FDOT contract T5836 bid tabulation
SR 60 FROM BLANKET BAY SLOUGH TO PEAVINE TR. Let by Florida DOT on March 26, 2025, Osceola, District 5. 7 bids received; low bid $18,317,204 by C.W. Roberts Contracting, Inc..
- Owner
- Florida DOT
- Letting
- 26 MAR 2025
- Pay items
- 89
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | C.W. Roberts Contracting, Inc. | $18,317,204 | Low |
| 2 | Southland Construction, Inc. | $19,500,000 | +6.0% |
| 3 | Ohla USA Inc | $19,613,473 | +7.0% |
| 4 | Watson Civil Construction, Inc. | $20,283,668 | +11% |
| 5 | Ajax Paving Industries of Florida LLC | $21,946,052 | +20% |
| 6 | Sema Construction, Inc. | $24,790,000 | +35% |
| 7 | Ranger Construction Industries, Inc. | $27,421,769 | +50% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. C.W. Roberts Contracting, Inc. | 2. Southland Construction, Inc. | 3. Ohla USA Inc | 4. Watson Civil Construction, Inc. | 5. Ajax Paving Industries of Florida LLC | 6. Sema Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $1,483,000 | $1,587,121 | $1,946,760 | $2,020,000 | $930,180 | $2,450,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $1,600,000 | $1,120,000 | $1,030,730 | $1,500,000 | $765,573 | $700,000 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $470,000 | $1,018,000 | $450,000 | $950,000 | $831,942 | $1,200,000 |
| 0020 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $485,000 | $854,000 | $400,000 | $906,000 | $871,214 | $1,500,000 |
| 0025 | Commercial material for temporary driveway maintenance (0102-3) | CY | 60.50 | $206.00 | $160.00 | $140.00 | $270.00 | $90.63 | $330.00 |
| 0030 | Traffic control officer (0102-14) | HR | 3,192 | $138.00 | $93.00 | $83.00 | $90.00 | $108.40 | $100.00 |
| 0035 | Work zone sign (0102-60) | ED | 13,982 | $0.25 | $0.22 | $0.20 | $0.28 | $0.24 | $0.40 |
| 0040 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 23,088 | $0.01 | $39.40 | $36.00 | $36.40 | $39.82 | $38.00 |
| 0045 | Temporary barrier, relocate, anchored (0102-71-25) | LF | 21,060 | $0.01 | $16.90 | $15.50 | $15.65 | $17.09 | $16.00 |
| 0050 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 55,881 | $0.10 | $0.11 | $0.09 | $0.13 | $0.12 | $0.25 |
| 0055 | Temporary crash cushion, redirective option (0102-89-1) | LO | 44 | $0.01 | $1,070.00 | $3,000.00 | $1,675.00 | $1,205.64 | $4,000.00 |
| 0060 | Portable changeable message sign, temporary (0102-99) | ED | 914 | $10.00 | $10.00 | $9.00 | $13.00 | $11.61 | $15.00 |
| 0065 | Portable regulatory, sign (0102-150-1) | ED | 900 | $5.00 | $4.90 | $4.25 | $6.00 | $4.98 | $7.00 |
| 0070 | Radar speed display unit (0102-150-2) | ED | 900 | $5.00 | $4.90 | $4.25 | $6.00 | $5.25 | $7.00 |
| 0075 | Removable tape, white, solid 6" (0102-913-21) | GM | 2.68 | $15,000 | $13,300 | $12,000 | $12,800 | $14,215 | $13,600 |
| 0080 | Removable tape, yellow, solid, (0102-913-31) | GM | 2.67 | $15,000 | $13,300 | $12,000 | $13,800 | $14,215 | $13,600 |
| 0085 | Sediment barrier (0104-10-3) | LF | 30,335 | $3.35 | $0.96 | $3.00 | $1.75 | $0.88 | $1.80 |
| 0090 | Floating turbidity barrier (0104-11) | LF | 74 | $11.50 | $11.00 | $12.00 | $13.70 | $10.93 | $14.00 |
| 0095 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 5,876 | $5.50 | $5.70 | $5.00 | $5.70 | $5.19 | $5.50 |
| 0100 | Soil tracking prevention device (0104-15) | EACH | 4 | $5,000.00 | $3,400.00 | $0.01 | $3,600.00 | $1,500.00 | $6,400.00 |
| 0105 | Litter removal (0107-1) | ACRE | 509.46 | $51.50 | $27.00 | $45.00 | $47.00 | $45.00 | $60.00 |
| 0110 | Mowing (0107-2) | ACRE | 474.15 | $109.00 | $82.00 | $87.00 | $88.00 | $85.00 | $120.00 |
| 0115 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $256,000 | $111,000 | $1,730,000 | $905,000 | $670,422 | $1,318,339 |
| 0120 | Regular excavation (0120-1) | CY | 67,874.60 | $6.90 | $10.10 | $17.00 | $12.00 | $14.00 | $22.00 |
| 0125 | Subsoil excavation (0120-4) | CY | 2,898.50 | $23.00 | $26.00 | $18.00 | $36.00 | $172.31 | $35.00 |
| 0130 | Embankment (0120-6) | CY | 35,011.90 | $6.25 | $11.55 | $15.50 | $6.00 | $3.72 | $3.00 |
| 0135 | Type B stabilization (0160-4) | SY | 53,438 | $7.65 | $9.25 | $8.50 | $15.00 | $48.68 | $19.00 |
| 0140 | Optional base, base group 01 (0285-701) | SY | 17,682 | $27.25 | $33.30 | $33.00 | $35.00 | $30.49 | $32.00 |
| 0145 | Optional base, base group 10 (0285-710) | SY | 20,731 | $52.25 | $53.80 | $51.00 | $55.00 | $49.23 | $52.00 |
| 0150 | Turnout base- optional materials (0286-1) | SY | 72 | $82.25 | $59.40 | $56.00 | $132.00 | $68.13 | $71.00 |
| 0155 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 275 | $31.00 | $18.60 | $35.00 | $17.50 | $16.78 | $18.00 |
| 0160 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 20,943 | $6.20 | $5.15 | $7.10 | $4.80 | $4.66 | $4.90 |
| 0165 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 9,743 | $5.25 | $3.70 | $3.80 | $3.50 | $3.34 | $3.60 |
| 0170 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 9,742 | $3.25 | $3.25 | $3.30 | $3.10 | $2.95 | $3.10 |
| 0175 | Superpave asphaltic conc, traffic E (0334-1-15) | TN | 9,386.70 | $183.25 | $170.00 | $150.00 | $160.00 | $170.77 | $170.00 |
| 0180 | Asphalt concrete friction course,traffic E, FC-12.5, PG (0337-7-88) | TN | 6,472 | $188.50 | $186.00 | $170.00 | $173.00 | $190.12 | $180.00 |
| 0185 | Miscellaneous asphalt (0339-1) | TN | 381.50 | $438.50 | $409.00 | $275.00 | $380.00 | $463.56 | $600.00 |
| 0190 | Inlets, DT bot, type H, modify (0425-1589) | EACH | 2 | $27,000 | $21,300 | $20,000 | $15,000 | $14,515 | $10,400 |
| 0195 | Inlets, gutter, type S, <10' (0425-1701) | EACH | 22 | $8,300.00 | $7,800.00 | $9,500.00 | $6,000.00 | $6,586.54 | $8,900.00 |
| 0200 | Inlets, gutter, type S, J bottom <10' (0425-1703) | EACH | 26 | $11,300 | $9,060.00 | $12,000 | $8,000.00 | $12,878 | $10,500 |
| 0205 | Inlets, gutter, type S, J bottom, >10' (0425-1704) | EACH | 16 | $15,800 | $10,230 | $14,500 | $9,600.00 | $12,993 | $15,700 |
| 0210 | Manholes, J-8, >10' (0425-2-92) | EACH | 4 | $19,300 | $10,400 | $14,000 | $8,900.00 | $10,494 | $14,600 |
| 0215 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 42 | $150.00 | $232.00 | $105.00 | $152.00 | $183.93 | $420.00 |
| 0220 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 809 | $150.00 | $169.00 | $100.00 | $93.00 | $186.95 | $310.00 |
| 0225 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 1,156 | $167.35 | $226.00 | $130.00 | $120.00 | $223.51 | $330.00 |
| 0230 | Pipe culvert, opt material, round, 30"S/CD (0430-175130) | LF | 2,080 | $213.50 | $300.00 | $180.00 | $200.00 | $290.93 | $380.00 |
| 0235 | Pipe culvert, opt material, round, 36"S/CD (0430-175136) | LF | 5,624 | $282.75 | $349.00 | $215.00 | $249.00 | $360.41 | $460.00 |
| 0240 | Pipe culvert, opt material, round, 42"S/CD (0430-175142) | LF | 276 | $363.50 | $413.00 | $255.00 | $310.00 | $445.89 | $870.00 |
| 0245 | Pipe culvert,optional material,other-elip/arch, (0430-175218) | LF | 141 | $225.00 | $256.00 | $140.00 | $195.00 | $230.35 | $610.00 |
| 0250 | Pipe culvert,optional material,round, jack & bore, 24", storm and cross drain (0430-185124) | LF | 321 | $2,540.00 | $1,210.00 | $1,500.00 | $1,050.00 | $1,591.35 | $1,300.00 |
| 0255 | Pipe culvert,optional material,round, jack & bore, 36", storm and cross drain (0430-185136) | LF | 158 | $3,230.00 | $1,760.00 | $1,700.00 | $1,075.00 | $1,584.14 | $1,400.00 |
| 0260 | Straight concrete endwalls, double, 0 degrees, round (0430-524200) | EACH | 1 | $13,500 | $15,800 | $8,000.00 | $5,200.00 | $6,495.78 | $7,300.00 |
| 0265 | Straight concrete endwalls, double, 0 degrees, round (0430-530200) | EACH | 2 | $16,500 | $11,400 | $9,400.00 | $7,500.00 | $8,125.50 | $8,400.00 |
| 0270 | Straight concrete endwalls, double, 0 degrees, round (0430-536200) | EACH | 2 | $18,500 | $12,500 | $11,975 | $15,300 | $9,824.23 | $9,400.00 |
| 0275 | U-endwall with baffles, index 261/430-011, 1:2 slope, 18"pipe (0430-611325) | EACH | 5 | $9,800.00 | $8,280.00 | $5,700.00 | $4,300.00 | $6,689.52 | $5,700.00 |
| 0280 | Mitered end section, optional round, 36" CD (0430-982138) | EACH | 1 | $7,500.00 | $10,000 | $11,350 | $5,300.00 | $9,562.43 | $9,700.00 |
| 0285 | Mitered end section, optional round, 42" CD (0430-982140) | EACH | 1 | $9,000.00 | $11,600 | $12,300 | $7,000.00 | $10,685 | $11,400 |
| 0290 | Mitered end section, optional - elliptical / arch, 18" CD (0430-982625) | EACH | 7 | $4,500.00 | $2,650.00 | $5,400.00 | $2,300.00 | $3,132.24 | $4,400.00 |
| 0295 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 2 | $3,230.00 | $2,600.00 | $5,200.00 | $1,900.00 | $3,147.38 | $4,300.00 |
| 0300 | Shoulder gutter- concrete (0520-6) | LF | 11,032 | $41.00 | $38.00 | $52.00 | $35.00 | $48.68 | $56.00 |
| 0305 | Concrete ditch pavement, 4", reinforced (0524-1-29) | SY | 189 | $173.00 | $93.00 | $310.00 | $147.00 | $176.04 | $450.00 |
| 0310 | Guardrail -roadway, general (0536-1-1) | LF | 11,381 | $26.00 | $24.80 | $20.50 | $20.50 | $21.13 | $21.00 |
| 0315 | Special guardrail post- post for shallow mount (0536-7-3) | EACH | 12 | $118.00 | $150.00 | $145.00 | $142.00 | $148.69 | $150.00 |
| 0320 | Guardrail end treatment- trailing anchorage (0536-85-20) | EACH | 4 | $1,335.00 | $1,185.00 | $1,300.00 | $1,120.00 | $1,171.50 | $1,200.00 |
| 0325 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 4 | $3,370.00 | $2,900.00 | $3,000.00 | $2,750.00 | $2,869.29 | $2,800.00 |
| 0330 | Fencing, type A, 0.0-5.0', standard (0550-10110) | LF | 211 | $45.00 | $45.75 | $49.00 | $20.00 | $21.67 | $43.00 |
