ALDOT contract 20260731017 bid tabulation
ROADWAY WIDENING AND PEDESTRIAN IMPROVEMENTS (GRADING, DRAINAGE, PAVEMENT, TRAFFIC SIGNALS, AND TRAFFIC STRIPE) ON SR-204 FROM THE JUNCTION OF NISBET LAKE ROAD TO THE JUNCTION OF SR-21 IN JACKSONVILLE. Let by Alabama DOT on July 31, 2026, Calhoun, 0402. 4 bids received; low bid $8,240,555 by Alabama Grading & Excavation, LLC..
- Owner
- Alabama DOT
- Letting
- 31 JUL 2026
- Pay items
- 155
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Alabama Grading & Excavation, LLC. | $8,240,555 | Low |
| 2 | Apac-Alabama, Inc. | $8,877,476 | +8.0% |
| 3 | Gillespie Construction, LLC | $8,943,900 | +9.0% |
| 4 | Vulcan Materials Asphalt and Construction, | $9,779,594 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alabama Grading & Excavation, LLC. | 2. Apac-Alabama, Inc. | 3. Gillespie Construction, LLC | 4. Vulcan Materials Asphalt and Construction, |
|---|---|---|---|---|---|---|---|
| 0010 | Removing concrete sidewalk (206C000) | SY | 106 | $21.40 | $13.89 | $55.00 | $35.00 |
| 0020 | Removing concrete median (206C008) | SY | 404 | $15.31 | $17.36 | $65.00 | $40.00 |
| 0030 | Removing concrete driveway (206C010) | SY | 260 | $21.58 | $13.89 | $65.00 | $40.00 |
| 0040 | Removing pipe (206D000) | LF | 1,268 | $20.82 | $18.52 | $35.00 | $52.00 |
| 0050 | Removing curb and gutter (206D003) | LF | 2,495 | $14.08 | $14.47 | $25.00 | $27.00 |
| 0060 | Removing headwalls (206E000) | EACH | 11 | $642.90 | $694.59 | $550.00 | $1,350.00 |
| 0070 | Removing inlets (206E001) | EACH | 12 | $864.48 | $1,041.89 | $2,500.00 | $2,250.00 |
| 0080 | Removing junction boxes (206E002) | EACH | 2 | $658.89 | $1,157.66 | $4,500.00 | $3,000.00 |
| 0090 | Removing permanent barricade (206E033) | EACH | 1 | $460.93 | $1,157.66 | $1,500.00 | $5,000.00 |
| 0100 | Removing raised pavement markers (206E043) | EACH | 694 | $4.00 | $4.58 | $35.00 | $1.00 |
| 0110 | Removing existing bollard (all types) (206E080) | EACH | 4 | $275.00 | $463.06 | $750.00 | $150.00 |
| 0120 | Mailbox reset, single (209A000) | EACH | 2 | $250.00 | $463.06 | $350.00 | $500.00 |
| 0130 | Unclassified excavation (210A000) | CY | 9,640 | $18.00 | $23.15 | $40.00 | $45.00 |
| 0140 | Borrow excavation (loose truckbed measurement) (210D001) | CY | 6,393 | $23.00 | $19.68 | $45.00 | $57.00 |
| 0150 | Structure excavation (214A000) | CY | 15,810 | $22.87 | $13.89 | $20.00 | $16.00 |
| 0160 | Foundation backfill, commercial (aldot #57) (214B001) | CY | 5,909 | $72.00 | $95.19 | $55.00 | $60.00 |
| 0170 | Roadbed stabilizing material, aldot #467 (231B001) | TON | 3,659 | $45.10 | $57.77 | $55.00 | $60.00 |
| 0180 | Crushed aggregate base course, type B, plant mixed, 6" compacted thickness (301A012) | SY | 13,721 | $16.00 | $20.17 | $20.00 | $29.00 |
| 0190 | Crushed aggregate, section 825, type B, for miscellaneous use (305B078) | TON | 3,132 | $36.32 | $48.00 | $55.00 | $67.00 |
| 0200 | Bituminous treatment A (401A000) | SY | 11,745 | $5.20 | $1.54 | $1.52 | $1.80 |
| 0210 | Tack coat (405A000) | GAL | 5,814 | $4.47 | $5.13 | $5.45 | $4.00 |
| 0220 | Micro-milling existing pavement (approximately 1.10" thru 2.00" thick) (408B001) | SY | 23,806 | $2.71 | $3.47 | $3.36 | $3.30 |
| 0230 | Material remixing device (410H000) | EACH | 1 | $30,000 | $71,800 | $69,300 | $30,000 |
| 0240 | Superpave bituminous concrete wearing surface layer, 3/8" maximum aggregate size mix, esal range C/D (424A356) | TON | 1,599 | $113.88 | $143.36 | $138.82 | $175.00 |
| 0250 | Superpave bituminous concrete wearing surface layer, widening, 3/8" maximum aggregate size mix,esal range C/D (424A359) | TON | 131 | $140.42 | $324.54 | $310.86 | $280.00 |
| 0260 | Superpave bituminous concrete upper binder layer, 1" maximum aggregate size mix, esal range C/D (424B651) | TON | 694 | $97.22 | $155.29 | $151.03 | $170.00 |
| 0270 | Superpave bituminous concrete upper binder layer, leveling, 3/4" maximum aggregate size mix, esal range C/D (424B658) | TON | 3,302 | $101.00 | $129.32 | $125.07 | $140.00 |
| 0280 | Superpave bituminous concrete upper binder layer, widening, 1" maximum aggregate size mix, esal range C/D (424B662) | TON | 417 | $114.30 | $158.64 | $152.79 | $210.00 |
| 0290 | Superpave bituminous concrete lower binder layer, 1" maximum aggregate size mix, esal range C/D (424B681) | TON | 694 | $95.24 | $155.29 | $151.14 | $170.00 |
| 0300 | Superpave bituminous concrete lower binder layer, patching, 1" maximum aggregate size mix, esal range C/D (424B685) | TON | 500 | $126.10 | $185.79 | $178.75 | $210.00 |
| 0310 | Aggregate surfacing (aldot #57) (430B003) | TON | 1,070 | $46.85 | $55.46 | $75.00 | $108.00 |
| 0320 | Aggregate surfacing (1" down, crusher run) (430B043) | TON | 500 | $45.69 | $48.00 | $75.00 | $102.00 |
| 0330 | Scrub seal (433A000) | SY | 26,424 | $3.83 | $3.80 | $4.09 | $3.20 |
| 0340 | Structural steel (508A000) | LB | 2,262 | $11.00 | $7.90 | $6.00 | $9.00 |
| 0350 | Sidewalk handrail (517D000) | LF | 1,603 | $268.00 | $177.58 | $181.50 | $340.00 |
| 0360 | Culvert concrete extension (cast in place) (524B011) | CY | 16 | $3,850.00 | $5,199.27 | $4,000.00 | $5,000.00 |
| 0370 | Retaining wall(MSE) (529A012) | SF | 100 | $225.00 | $174.28 | $225.00 | $175.00 |
| 0380 | 18" roadway pipe (class 3 R.C.) (530A001) | LF | 109 | $113.95 | $63.38 | $130.00 | $85.00 |
| 0390 | 24" roadway pipe (class 3 R.C.) (530A002) | LF | 3,016 | $120.00 | $93.65 | $120.00 | $106.00 |
| 0400 | 30" roadway pipe (class 3 R.C.) (530A003) | LF | 242 | $125.00 | $125.22 | $150.00 | $140.00 |
| 0410 | 36" roadway pipe (class 3 R.C.) (530A004) | LF | 217 | $233.00 | $166.55 | $175.00 | $165.00 |
| 0420 | 48" roadway pipe (class 3 R.C.) (530A006) | LF | 848 | $251.94 | $295.37 | $400.00 | $250.00 |
| 0430 | 59" span, 36" rise roadway pipe (class 3 R.C.) (530B006) | LF | 236 | $246.28 | $619.67 | $325.00 | $370.00 |
| 0440 | 73" span, 45" rise roadway pipe (class 3 R.C.) (530B008) | LF | 54 | $421.73 | $1,075.52 | $800.00 | $550.00 |
| 0450 | Cleaning existing pipe (less than or equal to 48" horizontal opening) (534E001) | LF | 994 | $85.00 | $17.28 | $20.00 | $18.00 |
| 0460 | 18" side drain pipe (535A001) | LF | 131 | $58.93 | $63.74 | $120.00 | $85.00 |
| 0470 | 24" side drain pipe (535A002) | LF | 132 | $193.79 | $93.71 | $125.00 | $110.00 |
| 0480 | 30" side drain pipe (535A003) | LF | 142 | $204.00 | $119.77 | $145.00 | $140.00 |
| 0490 | 48" side drain pipe (535A006) | LF | 86 | $220.00 | $296.07 | $400.00 | $230.00 |
| 0500 | Mobilization (600A000) | LS | 1 | $527,919 | $640,335 | $409,190 | $684,525 |
| 0510 | Right of way markers (602A000) | EACH | 10 | $580.53 | $481.81 | $1,100.00 | $1,000.00 |
| 0520 | Loose riprap, class 2 (610C001) | TON | 3,072 | $43.56 | $71.26 | $75.00 | $85.00 |
| 0530 | Filter blanket, geotextile (610D003) | SY | 4,337 | $4.27 | $5.21 | $3.47 | $3.50 |
| 0540 | Slope paving (614A000) | CY | 390 | $712.00 | $679.68 | $750.00 | $680.00 |
| 0550 | Concrete sidewalk, 4" thick (618A000) | SY | 3,146 | $106.00 | $97.60 | $115.00 | $100.00 |
| 0560 | Concrete driveway, 6" thick (includes wire mesh) (618B003) | SY | 295 | $135.00 | $110.38 | $125.00 | $112.00 |
| 0570 | Detectable warning surface (618C001) | SF | 350 | $68.00 | $69.71 | $50.00 | $70.00 |
| 0580 | Curb ramp (618D000) | SY | 378 | $218.00 | $145.23 | $375.00 | $145.00 |
| 0590 | 24" roadway pipe end treatment, class 1 (619A003) | EACH | 1 | $3,100.00 | $3,020.80 | $2,500.00 | $2,900.00 |
| 0600 | 36" roadway pipe end treatment, class 1 (619A005) | EACH | 1 | $3,500.00 | $3,340.32 | $2,750.00 | $3,200.00 |
| 0610 | 48" roadway pipe end treatment, class 1 (619A007) | EACH | 1 | $4,500.00 | $6,390.16 | $4,000.00 | $6,150.00 |
| 0620 | 18" side drain pipe end treatment, class 1 (619A101) | EACH | 6 | $3,100.00 | $2,323.70 | $2,250.00 | $2,200.00 |
| 0630 | 24" side drain pipe end treatment, class 1 (619A102) | EACH | 4 | $3,500.00 | $2,527.02 | $2,500.00 | $2,400.00 |
| 0640 | 30" side drain pipe end treatment, class 1 (619A103) | EACH | 4 | $3,560.00 | $2,788.44 | $2,750.00 | $2,650.00 |
| 0650 | 48" side drain pipe end treatment, class 1 (619A106) | EACH | 2 | $4,650.00 | $5,809.24 | $4,000.00 | $5,600.00 |
| 0660 | 73" span, 45" rise roadway pipe end treatment, class 1 (619B023) | EACH | 1 | $8,000.00 | $8,365.30 | $6,000.00 | $8,200.00 |
| 0670 | Junction boxes, type 1 or 1P (621A011) | EACH | 3 | $5,500.00 | $6,564.44 | $4,500.00 | $4,000.00 |
| 0680 | Junction boxes, type 1 or 2P (621A019) | EACH | 3 | $5,500.00 | $6,738.72 | $4,500.00 | $10,000 |
| 0690 | Inlets, type S1 or S3 (1 wing) (621C015) | EACH | 13 | $6,700.00 | $8,713.85 | $6,000.00 | $7,600.00 |
| 0700 | Inlets, type S2 or S4 (1 wing) (621C016) | EACH | 9 | $6,900.00 | $9,062.41 | $6,000.00 | $12,500 |
| 0710 | Inlets, type S2 or S4 (2 wing) (621C018) | EACH | 1 | $7,500.00 | $9,585.24 | $7,500.00 | $16,000 |
| 0720 | Inlets, type PD (621C109) | EACH | 11 | $14,000 | $11,328 | $7,000.00 | $11,000 |
| 0730 | Inlet units, type S1 or S3 (621D015) | EACH | 18 | $1,025.00 | $1,161.85 | $2,500.00 | $1,150.00 |
| 0740 | Inlet units, type S2 or S4 (621D016) | EACH | 28 | $1,250.00 | $1,278.03 | $2,500.00 | $1,250.00 |
| 0750 | Inlet units, type P2 (621D043) | EACH | 5 | $1,020.00 | $1,917.05 | $2,500.00 | $1,850.00 |
| 0760 | Inlet units, type PD (621D109) | EACH | 4 | $1,500.00 | $1,917.05 | $2,500.00 | $1,850.00 |
| 0770 | Manholes, type L (621E002) | EACH | 2 | $6,500.00 | $8,713.86 | $4,500.00 | $6,500.00 |
| 0780 | Concrete gutter (valley) (623A001) | LF | 554 | $71.00 | $40.66 | $75.00 | $40.00 |
| 0790 | Concrete curb, type N (623B000) | LF | 243 | $72.00 | $48.80 | $55.00 | $48.00 |
| 0800 | Concrete curb, type A (623B002) | LF | 633 | $72.00 | $48.80 | $45.00 | $48.00 |
| 0810 | Combination curb & gutter, type C (623C000) | LF | 7,268 | $42.00 | $44.15 | $50.00 | $44.00 |
| 0820 | Steel beam guardrail, class A, type 2 (630A001) | LF | 2,188 | $28.60 | $30.21 | $31.20 | $30.00 |
| 0830 | Guardrail end anchor, type 8 (MASH) (630C077) | EACH | 3 | $1,540.00 | $1,626.59 | $1,680.00 | $1,600.00 |
| 0840 | Guardrail end anchor, type 20 series (MASH) (630C080) | EACH | 7 | $4,125.00 | $4,356.93 | $4,500.00 | $4,200.00 |
| 0850 | Topsoil (650A000) | CY | 3,846 | $62.10 | $13.89 | $45.00 | $47.00 |
| 0860 | Solid sodding (654A000) | SY | 14,893 | $10.03 | $10.49 | $9.35 | $12.00 |
| 0870 | Erosion control product, type S2 (659C002) | SY | 2,000 | $7.00 | $4.03 | $1.79 | $2.20 |
| 0880 | Erosion control product, type C4 (659C005) | SY | 745 | $7.50 | $4.53 | $5.56 | $7.00 |
| 0890 | Temporary seeding (665A000) | ACRE | 7 | $49.70 | $667.77 | $893.75 | $1,000.00 |
| 0900 | Temporary mulching (665B001) | TON | 21 | $73.02 | $689.85 | $880.00 | $1,000.00 |
| 0910 | Temporary pipe (665C010) | LF | 150 | $50.00 | $57.88 | $125.00 | $120.00 |
| 0920 | Temporary pipe end treatment (665D001) | EACH | 4 | $880.00 | $3,485.54 | $1,500.00 | $2,200.00 |
| 0930 | Polyethylene (665E000) | SY | 500 | $88.00 | $3.06 | $3.95 | $4.00 |
| 0940 | Sand bags (665G000) | EACH | 720 | $9.00 | $6.68 | $8.53 | $10.00 |
| 0950 | Temporary riprap, class 2 (665I000) | TON | 350 | $40.00 | $94.42 | $75.00 | $95.00 |
| 0960 | Temporary riprap, class 1 (665I002) | TON | 350 | $40.00 | $94.42 | $75.00 | $95.00 |
| 0970 | Silt fence (665J002) | LF | 4,500 | $6.00 | $5.46 | $2.85 | $3.00 |
| 0980 | Temporary coarse aggregate,aldot number 1 (665N000) | TON | 400 | $39.00 | $61.25 | $75.00 | $90.00 |
| 0990 | Temporary coarse aggregate,aldot number 4 (665N001) | TON | 250 | $40.00 | $61.25 | $75.00 | $90.00 |
| 1000 | Silt fence removal (665O001) | LF | 4,500 | $1.20 | $2.21 | $1.16 | $1.20 |
| 1010 | Inlet protection, stage 3 or 4 (665P005) | EACH | 51 | $125.00 | $82.78 | $182.60 | $190.00 |
| 1020 | Wattle, 20 inch (665Q020) | LF | 500 | $10.00 | $9.93 | $12.16 | $15.00 |
| 1030 | Construction safety fence (674A000) | LF | 300 | $10.00 | $3.47 | $6.00 | $12.00 |
| 1040 | Geometric controls (680A001) | LS | 1 | $50,000 | $372,942 | $45,000 | $200,000 |
| 1050 | Construction fuel (maximum bid limited to $ 374,300.00) (698A000) | LS | 1 | $0.00 | $0.00 | $0.00 | $0.00 |
| 1060 | Solid white, class 2, type A traffic stripe (5" wide) (701A227) | MI | 3 | $5,060.00 | $4,356.93 | $4,500.00 | $4,200.00 |
| 1070 | Solid yellow, class 2, type A traffic stripe (5" wide) (701A230) | MI | 3 | $5,060.00 | $4,356.93 | $4,500.00 | $4,200.00 |
| 1080 | Broken yellow, class 2, type A traffic stripe (5" wide) (701A244) | MI | 1 | $1,980.00 | $2,410.83 | $2,700.00 | $2,320.00 |
| 1090 | Dotted, class 2, type A traffic stripe (5" wide) (701B207) | LF | 1,437 | $0.39 | $1.16 | $2.40 | $1.10 |
| 1100 | Broken temporary traffic stripe (701C000) | MI | 3 | $2,420.00 | $987.57 | $1,080.00 | $970.00 |
| 1110 | Solid temporary traffic stripe (701C001) | MI | 16 | $3,300.00 | $1,016.62 | $1,188.00 | $1,000.00 |
| 1120 | Traffic control markings, class 2, type A (703A002) | SF | 3,503 | $7.15 | $5.23 | $12.00 | $5.00 |
| 1130 | Traffic control legends, class 2, type A (703B002) | SF | 247 | $9.63 | $6.68 | $12.00 | $6.50 |
| 1140 | Temporary traffic control markings (703D001) | SF | 3,503 | $2.47 | $1.16 | $2.40 | $1.10 |
| 1150 | Pavement markers, class C, type 2- C (705A022) | EACH | 311 | $9.00 | $11.62 | $7.20 | $12.00 |
| 1160 | Pavement markers, class C, type 2- E (705A024) | EACH | 36 | $9.00 | $11.62 | $7.20 | $12.00 |
| 1170 | Pavement markers, class A-H, type 2-C (705A030) | EACH | 312 | $9.00 | $5.81 | $7.20 | $6.00 |
| 1180 | Pavement markers, class A-H, type 2-D (705A037) | EACH | 118 | $9.00 | $5.81 | $7.20 | $6.00 |
| 1190 | Milepost, type B (709A001) | EACH | 1 | $825.00 | $871.39 | $900.00 | $215.00 |
| 1200 | Class 10 aluminum flat sign panels (type XI background) (710A163) | SF | 72 | $33.00 | $34.86 | $36.00 | $28.00 |
| 1210 | Class 10 aluminum flat sign panels (type XI background, fluorescent) (710A164) | SF | 89 | $38.50 | $40.66 | $42.00 | $28.00 |
| 1220 | Class 4, aluminum flat sign panels (type IV background) (710A171) | SF | 170 | $27.50 | $29.05 | $30.00 | $24.00 |
| 1230 | Roadway sign post (#3 U channel, galvanized steel or 2 ", 14 GA square tubular steel) (710B021) | LF | 406 | $19.80 | $20.91 | $21.60 | $22.00 |
| 1240 | Removal of existing traffic control unit ( SR-204 at nisbet lake road) (730A000) | LS | 1 | $5,500.00 | $5,809.23 | $5,750.00 | $5,800.00 |
| 1250 | Furnishing and installing traffic control unit ( SR-204 at nisbet lake road) (730C000) | LS | 1 | $13,200 | $13,942 | $13,800 | $13,800 |
| 1260 | Furnishing and installing traffic control unit ( SR-204 at midblock crossing) (730C001) | LS | 1 | $7,150.00 | $7,552.01 | $7,475.00 | $7,400.00 |
| 1270 | Metal traffic signal pole foundation (730E000) | EACH | 6 | $8,800.00 | $9,294.78 | $9,200.00 | $9,100.00 |
| 1280 | Metal traffic signal pole with 60' mast arm assembly and 50' mast arm assembly (730F000) | EACH | 1 | $53,900 | $56,931 | $56,350 | $55,000 |
| 1290 | Metal traffic signal pole with 70' mast arm assembly (730F001) | EACH | 1 | $35,511 | $37,508 | $37,240 | $36,000 |
| 1300 | Metal traffic signal pole with 45' mast arm assembly (730F002) | EACH | 1 | $35,200 | $37,179 | $36,800 | $36,000 |
| 1310 | Metal traffic signal pole with 20' mast arm assembly (730F003) | EACH | 1 | $17,600 | $18,590 | $18,400 | $18,000 |
| 1320 | Metal traffic signal pole with 25' mast arm assembly (730F004) | EACH | 1 | $17,600 | $18,590 | $18,400 | $18,000 |
| 1330 | Metal traffic signal strain pole (730G001) | EACH | 1 | $7,150.00 | $7,552.01 | $7,475.00 | $7,300.00 |
| 1340 | Traffic signal junction box type S1 (730K001) | EACH | 1 | $715.00 | $755.20 | $747.50 | $730.00 |
| 1350 | Traffic signal junction box type S2 (730K002) | EACH | 5 | $1,540.00 | $1,626.59 | $1,610.00 | $1,560.00 |
| 1360 | 1", non-metallic, conduit (730L003) | LF | 80 | $13.20 | $13.94 | $13.80 | $13.50 |
| 1370 | 2", non-metallic, conduit (730L005) | LF | 615 | $13.20 | $13.94 | $13.80 | $13.50 |
| 1380 | Luminaire extension assembly, 12' (730N000) | EACH | 6 | $3,080.00 | $3,253.17 | $3,220.00 | $3,130.00 |
| 1390 | Luminaire extension assembly, post- top (730N001) | EACH | 6 | $3,080.00 | $3,253.17 | $3,220.00 | $3,130.00 |
| 1400 | Vehicular signal head, 12 inch, 3 (730P022) | EACH | 12 | $1,540.00 | $1,626.59 | $1,610.00 | $1,570.00 |
| 1410 | Pedestrian signal head, type LED (730P100) | EACH | 6 | $902.00 | $952.72 | $943.00 | $920.00 |
| 1420 | Miscellaneous equipment, pedestrian push button (730Q001) | EACH | 6 | $1,375.00 | $1,452.31 | $1,437.50 | $1,400.00 |
| 1430 | Miscellaneous equipment, pedestal pole and foundation (730Q005) | EACH | 6 | $5,280.00 | $5,576.87 | $5,520.00 | $5,400.00 |
| 1440 | Controller assembly, type NEMA, 8 channels (730R040) | EACH | 1 | $29,700 | $31,370 | $31,050 | $30,000 |
| 1450 | Controller assembly, type NEMA, 16 channels (730R041) | EACH | 1 | $29,700 | $31,370 | $31,050 | $30,000 |
| 1460 | Electrical power service assembly with wood pole (730T010) | EACH | 2 | $5,280.00 | $5,576.87 | $5,520.00 | $5,370.00 |
| 1470 | Video detection system ( SR-204 at nisbet lake road) (730U015) | LS | 1 | $27,500 | $29,046 | $28,750 | $28,000 |
| 1480 | Construction signs (740B000) | SF | 969 | $6.05 | $6.39 | $6.60 | $8.00 |
| 1490 | Channelizing drums (740D000) | EACH | 250 | $30.00 | $63.90 | $66.00 | $32.00 |
| 1500 | Cones (36 inches high) (740E000) | EACH | 250 | $37.50 | $29.05 | $25.00 | $12.00 |
| 1510 | Barricades, type II (740F001) | EACH | 8 | $275.00 | $290.46 | $300.00 | $120.00 |
| 1520 | Portable sequential arrow and chevron sign unit (741C010) | EACH | 1 | $4,950.00 | $5,228.31 | $5,400.00 | $3,300.00 |
| 1530 | Portable changeable message sign, type 1 (742A002) | EACH | 2 | $11,550 | $12,199 | $12,600 | $8,500.00 |
| 1540 | 6" electrical conduit, 1 line, type 5 installation (756A028) | LF | 275 | $60.50 | $63.90 | $63.25 | $62.00 |
| 1550 | Bollard, complete in place (770L005) | EACH | 297 | $660.00 | $697.11 | $365.00 | $450.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of July 31, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.