FDOT contract T1917 bid tabulation

SR 17 FROM S OF CR 17 (KENILWORTH BLVD) TO E OF SR 25 (US 98. Let by Florida DOT on October 29, 2025, Highlands, District 1. 4 bids received; low bid $10,727,844 by Ohla USA Inc.

Owner
Florida DOT
Letting
29 OCT 2025
Pay items
142
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ohla USA Inc$10,727,844Low
2Ajax Paving Industries of Florida LLC$11,093,296+3.0%
3C.W. Roberts Contracting, Inc.$11,125,640+4.0%
4Watson Civil Construction, Inc.$12,283,909+15%
FDOT contract T1917: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ohla USA Inc2. Ajax Paving Industries of Florida LLC3. C.W. Roberts Contracting, Inc.4. Watson Civil Construction, Inc.
0005Mobilization (0101-1)LS1$1,070,000$160,300$250,000$146,400
0010Mobilization (0101-1)LS1$1.00$775,400$566,000$1,073,600
0015Maintenance of traffic (0102-1)DA1$750,000$46,220$9,000.00$65,000
0020Maintenance of traffic (0102-1)DA1$550,000$754,020$418,000$750,000
0025Pedestrian or bicycle special detour (0102-4-1)SY1$0.01$3,961.76$10,000$6,100.00
0030Traffic control officer (0102-14)HR3,070$110.00$80.00$89.00$120.00
0035Work zone sign (0102-60)ED23,981$0.21$0.23$0.25$0.30
0040Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED17,790$0.09$0.10$0.10$0.13
0045Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD5,310$0.05$0.06$0.05$0.08
0050Portable changeable message sign, temporary (0102-99)ED714$9.00$9.93$10.50$13.00
0055Type III barricade (0102-115)ED810$0.30$0.33$0.35$0.40
0060Sediment barrier (0104-10-3)LF9,653$3.00$0.94$4.25$1.75
0065Floating turbidity barrier (0104-11)LF284$16.50$13.24$16.50$15.00
0070Inlet protection system (0104-18)EACH139$215.00$148.90$152.50$135.00
0075Litter removal (0107-1)ACRE447.09$0.01$65.00$54.35$47.00
0080Mowing (0107-2)ACRE446.39$0.01$65.00$106.50$92.00
0085Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$100,000$20,000$19,000$13,000
0090Monitor existing structures- vibration monitoring (0108-2)LS1$10,000$5,500.00$4,600.00$25,000
0095Clearing & grubbing (0110-1-1)ACRE1$500,000$37,277$57,500$60,000
0100Clearing & grubbing (0110-1-1)ACRE1$500,000$87,943$10,000$80,000
0105Removal of existing concrete (0110-4-10)SY944$40.00$49.13$41.00$32.00
0110Regular excavation (0120-1)CY7.90$1.00$984.15$973.00$350.00
0115Borrow excavation, truck measure (0120-2-2)CY622$25.00$64.45$35.00$35.00
0120Embankment (0120-6)CY116.60$36.00$107.04$137.50$30.00
0125Regular excavation (3-R projects only) (0120-71)LS1$16,000$23,239$4,000.00$30,000
0130Type B stabilization (0160-4)SY829$0.01$90.13$35.50$34.00
0135Optional base, base group 09 (0285-709)SY566$65.00$164.81$76.35$175.00
0140Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY260,167$2.60$3.21$3.70$3.45
0145Superpave asphaltic conc, traffic C (0334-1-13)TN360.80$190.00$334.59$357.00$356.00
0150Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN21,625.10$160.00$184.09$202.00$197.00
0155Concrete class II, bulkhead (0400-2-8)CY48.50$0.01$3,805.28$2,450.00$1,800.00
0160Reinforcing steel- bulkhead (0415-1-8)LB7,001$0.01$3.31$2.15$2.90
0165Inlets, curb, type 9, <10' (0425-1201)EACH1$10,000$11,030$11,750$7,300.00
0170Inlets, ditch bottom, type C, partial (0425-1525)EACH1$6,000.00$5,184.01$5,500.00$8,300.00
0175Inlets, DT bot, type C, modify (0425-1529)EACH2$10,000$5,404.60$5,700.00$4,200.00
0180Inlets, closed flume (0425-1910)EACH1$10,000$12,133$13,000$9,200.00