| 0335 | Fence gate, type A, double, 12.1- 18.0' opening (0550-60123) | EACH | 2 | $3,755.00 | $1,070.00 | $4,004.00 | $1,500.00 | $1,625.16 | $1,000.00 |
| 0340 | Performance turf, sod (0570-1-2) | SY | 147,291 | $6.10 | $3.44 | $2.80 | $6.50 | $5.49 | $4.00 |
| 0345 | Raised pavement marker, type B (0706-1-3) | EACH | 14,428 | $5.25 | $5.00 | $4.50 | $4.40 | $4.88 | $4.70 |
| 0350 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 26.11 | $1,160.00 | $1,660.00 | $1,500.00 | $1,400.00 | $1,068.39 | $1,000.00 |
| 0355 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 23.48 | $1,158.00 | $1,660.00 | $1,500.00 | $1,400.00 | $1,058.36 | $1,000.00 |
| 0360 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 0.42 | $681.00 | $900.00 | $785.00 | $340.00 | $644.04 | $700.00 |
| 0365 | Disputes review board, meeting- DO not bid (0999-20-1) | DA | 11 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 |
| 0370 | Disputes review board, hearing- DO not bid (0999-20-2) | EACH | 2 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 |
| 0375 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $150,000 | $150,000 | $150,000 | $150,000 | $150,000 | $150,000 |
| 0380 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 9.12 | $1,765.00 | $2,445.00 | $2,700.00 | $2,550.00 | $1,465.70 | $2,800.00 |
| 0385 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 2 | $695.00 | $449.00 | $410.00 | $490.00 | $444.21 | $630.00 |
| 0390 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 5 | $1,735.00 | $1,830.00 | $1,680.00 | $2,000.00 | $1,774.87 | $1,600.00 |
| 0395 | Single column ground sign assembly, remove (0700-1600) | EACH | 1 | $46.25 | $55.00 | $50.00 | $26.00 | $54.17 | $42.00 |
| 0400 | Multi-column ground sign assembly, F&I ground mount, 100.0 SF (0700-2115) | EACH | 6 | $9,500.00 | $6,700.00 | $6,250.00 | $12,400 | $6,570.60 | $8,600.00 |
| 0405 | Raised pavement marker, type B (0706-1-3) | EACH | 1,280 | $5.80 | $5.00 | $4.50 | $4.40 | $5.42 | $5.50 |
| 0410 | Painted pavement markings, surface (0710-90) | LS | 1 | $34,700 | $36,000 | $33,000 | $22,000 | $31,450 | $31,500 |
| 0415 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 8 | $230.00 | $332.00 | $300.00 | $104.00 | $216.69 | $210.00 |
| 0420 | Thermoplastic, standard, arrow (0711-11170) | EACH | 8 | $92.50 | $99.65 | $90.00 | $131.00 | $83.46 | $84.00 |
| 0425 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 806 | $8.00 | $7.75 | $7.00 | $5.45 | $7.58 | $7.50 |
| 0430 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 7.22 | $7,000.00 | $5,750.00 | $5,200.00 | $6,900.00 | $6,320.05 | $6,300.00 |
| 0435 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 1.56 | $2,100.00 | $3,320.00 | $3,000.00 | $2,625.00 | $1,950.19 | $1,900.00 |
| 0440 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 7.69 | $6,950.00 | $5,750.00 | $5,200.00 | $6,900.00 | $6,380.24 | $6,300.00 |
| 0445 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.48 | $2,100.00 | $3,320.00 | $2,975.00 | $2,600.00 | $1,950.19 | $1,900.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of March 26, 2025. Compiled by Mirage Metrics.