FDOT contract T5852 bid tabulation

SR 500 (US 441) FROM MILLS ST TO COLLEGE DR. Let by Florida DOT on June 11, 2025, Lake, District 5. 5 bids received; low bid $8,337,454 by C.W. Roberts Contracting, Inc..

Owner
Florida DOT
Letting
11 JUN 2025
Pay items
144
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1C.W. Roberts Contracting, Inc.$8,337,454Low
2Ranger Construction Industries, Inc.$8,394,558+1.0%
3Superior Asphalt, Inc.$8,821,001+6.0%
4Masci General Contractors, Inc$10,112,994+21%
5Anderson Columbia Co., Inc.$11,286,787+35%
FDOT contract T5852: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. C.W. Roberts Contracting, Inc.2. Ranger Construction Industries, Inc.3. Superior Asphalt, Inc.4. Masci General Contractors, Inc5. Anderson Columbia Co., Inc.
0005Mobilization (0101-1)LS1$723,955$625,000$636,224$887,000$1,116,095
0010Maintenance of traffic (0102-1)DA1$407,353$279,100$555,000$332,100$497,176
0015Commercial material for temporary driveway maintenance (0102-3)CY5.30$190.00$109.90$245.00$99.50$756.60
0020Pedestrian or bicycle special detour (0102-4-1)SY1$11,000$1,000.00$8,135.00$8,774.50$13,533
0025Traffic control officer (0102-14)HR136$100.00$93.40$115.00$97.50$155.05
0030Pedestrian escort operation (0102-25100)HR1,008$33.00$29.80$38.00$72.50$124.22
0035Work zone sign (0102-60)ED23,976$0.25$0.25$0.30$0.24$0.28
0040Temporary barrier, F&I, low profile, concrete (0102-71-13)LF474$43.50$42.85$47.75$43.00$52.58
0045Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED33,716$0.11$0.10$0.15$0.14$0.13
0050Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD2,296$0.06$0.05$0.10$0.09$0.07
0055Arrow board / advance warning arrow panel (0102-76)ED808$5.60$5.50$5.25$6.00$6.74
0060Portable changeable message sign, temporary (0102-99)ED568$11.00$11.00$11.40$14.00$13.48
0065Temporary signalization and maintenance, intersection (0102-104)ED540$21.00$17.35$60.00$18.98$21.31
0070Temporary traffic detection and maintenance, intersection (0102-107-1)ED540$21.00$17.35$39.00$18.98$21.31
0075Type III barricade (0102-115)ED72$0.40$0.40$1.10$1.00$0.47
0080Sediment barrier (0104-10-3)LF4,448$3.05$2.90$1.35$1.50$4.67
0085Soil tracking prevention device (0104-15)EACH2$1,900.00$1,500.00$5,205.00$2,900.00$8,414.90
0090Inlet protection system (0104-18)EACH216$155.00$214.30$135.50$200.00$202.23
0095Litter removal (0107-1)ACRE600$22.50$22.00$47.75$25.89$26.96
0100Mowing (0107-2)ACRE600$67.50$65.90$84.75$80.89$87.63
0105Clearing & grubbing (0110-1-1)ACRE1$91,450$10,170$81,000$45,430$73,311
0110Removal of existing concrete (0110-4-10)SY836$43.00$21.15$37.80$37.50$116.10
0115Mailbox, F&I single (0110-7-1)EACH3$825.00$236.50$196.75$300.00$269.64
0120Regular excavation (0120-1)CY407.30$57.00$20.05$54.00$29.50$139.78
0125Embankment (0120-6)CY451.60$65.00$22.45$48.75$31.20$126.83
0130Type B stabilization (0160-4)SY2,931$25.00$20.40$30.25$23.50$22.91
0135Optional base, base group 01 (0285-701)SY431$75.50$25.90$33.25$59.30$68.56
0140Optional base, base group 03 (0285-703)SY28$88.75$39.25$38.50$59.30$91.66
0145Optional base, base group 09 (0285-709)SY1,542$42.25$30.85$41.75$45.20$52.08
0150Milling existing asphalt pavement, 2" avg depth (0327-70-5)SY200,534$1.75$2.45$2.35$2.95$4.50
0155Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY5,726$3.35$1.00$2.20$2.59$3.11
0160Milling existing asphalt pavement, 4" avg depth (0327-70-7)SY21,854$3.55$4.70$3.15$4.15$6.06
0165Superpave asphaltic conc, traffic C (0334-1-13)TN3,134.50$120.00$122.80$141.45$185.52$166.24
0170Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN24,551.20$143.75$155.50$155.40$193.52$172.62
0175Miscellaneous asphalt (0339-1)TN1.50$4,300.00$514.50$415.00$1,320.00$661.82