0185Manholes, J-7, partial (0425-2-73)EACH1$8,000.00$9,926.82$10,500$6,700.00
0190Manholes, J-8, <10' (0425-2-91)EACH1$17,500$16,545$17,500$8,500.00
0195Manholes, J-8, >10' (0425-2-92)EACH2$25,000$25,479$27,000$14,000
0200Pipe culvert,optional material,round, 15"S/CD (0430-175115)LF4$900.00$1,500.05$1,600.00$345.00
0205Pipe culvert,optional material,round, 24"S/CD (0430-175124)LF28$250.00$683.85$723.00$324.00
0210Pipe culvert, opt material, round, 36"S/CD (0430-175136)LF8$600.00$1,433.87$1,600.00$443.00
0215Pipe culvert, opt material, round, 42"S/CD (0430-175142)LF13$500.00$1,323.58$1,400.00$531.00
0220Pipe culvert, opt material, round, 48"S/CD (0430-175148)LF34$600.00$1,654.47$1,700.00$600.00
0225Pipe culvert,optional material,other-elip/arch, (0430-175218)LF39$240.00$529.43$570.00$250.00
0230PVC pipe for back of sidewalk, (0430-963-1)LF48$125.00$386.04$156.00$210.00
0235Sheet piling steel, F&I (0455-133-3)SF2,912$0.01$169.86$160.00$425.00
0240Concrete curb & gutter, type F (0520-1-10)LF1,444$70.00$35.84$72.00$50.00
0245Valley gutter- concrete (0520-3)LF88$95.00$52.10$95.00$85.00
0250Concrete sidewalk and driveways, 4" thick (0522-1)SY358$130.00$92.01$154.00$69.00
0255Concrete sidewalk and driveways, 6" thick (0522-2)SY401$150.00$107.46$160.00$89.00
0257Concrete ditch pavement, non reinforced, 4" (0524-1-2)SY6$350.00$1,497.14$1,300.00$555.00
0260Detectable warnings (0527-2)SF2,862$25.00$28.49$34.00$38.00
0265Articulating concrete block revetment system, thickness 9" (0530-4-9)SY79$600.00$1,036.80$1,100.00$660.00
0270Performance turf (0570-1-1)SY868$6.50$10.46$10.00$7.00
0275Performance turf, sod (0570-1-2)SY24,690$6.80$5.68$7.25$7.70
0280Irrigation system- modify existing system (0590-70-5)LS1$10,000$54,873$520.00$13,000
0285Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF32$6.25$4.41$4.50$4.20
0290Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM0.02$3,000.00$3,860.43$3,900.00$3,500.00
0295Initial contingency amount, DO not bid (0999-25)LS1$30,000$30,000$30,000$30,000
0300Initial contingency amount, DO not bid (0999-25)LS1$54,458$54,458$54,458$54,458
0305Utility pipe- high density polyethylene, furnish & install, casing/conduit, 6" (1050-42106)LF8$1,000.00$496.34$525.00$333.00
0310Midblock crosswalk: rec rapid flashing beacon, solar, sign assembly- back-back accessible detector (0654-2-28)AS12$11,500$12,574$13,800$11,800
0315Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH21$550.00$606.64$590.00$570.00
0320Single column ground sign assembly, relocate (0700-1500)EACH5$500.00$595.61$495.00$560.00
0325Single column ground sign assembly, remove (0700-1600)EACH13$35.00$49.63$60.00$47.00
0330Single column ground sign assembly, F&I cantilever mount, 12.0-20.0 SF (0700-1912)EACH3$4,300.00$4,632.52$3,450.00$4,400.00
0335Single column ground sign assembly, F&I cantilever mount, 20.1-30.0 SF (0700-1913)EACH1$3,400.00$4,191.32$4,600.00$4,000.00
0340Single column ground sign assembly, F&I cantilever mount, 30.1+ SF (0700-1914)EACH1$3,500.00$4,411.92$5,100.00$4,200.00
0345Multi-column ground sign assembly, F&I ground mount, 20.0 SF (0700-2112)EACH2$5,000.00$6,066.39$5,800.00$5,700.00
0350Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113)EACH2$5,500.00$6,397.28$7,400.00$6,000.00
0355Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114)EACH1$8,250.00$9,375.33$8,400.00$8,800.00
0360Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH11$325.00$386.04$340.00$361.00
0365Sign panel, furnish & install ground mount, 12-20 SF (0700-3102)EACH1$350.00$441.19$625.00$415.00
0370Sign panel, remove, UP to 12 SF (0700-3601)EACH10$40.00$49.63$48.00$47.00
0375Sign panel, remove, 12-20 SF (0700-3602)EACH2$40.00$49.63$65.00$47.00
0380Delineator, flexible tubular (0705-11-1)EACH24$135.00$165.45$226.00$92.00
0385Raised pavement marker, type B (0706-1-3)EACH4,631$4.00$4.41$4.70$4.20
0390Painted pavement markings, surface (0710-90)LS1$105,000$123,977$132,000$110,000
0395Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF5,986$3.00$3.39$3.50$3.20
0400Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF6,571$4.25$5.07$5.50$4.85
0405Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF4,281$5.50$6.77$7.20$6.50
0410Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.75$2,500.00$2,481.71$2,600.00$2,370.00
0415Thermoplastic, standard, message or symbol (0711-11160)EACH40$115.00$137.87$146.75$131.00
0420Thermoplastic, standard, arrow (0711-11170)EACH83$48.00$59.56$63.50$57.00
0425Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF3,273$5.00$4.62$5.00$4.40
0430Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.12$4,250.00$2,481.71$2,500.00$2,300.00
0435Thermoplastic, standard, blue, solid,6" (0711-11421)LF324$6.50$6.51$7.00$6.20
0440Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF2,924$14.00$17.63$18.50$17.00
0445Thermoplastic, preformed, white, message (0711-14160)EACH44$300.00$292.29$311.00$277.00
0450Thermoplastic, preformed, white, arrow (0711-14170)EACH26$75.00$95.96$102.00$91.00
0455Thermoplastic, preformed, 6" white, railroad dynamic envelope (0711-14191)LF364$6.00$4.96$5.25$4.70
0460Thermoplastic, preformed, 12" white on asphalt pavement, railroad dynamic envelope (0711-14193)LF386$12.00$8.82$9.40$8.40
0465Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101)GM0.03$8,000.00$7,278.57$7,300.00$6,500.00
0470Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201)GM0.04$10,500$6,671.93$7,000.00$6,200.00
0475Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM22.63$4,250.00$5,174.08$5,500.00$4,900.00
0480Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.26$6,500.00$6,898.04$7,150.00$6,400.00
0485Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM0.70$4,500.00$1,293.80$1,400.00$1,220.00
0490Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM22.11$4,500.00$4,756.05$5,050.00$4,500.00
0495Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM0.91$2,500.00$1,189.01$1,250.00$1,120.00
0500Conduit, furnish & install, open trench (0630-2-11)LF338$20.00$27.57$25.00$19.00
0505Conduit, furnish & install, directional bore (0630-2-12)LF1,580$25.00$32.54$35.00$38.00
0510Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH44$1,250.00$1,654.47$2,150.00$1,200.00
0515Electrical power service, F&I, underground, meter by contractor (0639-1122)AS8$6,500.00$4,136.18$6,500.00$5,420.00
0520Electrical service wire, & install (0639-2-1)LF176$3.50$24.27$5.85$13.00
0525Electrical service disconnect, F&I, pole mount (0639-3-11)EACH8$1,500.00$2,095.66$1,675.00$3,420.00
0530Prestressed concrete pole, install (0641-2-30)EACH8$1,700.00$2,316.26$1,525.00$3,400.00
0535Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF7,652$2.25$2.32$2.25$4.30
0540Luminaire & bracket arm, luminaire and arm; pole remains (0715-5-51)EACH1$250.00$242.66$420.00$233.00
0545Load center, F&I, primary voltage (0715-7-12)EACH8$9,950.00$18,751$14,000$17,000
0550Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 8' arm length (0715-61111)EACH11$6,500.00$10,754$8,900.00$7,400.00
0555Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 12' arm length (0715-61142)EACH4$7,500.00$10,809$9,200.00$11,300
0560Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 8' arm length (0715-61311)EACH3$8,500.00$11,361$9,400.00$7,500.00
0565Light pole complete, remove pole and foundation (0715-69000)EACH4$1,650.00$1,009.23$2,100.00$697.00
0570Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH18$650.00$954.08$775.00$815.00
0575Initial contingency amount, DO not bid (0999-25)LS1$20,000$20,000$20,000$20,000
0580Conduit, furnish & install, open trench (0630-2-11)LF1,002$20.00$36.95$26.00$54.50
0585Conduit, furnish & install, directional bore (0630-2-12)LF1,480$44.00$51.84$58.00$54.50
0590Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI6$8,900.00$4,687.67$7,500.00$13,400
0595Signal cable, remove- intersection (0632-7-6)PI6$3,500.00$623.18$2,900.00$930.00
0600Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH86$1,135.00$1,875.07$2,100.00$1,200.00
0605Aluminum signals pole, (0646-1-11)EACH26$2,500.00$2,592.00$3,300.00$2,450.00
0610Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH4$1,250.00$722.45$1,700.00$2,400.00
0615Aluminum signals pole, remove (0646-1-60)EACH16$900.00$319.86$950.00$700.00
0620Vehicular traffic signal, furnish & install aluminum, 1 section, 1 way (0650-1-11)AS10$1,500.00$920.99$1,100.00$900.00
0625Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS1$3,000.00$2,095.66$1,800.00$1,520.00
0630Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16)AS1$4,000.00$2,757.45$2,400.00$1,950.00
0635Vehicular traffic signal, remove- poles to remain (0650-1-60)AS12$55.00$154.42$35.00$117.00
0640Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- black with reflect border (0650-2102)EACH30$500.00$860.32$750.00$543.00
0645Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS24$780.00$909.96$960.00$800.00
0650Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS2$3,000.00$1,764.77$1,900.00$1,680.00
0655Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS9$150.00$132.36$111.50$117.00
0660Loop detector inductive , F&I, type 6, 2 CH,SS,S,TD (0660-1106)EACH13$900.00$1,102.98$1,150.00$1,020.00
0665Loop detector inductive, F&I, type 12, 4 CH, SS, RM, TD (0660-1112)EACH25$350.00$628.70$650.00$621.00
0670Loop assembly, F&I, type B (0660-2102)AS11$850.00$2,040.51$1,330.00$1,300.00
0675Loop assembly, F&I, type E (0660-2105)AS2$1,900.00$2,592.00$1,750.00$1,900.00
0680Loop assembly, F&I, type F (0660-2106)AS25$2,200.00$1,819.92$2,750.00$2,200.00
0685Pedestrian detector, furnish & install, standard (0665-1-11)EACH28$500.00$408.10$411.00$270.00
0690Traffic controller, modify (0671-2-40)EACH6$650.00$2,150.81$900.00$8,100.00
0695ITS CCTV camera, pressurized, high definition (0682-1163)EACH6$7,500.00$7,279.67$10,300$5,600.00
0700Cellular modem, furnish and install (0684-8-1)EACH5$5,500.00$5,404.60$5,700.00$4,200.00
0705Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH1$1,000.00$1,378.73$1,375.00$1,150.00
FDOT contract T1917: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of October 29, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy