FDOT contract T6601 bid tabulation
SR 916 (NW 138 ST) FROM E OF NW 67 AVE TO NW 57 AVE. Let by Florida DOT on March 26, 2025, Miami-Dade, District 6. 7 bids received; low bid $2,559,250 by Weekley Asphalt Paving, Inc..
- Owner
- Florida DOT
- Letting
- 26 MAR 2025
- Pay items
- 117
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Weekley Asphalt Paving, Inc. | $2,559,250 | Low |
| 2 | General Asphalt Company, LLC | $2,669,406 | +4.0% |
| 3 | Florida Engineering & Development Corp | $2,769,573 | +8.0% |
| 4 | Aum Construction Inc. | $2,819,638 | +10% |
| 5 | Roadway Construction, LLC | $2,840,583 | +11% |
| 6 | Ohla USA Inc | $2,995,661 | +17% |
| 7 | The Stout Group LLC | $3,233,626 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Weekley Asphalt Paving, Inc. | 2. General Asphalt Company, LLC | 3. Florida Engineering & Development Corp | 4. Aum Construction Inc. | 5. Roadway Construction, LLC | 6. Ohla USA Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $60,000 | $200,000 | $273,669 | $200,000 | $284,058 | $290,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $339,000 | $250,000 | $197,948 | $150,000 | $538,251 | $355,000 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $21,240 | $5,000.00 | $34,860 | $5,000.00 | $100.00 | $18,786 |
| 0020 | Traffic control officer (0102-14) | HR | 150 | $95.00 | $88.00 | $83.48 | $80.00 | $65.00 | $76.00 |
| 0025 | Work zone sign (0102-60) | ED | 12,000 | $0.24 | $0.26 | $0.25 | $0.50 | $0.24 | $0.33 |
| 0030 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 432 | $59.90 | $50.60 | $47.38 | $70.00 | $0.01 | $79.68 |
| 0035 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 8,700 | $0.14 | $0.15 | $0.14 | $0.20 | $0.14 | $0.19 |
| 0040 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 279,400 | $0.04 | $0.04 | $0.04 | $0.10 | $0.04 | $0.06 |
| 0045 | Temporary separator, F&I remove (0102-75-1) | LF | 1,425 | $19.00 | $20.90 | $19.57 | $23.00 | $0.01 | $26.29 |
| 0050 | Arrow board / advance warning arrow panel (0102-76) | ED | 480 | $5.15 | $5.67 | $5.30 | $7.00 | $5.15 | $7.13 |
| 0055 | Portable changeable message sign, temporary (0102-99) | ED | 570 | $10.40 | $11.44 | $10.71 | $15.00 | $10.40 | $14.39 |
| 0060 | Temporary signalization and maintenance, intersection (0102-104) | ED | 720 | $7.00 | $9.79 | $9.17 | $10.00 | $8.90 | $14.83 |
| 0065 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 720 | $7.00 | $9.79 | $9.17 | $10.00 | $8.90 | $14.83 |
| 0070 | Type III barricade (0102-115) | ED | 960 | $0.45 | $0.50 | $0.46 | $3.00 | $0.45 | $0.62 |
| 0075 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.11 | $26,400 | $12,650 | $27,192 | $20,000 | $11,500 | $12,000 |
| 0080 | Removable tape, white, symbol or arrow (0102-913-29) | EACH | 1 | $697.00 | $330.00 | $717.91 | $750.00 | $300.00 | $315.00 |
| 0085 | Sediment barrier (0104-10-3) | LF | 1,670 | $2.60 | $4.40 | $2.73 | $3.50 | $2.15 | $7.75 |
| 0090 | Inlet protection system (0104-18) | EACH | 54 | $160.00 | $220.00 | $99.34 | $250.00 | $115.60 | $175.00 |
| 0095 | Litter removal (0107-1) | ACRE | 38.36 | $50.00 | $0.01 | $115.16 | $100.00 | $0.01 | $65.00 |
| 0100 | Mowing (0107-2) | ACRE | 29.13 | $50.00 | $0.01 | $120.90 | $100.00 | $0.01 | $82.00 |
| 0105 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $21,450 | $1.10 | $10,712 | $15,000 | $1,200.00 | $16,500 |
| 0110 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $15,000 | $1.10 | $7,210.00 | $10,000 | $7,000.00 | $13,750 |
| 0115 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $109,300 | $30,250 | $72,297 | $20,000 | $12,512 | $290,000 |
| 0120 | Removal of existing concrete (0110-4-10) | SY | 1,158 | $40.00 | $60.83 | $50.31 | $40.00 | $35.85 | $35.00 |
| 0125 | Tree protection barrier (0110-21) | LF | 532 | $14.00 | $5.50 | $6.52 | $10.00 | $4.42 | $9.00 |
| 0130 | Tree root and branch pruning (0110-22) | EACH | 1 | $500.00 | $2,750.00 | $10,300 | $5,000.00 | $1,500.00 | $1,750.00 |
| 0135 | Borrow excavation, truck measure (0120-2-2) | CY | 0.90 | $900.00 | $1,100.00 | $308.66 | $2,000.00 | $702.12 | $4,387.69 |
| 0140 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $5,000.00 | $2,420.00 | $90.93 | $3,500.00 | $861.28 | $3,955.60 |
| 0145 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 35,868 | $3.00 | $3.86 | $3.87 | $5.00 | $4.50 | $4.04 |
| 0150 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 2,959.10 | $195.00 | $224.66 | $226.66 | $260.00 | $210.00 | $160.00 |
| 0155 | Miscellaneous asphalt (0339-1) | TN | 1.50 | $800.00 | $1,600.00 | $689.69 | $2,000.00 | $1,035.36 | $3,582.32 |
| 0160 | Manhole, adjust (0425-5) | EACH | 24 | $750.00 | $880.00 | $981.80 | $1,500.00 | $550.00 | $850.00 |
| 0165 | Pipe handrail - guiderail, steel (0515-1-1) | LF | 35 | $278.00 | $275.00 | $264.71 | $380.00 | $250.00 | $251.00 |
| 0170 | Pipe handrail - guiderail, relocate, steel (0515-1-41) | LF | 31 | $100.00 | $99.00 | $55.62 | $150.00 | $90.00 | $91.00 |
| 0175 | Concrete curb & gutter, type E (0520-1-7) | LF | 73 | $64.57 | $52.58 | $68.22 | $45.00 | $52.71 | $46.00 |
| 0180 | Concrete curb & gutter, type F (0520-1-10) | LF | 768 | $64.57 | $33.99 | $52.13 | $45.00 | $46.57 | $75.00 |
| 0185 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 460 | $69.77 | $62.08 | $71.05 | $100.00 | $73.16 | $81.00 |
| 0190 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 593 | $90.91 | $83.25 | $92.18 | $110.00 | $101.98 | $100.00 |
| 0195 | Detectable warnings (0527-2) | SF | 346 | $49.00 | $46.34 | $43.31 | $40.00 | $30.72 | $36.00 |
| 0200 | Guardrail -roadway, general (0536-1-1) | LF | 103 | $29.00 | $28.60 | $25.75 | $55.00 | $26.00 | $27.00 |
| 0205 | Pipe rail for guardrail (0536-6) | LF | 50 | $26.00 | $25.30 | $29.61 | $45.00 | $23.00 | $24.00 |
| 0210 | Special guardrail post- post for shallow mount (0536-7-3) | EACH | 3 | $220.00 | $216.70 | $412.00 | $250.00 | $197.00 | $197.00 |
| 0215 | Special guardrail post- frangible leave-out for mounting through concrete surface (0536-7-4) | EACH | 5 | $173.00 | $170.50 | $566.50 | $350.00 | $155.00 | $155.00 |
| 0220 | Guardrail removal (0536-73) | LF | 59 | $10.00 | $7.70 | $7.21 | $5.00 | $7.00 | $7.50 |
| 0225 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 1 | $3,900.00 | $3,795.00 | $4,326.00 | $6,000.00 | $3,450.00 | $3,450.00 |
| 0230 | Performance turf, sod (0570-1-2) | SY | 41 | $28.00 | $6.05 | $10.26 | $30.00 | $95.54 | $16.60 |
| 0235 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 33 | $50.00 | $41.69 | $39.04 | $38.00 | $37.90 | $41.00 |
| 0240 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 2 | $1,600.00 | $1,360.81 | $1,274.22 | $1,500.00 | $1,237.10 | $1,481.00 |
| 0245 | Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0250 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 4 | $3,700.00 | $2,170.41 | $2,032.29 | $2,000.00 | $1,973.10 | $2,657.00 |
| 0255 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 4 | $3,500.00 | $2,316.49 | $2,169.08 | $1,800.00 | $2,105.90 | $2,455.00 |
| 0260 | Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132) | EACH | 1 | $5,200.00 | $7,969.06 | $7,461.94 | $8,000.00 | $7,244.60 | $7,700.00 |
| 0265 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0270 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 10 | $495.00 | $533.50 | $509.85 | $750.00 | $495.00 | $511.00 |
| 0275 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 6 | $2,350.00 | $1,485.00 | $2,420.50 | $1,700.00 | $2,350.00 | $1,602.00 |
| 0280 | Single column ground sign assembly, F&I ground mount, SF sheeting area for back to back signs (0700-1114) | EACH | 1 | $2,550.00 | $1,925.00 | $2,626.50 | $5,000.00 | $2,550.00 | $3,205.00 |
| 0285 | Single column ground sign assembly, install (0700-1400) | EACH | 1 | $995.00 | $330.00 | $1,024.85 | $1,300.00 | $995.00 | $457.00 |
| 0290 | Single column ground sign assembly, remove (0700-1600) | EACH | 22 | $10.00 | $49.50 | $10.30 | $100.00 | $10.00 | $30.00 |
| 0295 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 1 | $375.00 | $385.00 | $386.25 | $500.00 | $375.00 | $150.00 |
| 0300 | Object marker, type 1 (0705-10-1) | EACH | 9 | $270.00 | $280.50 | $278.10 | $350.00 | $270.00 | $103.00 |
| 0305 | Delineator, flexible tubular (0705-11-1) | EACH | 1 | $90.00 | $110.00 | $92.70 | $300.00 | $90.00 | $110.00 |