0180Inlets, DT bot, type C,jbot, <10' (0425-1523)EACH1$12,000$14,800$10,260$15,645$15,023
0185Inlets, ditch bottom, type C, partial (0425-1525)EACH1$4,800.00$4,980.00$11,880$4,523.00$7,934.12
0190Manhole, adjust (0425-5)EACH19$280.00$722.50$1,300.00$1,230.00$1,756.05
0195Pipe culvert, optional material, other shape - ellip/arch, 24"SD (0430-174224)LF100$235.00$209.40$324.00$299.56$201.69
0200Pipe culvert, opt material, round, 36"S/CD (0430-175136)LF18$500.00$640.00$378.00$459.60$446.38
0205Mitered end sect, optional - elliptical / arch, 24" SD (0430-984629)EACH12$4,000.00$3,180.00$324.00$4,500.00$3,166.23
0210Pedestrian / bicycle railing, NS, 42" type 1 (0515-2111)LF15$225.00$527.50$162.75$217.00$269.64
0215Concrete curb & gutter, type E (0520-1-7)LF340$69.00$102.80$54.00$50.90$95.45
0220Concrete curb & gutter, type F (0520-1-10)LF963$65.00$74.90$59.50$50.90$93.47
0225Concrete curb, type D (0520-2-4)LF5$120.00$280.80$48.50$112.50$274.84
0230Traffic separator concrete- type I, 4' wide (0520-5-11)LF155$110.75$79.60$243.00$110.50$248.74
0235Median concrete barrier, tall grade-separated (0521-1-13)LF311$625.00$560.00$675.00$720.00$1,219.93
0240Concrete sidewalk and driveways, 4" thick (0522-1)SY772$87.50$75.00$75.75$99.65$189.57
0245Concrete sidewalk and driveways, 6" thick (0522-2)SY628$155.00$160.90$97.25$121.50$200.79
0250Detectable warnings (0527-2)SF1,004$33.50$48.35$23.00$33.29$52.58
0255Guardrail -roadway, general (0536-1-1)LF67$28.00$70.60$27.25$40.00$53.93
0260Pipe rail for guardrail (0536-6)LF37$28.00$43.70$27.25$35.00$40.44
0265Guardrail removal (0536-73)LF76$5.60$21.90$5.50$10.00$13.48
0270Guardrail end treatment- parallel approach terminal (0536-85-24)EACH1$4,650.00$5,490.00$4,500.00$5,200.00$6,740.96
0275Performance turf, sod (0570-1-2)SY4,388$16.00$11.40$4.50$4.75$9.44
0280Conduit, furnish & install, open trench (0630-2-11)LF6$50.00$26.40$50.00$28.84$32.39
0285Conduit, furnish & install, directional bore (0630-2-12)LF207$50.00$29.90$50.00$32.63$36.65
0290Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH6$1,425.00$1,820.00$1,410.00$1,982.29$2,227.09
0295Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80)EACH1$13,900$11,200$13,550$12,282$13,799
0300Aluminum pole- index 695-001, furnish & install, 20' (0646-2120)EACH1$5,850.00$4,230.00$5,670.00$4,619.04$5,189.46
0305Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH12$3,100.00$2,790.00$3,035.00$3,050.84$3,427.59
0310Traffic monitoring site solar power unit, furnish & install (0695-5-1)EACH1$2,700.00$4,950.00$2,660.00$5,407.79$6,075.61
0315Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH12$2,500.00$2,510.00$2,470.00$2,740.93$3,079.41
0320Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162)EACH1$8,000.00$8,450.00$7,840.00$9,228.74$10,368
0325Traffic monitoring site cabinet, furnish & install, type 4, 2 plane back, polemount (0695-7173)EACH1$7,900.00$9,090.00$7,735.00$9,925.70$11,151
0330Traffic monitoring site communications modem furnish install (0695-8-11)EACH1$1,300.00$3,290.00$1,285.00$3,588.00$4,031.10
0335Raised pavement marker, type B (0706-1-3)EACH418$4.75$4.95$4.60$5.00$5.73
0340Painted pavement markings, standard, white, solid, 6" (0710-11101)GM13.94$2,200.00$1,100.00$2,170.00$1,300.00$2,696.39
0345Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF4,310$1.15$0.55$1.10$1.00$1.35
0350Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF889$2.25$1.10$2.20$1.50$2.70
0355Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM15.57$785.00$549.00$760.00$710.00$943.73
0360Painted pavement markings, standard, white, message or symbol (0710-11160)EACH15$60.00$38.45$54.25$57.50$67.41
0365Painted pavement markings, standard, white, arrows (0710-11170)EACH178$43.00$27.45$41.25$30.00$51.24
0370Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM7.89$5,600.00$1,100.00$5,425.00$1,300.00$6,740.96
0375Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM1.38$1,000.00$547.00$975.00$710.00$1,213.37
0380Initial contingency amount, DO not bid (0999-25)LS1$105,000$105,000$105,000$105,000$105,000
0385Ground-in rumble strips, 8" sinusoidal (0546-72-3)GM2.66$3,200.00$2,200.00$2,170.00$3,955.00$11,943
0390Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH100$480.00$588.50$575.00$600.00$714.54
0395Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH46$1,500.00$1,830.00$2,170.00$2,120.00$2,696.39
0400Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH20$1,800.00$2,370.00$2,385.00$2,500.00$2,966.02
0405Single column ground sign assembly, relocate (0700-1500)EACH3$1,100.00$379.00$1,085.00$1,100.00$1,348.19
0410Single column ground sign assembly, remove (0700-1600)EACH147$120.00$126.40$27.15$40.00$33.70
0415Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113)EACH8$5,000.00$8,350.00$7,050.00$7,500.00$8,763.25
0420Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114)EACH2$7,000.00$9,730.00$7,590.00$8,000.00$9,437.35
0425Multi-column ground sign assembly, remove (0700-2600)EACH12$1,200.00$2,020.00$2,170.00$2,300.00$2,696.39
0430Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH14$390.00$344.50$380.00$450.00$471.86
0435Sign panel, relocate, UP to 12 SF (0700-3501)EACH55$200.00$410.50$54.25$75.00$67.41
0440Sign panel, remove, UP to 12 SF (0700-3601)EACH14$55.00$252.80$27.25$95.00$33.70
0445Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH24$110.00$173.70$135.50$145.00$168.53
0450Tubular marker, 36" white post (0704-1-3)EACH38$195.00$247.30$425.00$250.00$303.34
0455Tubular marker, 36" yellow (0704-1-4)EACH41$200.00$247.30$245.00$250.00$303.34
0460Object marker, type 1 (0705-10-1)EACH12$200.00$185.90$325.00$350.00$404.45
0465Raised pavement marker, type B (0706-1-3)EACH3,527$4.75$4.95$4.60$5.00$5.73
0470Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF337$5.60$5.50$5.45$5.75$6.74
0475Painted pavement markings, surface (0710-90)LS1$89,150$133,000$86,330$115,000$107,323
0480Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF4,310$3.90$4.40$3.80$4.35$4.72
0485Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF605$5.05$6.60$4.90$6.45$6.07
0490Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF889$7.30$8.80$7.05$8.54$8.76
0495Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM1.38$1,650.00$2,740.00$1,626.00$2,700.00$2,022.28
0500Thermoplastic, standard, message or symbol (0711-11160)EACH15$165.00$137.40$162.75$165.00$202.23
0505Thermoplastic, standard, arrow (0711-11170)EACH178$106.00$109.90$103.00$109.50$128.08
0510Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF256$5.05$6.60$4.90$6.45$6.07
0515Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.74$1,670.00$2,730.00$1,625.00$2,700.00$2,022.28
0520Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF1,948$15.60$15.40$15.25$15.40$18.87
0525Thermoplastic, preformed, white, message (0711-14160)EACH47$223.00$219.80$217.00$215.00$269.64
0530Thermoplastic, preformed, white, arrow (0711-14170)EACH47$106.00$109.90$103.00$109.50$128.08
0535Thermoplastic, preformed, color, in pavement warning (0711-14760)EACH2$783.00$1,980.00$760.00$1,950.00$943.73
0540Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM13.94$5,597.00$5,270.00$5,425.00$5,120.00$6,740.96
0545Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.76$6,023.00$10,100$5,850.00$9,500.00$7,280.24
0550Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM15.57$1,477.00$1,650.00$1,430.00$1,650.00$1,779.61
0555Thermoplastic, standard other surfaces, white, 6", 6-10 dotted managed lane marking (0711-16171)GM0.78$1,664.00$1,630.00$1,625.00$1,650.00$2,022.28
0560Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM7.89$5,599.00$5,270.00$5,425.00$5,120.00$6,740.96
0565Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1)SF921$2.80$5.50$2.70$5.50$8.09
0570Itsfm subsurface documentation- project length (0611-1-1)MI4.21$2,000.00$4,420.00$1,875.00$4,830.00$5,426.47
0575Itsfm location documentation- intersection (0611-2-1)EACH2$2,000.00$2,020.00$1,875.00$2,208.00$2,480.68
0580Conduit, furnish & install, open trench (0630-2-11)LF349$31.50$22.60$31.00$24.70$27.74
0585Conduit, furnish & install, directional bore (0630-2-12)LF634$48.75$27.35$47.25$29.87$33.55
0590Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI2$13,500$13,800$13,140$14,975$16,911
0595Signal cable, remove- intersection (0632-7-6)PI2$1,770.00$3,540.00$1,715.00$3,864.00$4,341.17
0600Fiber optic cable, relocate, underground (0633-1420)LF31$11.75$5.35$11.40$5.87$6.59
0605Fiber optic connection, install, termination (0633-2-32)EACH24$110.00$61.00$107.50$66.59$74.81
0610Fiber optic connection hardware, F&I, buffer tube fan out kit (0633-3-14)EACH2$125.00$103.80$121.50$113.30$127.29
0615Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16)EACH2$1,675.00$2,210.00$1,625.00$2,415.00$2,713.24
0620Fiber optic cable locator (0633-6)DA270$265.00$227.50$256.00$220.00$279.08
0625Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH32$1,450.00$1,820.00$1,410.00$1,982.29$2,227.09
0630Electrical service wire, & install (0639-2-1)LF55$9.15$6.15$8.90$6.70$7.54
0635Aluminum signals pole, (0646-1-11)EACH8$2,800.00$3,850.00$2,785.00$4,120.00$4,726.61
0640Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH3$2,500.00$2,780.00$2,485.00$3,041.05$3,416.61
0645Aluminum signals pole, remove (0646-1-60)EACH3$350.00$758.00$345.00$828.00$930.25
0650Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH24$750.00$1,040.00$730.00$1,015.00$1,271.22
0655Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS8$1,050.00$1,440.00$1,020.00$1,573.68$1,768.02
0660Vehicle detection system - microwave, remove, complete system (0660-3-60)EACH1$1,400.00$2,530.00$1,370.00$2,760.00$3,100.84
0665Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH2$24,000$20,600$23,300$22,491$25,268
0670Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH8$10,600$9,750.00$10,330$10,648$11,963
0675Vehicle detection system- remove (0660-4-60)EACH1$1,750.00$2,530.00$1,715.00$2,760.00$3,100.84
0680Signal priority & preemption system, relocate (0663-1400)EACH2$1,590.00$3,100.00$1,540.00$3,381.00$3,798.53
0685Pedestrian detector, furnish & install, accessible (0665-1-12)EACH16$1,890.00$2,080.00$1,835.00$2,267.69$2,547.73
0690Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH8$58.75$63.20$57.00$69.00$77.52
0695Traffic controller, relocate- without cabinet (0671-2-50)EACH2$2,290.00$2,530.00$2,225.00$2,760.00$3,100.84
0700Traffic signal controller cabinet, furnish & install without controller, NEMA 44" W X 52" H X 24" D (0676-1116)EACH2$61,000$32,400$59,070$35,347$39,712
0705Traffic signal controller cabinet, remove (0676-1600)EACH2$1,180.00$2,460.00$1,145.00$2,691.00$3,023.32
0710Managed field ethernet switch, relocate (0684-1-4)EACH2$1,190.00$1,070.00$1,154.00$1,173.00$1,317.85
0715Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13)EACH2$11,050$11,600$10,720$12,100$14,255
0720Remote power management rpmu, furnish and install (0685-2-1)EACH2$2,250.00$1,050.00$2,190.00$1,147.19$1,288.87
FDOT contract T5852: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of June 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy