.00$4,000.00$3,880.00$4,000.00
38Wire fence (type A) (552-7001)LF44$36.00$60.00$70.00$35.00$55.00$18.70$40.00
39Wire fence (remove) (552-7011)LF44$5.00$1.00$10.00$15.00$11.00$7.50$5.00
40Remove SM RD SN sup&AM (644-7073)EACH6$125.00$10.00$65.00$205.00$200.00$67.60$100.50
41Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH5$70.00$45.00$36.00$35.00$100.00$37.20$44.91
42Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH8$90.00$45.00$52.00$50.00$100.00$53.10$45.00
TxDOT contract A00190177: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 2, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy