ARDOT contract 040866 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO REPLACE THREE STRUCTURES ON HIGHWAY 45 IN WASHINGTON COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, EARTHWORK, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH SLABS AND GUTTERS, MAINTENANCE OF TRAFFIC, CONCRETE DITCH PAVING, MINOR DRAINAGE, GUARDRAIL, GEOTEXTILE FABRIC, EROSION CONTROL, PAVEMENT MARKING, CONSTRUCT ONE CONTINUOUS W-BEAM UNIT (262.31'), CONSTRUCT ONE INTERGRAL CONTINUOUS W-BEAM UNIT (169.00'), AND MISC. ITEMS. Let by Arkansas DOT on May 21, 2025, Washington. 6 bids received; low bid $9,548,186 by Crossland Construction Co., Inc..
- Owner
- Arkansas DOT
- Letting
- 21 MAY 2025
- Pay items
- 89
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Crossland Construction Co., Inc. | $9,548,186 | Low |
| 2 | Emery Sapp & Sons, Inc. | $9,628,679 | +1.0% |
| 3 | Robertson Contractors, Inc. | $9,731,524 | +2.0% |
| 4 | Mobley Contractors, Inc. | $10,211,974 | +7.0% |
| 5 | Grant Garrett Excavating, Inc. | $10,945,596 | +15% |
| 6 | Robinson Construction, LLC | $11,656,822 | +22% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Crossland Construction Co., Inc. | 2. Emery Sapp & Sons, Inc. | 3. Robertson Contractors, Inc. | 4. Mobley Contractors, Inc. | 5. Grant Garrett Excavating, Inc. | 6. Robinson Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 17 | $28,000 | $2,402.05 | $2,150.00 | $2,534.70 | $12,535 | $1,250.00 |
| 0002 | Grubbing (201111) | STA | 17 | $21,000 | $56.38 | $1,450.00 | $2,203.95 | $8,389.99 | $1,250.00 |
| 0003 | Removal and disposal of fence (202011) | LF | 6,420 | $2.07 | $1.77 | $2.20 | $4.20 | $1.86 | $2.00 |
| 0004 | Removal and disposal of gates (202017) | EACH | 1 | $311.00 | $316.05 | $225.00 | $927.15 | $258.84 | $650.00 |
| 0005 | Removal and disposal of pipe culverts (202096) | EACH | 10 | $788.00 | $988.35 | $885.00 | $674.63 | $871.22 | $480.00 |
| 0006 | Removal and disposal of box culverts (202097) | EACH | 1 | $38,107 | $6,992.39 | $15,000 | $13,413 | $5,626.22 | $6,500.00 |
| 0007 | Removal and disposal of guardrail (202132) | LF | 224 | $30.00 | $29.36 | $10.50 | $9.45 | $10.28 | $10.20 |
| 0008 | Removal of existing bridge structure (site no. 1) (205011) | LS | 1 | $87,062 | $184,757 | $105,000 | $160,603 | $186,471 | $155,000 |
| 0009 | Removal of existing bridge structure (site no. 2) (205012) | LS | 1 | $87,062 | $140,694 | $60,000 | $98,996 | $93,897 | $155,000 |
| 0010 | Flowable select material (206021) | CY | 25 | $221.50 | $316.76 | $380.00 | $282.45 | $357.12 | $320.00 |
| 0011 | Unclassified excavation (210213) | CY | 35,756 | $15.83 | $10.90 | $10.85 | $9.45 | $5.74 | $18.50 |
| 0012 | Compacted embankment (210611) | CY | 81,479 | $3.47 | $11.47 | $14.10 | $15.23 | $12.59 | $21.00 |
| 0013 | Soil stabilization (210702) | TON | 100 | $424.88 | $415.25 | $180.00 | $129.15 | $407.74 | $383.65 |
| 0014 | Aggregate base course (class 7) (303117) | TON | 12,733 | $31.69 | $35.78 | $38.00 | $42.00 | $36.43 | $46.50 |
| 0015 | Tack coat (401011) | GAL | 2,760 | $4.30 | $3.57 | $3.57 | $3.75 | $3.93 | $4.45 |
| 0016 | Mineral aggregate in achm binder course (1") (406161) | TON | 1,559 | $138.35 | $114.53 | $114.53 | $120.26 | $103.30 | $155.00 |
| 0017 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 72 | $134.22 | $120.00 | $120.00 | $126.00 | $120.00 | $120.00 |
| 0018 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 3,964 | $152.71 | $129.14 | $129.14 | $135.60 | $113.90 | $147.65 |
| 0019 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 240 | $134.23 | $120.00 | $120.00 | $126.00 | $120.00 | $120.00 |
| 0020 | Cold milling asphalt pavement (412002) | SY | 444 | $9.10 | $7.57 | $7.57 | $7.95 | $10.64 | $14.20 |
| 0021 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 30 | $315.63 | $205.41 | $250.00 | $215.68 | $209.06 | $285.00 |
| 0022 | Achm patching of existing roadway (415011) | TON | 30 | $247.26 | $205.41 | $205.41 | $215.68 | $209.06 | $255.00 |
| 0023 | Approach slabs (504031) | CY | 230.74 | $1,057.50 | $613.42 | $865.00 | $865.65 | $1,407.70 | $345.00 |
| 0024 | Approach gutters (504264) | CY | 32.92 | $2,904.27 | $2,901.94 | $1,185.00 | $1,094.55 | $1,632.98 | $780.00 |
| 0025 | Furnishing field office (602011) | EACH | 1 | $17,000 | $65,690 | $40,000 | $64,875 | $75,954 | $35,000 |
| 0026 | Maintenance of traffic (603009) | LS | 1 | $86,655 | $170,889 | $200,000 | $320,309 | $40,088 | $165,000 |
| 0027 | Signs (604003) | SF | 414 | $8.00 | $7.67 | $7.00 | $5.25 | $5.71 | $6.00 |
| 0028 | Construction project information sign update (604010) | EACH | 2 | $55.00 | $54.80 | $50.00 | $78.75 | $85.71 | $90.00 |
| 0029 | Barricades (604013) | LF | 96 | $28.00 | $27.40 | $25.00 | $15.75 | $17.14 | $18.00 |
| 0030 | Traffic drums (604023) | EACH | 70 | $39.00 | $38.36 | $35.00 | $26.25 | $28.57 | $30.20 |
| 0031 | Furnishing and installing precast concrete barrier (604031) | LF | 872 | $84.00 | $83.28 | $62.00 | $66.91 | $86.86 | $72.00 |
| 0032 | Relocating precast concrete barrier (max. bid 25% of item number ) (604036) | LF | 472 | $21.00 | $20.82 | $14.00 | $14.70 | $21.71 | $18.00 |
| 0033 | Construction pavement markings (604041) | LF | 23,787 | $0.33 | $0.33 | $0.30 | $0.26 | $0.29 | $0.04 |
| 0034 | Removable construction pavement markings (604051) | LF | 1,725 | $3.32 | $3.29 | $3.00 | $1.05 | $1.14 | $1.20 |
| 0035 | Removal of permanent pavement markings (604061) | LF | 2,950 | $1.11 | $1.10 | $1.00 | $1.26 | $1.37 | $1.55 |
| 0036 | Vertical panels (604083) | EACH | 108 | $43.00 | $42.74 | $39.00 | $26.25 | $28.57 | $31.00 |
| 0037 | Concrete ditch paving (type B) (605012) | SY | 1,018 | $174.00 | $86.24 | $135.00 | $61.95 | $84.84 | $165.00 |
| 0038 | 24" reinforced concrete pipe culverts (class V) (605609) | LF | 34 | $168.00 | $344.27 | $185.00 | $256.20 | $144.75 | $76.55 |
| 0039 | 24" flared end sections for reinforced concrete pipe culverts (605858) | EACH | 2 | $673.00 | $1,316.50 | $2,150.00 | $5,253.15 | $2,385.14 | $1,420.00 |
| 0040 | 18" side drain (606703) | LF | 358 | $140.39 | $125.49 | $82.00 | $84.00 | $84.64 | $52.50 |
| 0041 | 24" side drain (606704) | LF | 130 | $151.86 | $162.46 | $105.00 | $122.33 | $109.42 | $64.55 |
| 0042 | Selected pipe bedding (606994) | CY | 40 | $76.64 | $66.60 | $70.00 | $84.53 | $85.63 | $44.00 |
| 0043 | 4" pipe underdrains (611008) | LF | 3,000 | $41.43 | $15.85 | $3.60 | $28.88 | $31.64 | $26.50 |
| 0044 | Underdrain outlet protectors (611013) | EACH | 12 | $545.00 | $713.22 | $446.00 | $723.98 | $867.39 | $375.00 |
| 0045 | Guardrail (type A) (617015) | LF | 900 | $31.01 | $30.69 | $28.00 | $32.55 | $32.00 | $37.20 |
| 0046 | Guardrail terminal (type 2) (617312) | EACH | 8 | $2,990.00 | $2,958.79 | $2,700.00 | $3,150.00 | $3,085.58 | $3,600.00 |
| 0047 | Thrie beam guardrail terminal (617332) | EACH | 8 | $1,993.00 | $2,361.84 | $1,800.00 | $1,995.00 | $2,057.05 | $2,280.00 |
| 0048 | Wire fence (type D-2) (619030) | LF | 8,413 | $9.92 | $9.82 | $8.96 | $9.41 | $10.24 | $18.65 |
| 0049 | Lime (620001) | TON | 39 | $71.99 | $71.22 | $65.00 | $68.25 | $74.29 | $350.00 |
| 0050 | Seeding (620011) | ACRE | 19.59 | $1,404.00 | $1,389.69 | $1,268.14 | $1,331.55 | $1,449.24 | $1,550.00 |
| 0051 | Mulch cover (620022) | ACRE | 82.92 | $1,039.00 | $1,028.42 | $938.47 | $985.39 | $1,072.49 | $955.00 |
| 0052 | Water (620030) | MGAL | 3,298.80 | $5.54 | $5.00 | $5.00 | $5.25 | $5.71 | $5.00 |
| 0053 | Temporary seeding (621001) | ACRE | 63.33 | $874.00 | $865.02 | $789.35 | $828.82 | $902.07 | $420.00 |
| 0054 | Silt fence (621021) | LF | 10,280 | $3.74 | $3.70 | $3.38 | $3.55 | $3.86 | $4.85 |
| 0055 | Sediment removal and disposal (621111) | CY | 640 | $5.58 | $6.51 | $3.00 | $17.85 | $28.49 | $35.00 |
| 0056 | Rock ditch checks (621151) | CY | 777 | $148.26 | $56.94 | $95.00 | $116.03 | $64.33 | $74.00 |
| 0057 | Filter sock (18") (621169) | LF | 500 | $15.41 | $15.24 | $13.91 | $14.61 | $15.89 | $16.50 |
| 0058 | Second seeding application (623001) | ACRE | 19.59 | $471.00 | $465.74 | $425.00 | $446.25 | $485.70 | $620.00 |
| 0059 | Solid sodding (624001) | SY | 694 | $5.42 | $5.36 | $4.89 | $5.13 | $5.59 | $12.55 |
| 0060 | Geotextile fabric (type special) (625031) | SY | 4,659 | $6.00 | $13.37 | $8.05 | $12.08 | $4.64 | $9.85 |
| 0061 | Erosion control matting (class 3) (626003) | SY | 1,553 | $7.59 | $7.51 | $6.85 | $7.19 | $7.83 | $23.40 |
| 0062 | Roadway construction control (635001) | LS | 1 | $160,585 | $109,757 | $95,000 | $5,254.43 | $28,586 | $250,000 |
| 0063 | Bridge construction control (636001) | LS | 1 | $183,509 | $21,629 | $70,000 | $53,420 | $222,123 | $155,000 |
| 0064 | Reflectorized paint pavement marking white (6") (718002) | LF | 12,424 | $0.55 | $0.55 | $0.50 | $0.37 | $0.40 | $0.52 |
| 0065 | Reflectorized paint pavement marking yellow (6") (718102) | LF | 12,442 | $0.55 | $0.55 | $0.50 | $0.37 | $0.40 | $0.48 |
| 0066 | Raised pavement markers (type II) (721002) | EACH | 79 | $8.00 | $7.67 | $7.00 | $12.60 | $13.71 | $2.45 |
| 0067 | Temporary impact attenuation barrier (731071) | EACH | 2 | $4,430.00 | $4,383.38 | $4,000.00 | $5,460.00 | $5,942.59 | $6,240.00 |
| 0068 | Temporary impact attenuation barrier (repair) (731072) | EACH | 4 | $554.00 | $547.92 | $500.00 | $787.50 | $857.11 | $872.00 |
| 0069 | Temporary impact attenuation barrier (relocation) (731075) | EACH | 4 | $3,322.00 | $3,287.53 | $3,000.00 | $4,725.00 | $5,142.63 | $5,500.00 |
| 0070 | Unclassified excavation for structures-bridge (801001) | CY | 676 | $59.47 | $633.99 | $465.00 | $882.60 | $114.28 | $35.00 |
| 0071 | Unclassified excavation for structures-roadway (801101) | CY | 96 | $21.31 | $1,465.23 | $415.00 | $643.30 | $15.18 | $35.00 |
| 0072 | Class S concrete-roadway (802012) | CY | 218.44 | $1,647.73 | $1,284.76 | $1,255.00 | $1,673.75 | $1,318.36 | $1,450.00 |
| 0073 | Class S concrete-bridge (802112) | CY | 389.94 | $1,874.48 | $2,399.44 | $1,940.00 | $2,022.20 | $1,828.49 | $1,850.00 |
| 0074 | Class S(AE) concrete-bridge (802122) | CY | 475.30 | $1,567.65 | $1,472.60 | $1,885.00 | $1,918.01 | $1,828.49 | $1,650.00 |
| 0075 | Class 2 protective surface treatment (803004) | SY | 1,814 | $6.09 | $6.03 | $8.00 | $6.88 | $6.28 | $9.30 |
| 0076 | Reinforcing steel-roadway (grade 60) (804003) | LB | 58,387 | $2.24 | $0.93 | $2.05 | $1.58 | $1.32 | $4.10 |
| 0077 | Reinforcing steel-bridge (grade 60) (804013) | LB | 64,258 | $1.21 | $1.69 | $2.20 | $1.67 | $2.86 | $2.85 |
| 0078 | Epoxy coated reinforcing steel (grade 60) (804023) | LB | 130,824 | $1.41 | $1.72 | $2.25 | $1.80 | $3.23 | $4.10 |
| 0079 | Steel piling (HP 14X73) (805024) | LF | 426 | $147.07 | $136.78 | $205.00 | $195.93 | $160.55 | $450.00 |
| 0080 | Preboring (805504) | LF | 404 | $437.95 | $488.19 | $480.00 | $535.11 | $557.48 | $425.00 |
| 0081 | Structural steel in beam spans (A709, GR. 50W) (807017) | LB | 330,188 | $3.25 | $3.09 | $3.15 | $2.98 | $5.58 | $4.00 |
| 0082 | Painting structural steel (807301) | TON | 44.30 | $787.00 | $1,386.25 | $785.00 | $1,065.34 | $1,541.60 | $1,467.00 |
| 0083 | Elastomeric bearings (808002) | CUIN | 12,759.50 | $2.00 | $5.07 | $5.05 | $4.31 | $27.58 | $2.00 |
| 0084 | Silicone joint sealant (809015) | LF | 70 | $28.00 | $150.03 | $160.00 | $181.57 | $142.85 | $95.00 |
| 0085 | Bridge name plate (type D) (812004) | EACH | 2 | $5,537.00 | $541.89 | $550.00 | $908.26 | $11,428 | $4,000.00 |
| 0086 | Filter blanket (816003) | SY | 1,039 | $12.00 | $7.68 | $5.20 | $11.16 | $2.72 | $65.00 |
| 0087 | Foundation protection riprap (816032) | TON | 4,672 | $55.00 | $86.79 | $95.00 | $81.32 | $92.69 | $74.50 |
| 0088 | 16' steel gates (619332) | EACH | 5 | $874.00 | $865.18 | $789.50 | $828.98 | $902.24 | $450.00 |
| 0090 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $450,000 | $424,946 | $463,000 | $338,953 | $519,831 | $554,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of May 21, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.