| 0310 | Raised pavement marker, type B (0706-1-3) | EACH | 1,077 | $5.00 | $4.40 | $5.15 | $7.00 | $4.00 | $4.20 |
| 0315 | Painted pavement markings, standard, yellow, island nose (0710-11290) | SF | 36 | $2.00 | $4.40 | $2.06 | $20.00 | $4.00 | $4.20 |
| 0320 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 51 | $2.00 | $4.95 | $2.06 | $20.00 | $4.50 | $4.70 |
| 0325 | Painted pavement markings, surface (0710-90) | LS | 1 | $26,295 | $17,752 | $27,084 | $25,000 | $16,138 | $16,750 |
| 0330 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 1,395 | $2.40 | $3.62 | $2.47 | $5.00 | $3.29 | $3.50 |
| 0335 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 108 | $3.60 | $5.43 | $3.71 | $5.00 | $4.94 | $5.20 |
| 0340 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 474 | $4.80 | $7.24 | $4.94 | $6.00 | $6.58 | $6.90 |
| 0345 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.19 | $2,300.00 | $3,025.00 | $2,368.98 | $8,000.00 | $2,661.29 | $2,775.00 |
| 0350 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 8 | $120.00 | $84.70 | $123.60 | $200.00 | $77.00 | $80.00 |
| 0355 | Thermoplastic, standard, arrow (0711-11170) | EACH | 64 | $80.00 | $61.60 | $82.40 | $100.00 | $56.00 | $59.00 |
| 0360 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 293 | $3.60 | $5.05 | $3.71 | $5.00 | $4.59 | $4.80 |
| 0365 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.03 | $6,336.00 | $3,025.00 | $6,526.13 | $15,000 | $2,661.29 | $2,775.00 |
| 0370 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 780 | $19.00 | $18.45 | $19.57 | $23.00 | $16.77 | $17.50 |
| 0375 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 2.97 | $6,336.00 | $5,500.00 | $6,526.08 | $6,500.00 | $4,993.28 | $5,200.00 |
| 0380 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.13 | $6,600.00 | $7,330.40 | $6,798.02 | $10,000 | $6,346.67 | $6,600.00 |
| 0385 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 1.65 | $2,300.00 | $1,375.00 | $2,369.00 | $6,500.00 | $1,248.49 | $1,300.00 |
| 0390 | Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133) | GM | 0.06 | $3,168.00 | $2,750.00 | $3,263.09 | $15,000 | $2,272.73 | $2,360.00 |
| 0395 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 2.17 | $6,336.00 | $5,153.50 | $6,526.08 | $6,500.00 | $4,665.56 | $4,850.00 |
| 0400 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 51 | $45.00 | $38.39 | $35.95 | $38.00 | $34.90 | $37.00 |
| 0405 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 12 | $1,600.00 | $1,438.03 | $1,346.52 | $1,500.00 | $1,307.30 | $1,485.00 |
| 0410 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $6,500.00 | $5,596.91 | $5,240.74 | $5,000.00 | $5,088.10 | $6,100.00 |
| 0415 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $3,200.00 | $3,154.25 | $2,953.53 | $2,000.00 | $2,867.50 | $3,075.00 |
| 0420 | Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13) | LF | 273 | $5.00 | $14.52 | $13.60 | $10.00 | $13.20 | $4.60 |
| 0425 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 1 | $15,000 | $14,743 | $13,804 | $15,000 | $13,402 | $14,950 |
| 0430 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 10 | $1,500.00 | $1,349.59 | $1,263.71 | $1,500.00 | $1,226.90 | $1,640.00 |
| 0435 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 15' arm length (0715-61352) | EACH | 1 | $12,000 | $8,348.56 | $7,817.19 | $15,000 | $7,589.60 | $8,000.00 |
| 0440 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 1 | $1,000.00 | $763.84 | $715.23 | $750.00 | $694.40 | $1,221.00 |
| 0445 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 2,878 | $35.00 | $54.34 | $50.88 | $38.00 | $49.40 | $41.00 |
| 0450 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 3 | $12,500 | $9,839.28 | $9,213.14 | $12,000 | $8,944.80 | $9,930.00 |
| 0455 | Signal cable, remove- intersection (0632-7-6) | PI | 3 | $500.00 | $781.55 | $731.82 | $750.00 | $710.50 | $1,764.00 |
| 0460 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 64 | $1,500.00 | $1,360.81 | $1,274.21 | $1,500.00 | $1,237.10 | $1,481.00 |
| 0465 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 3 | $3,200.00 | $2,065.69 | $1,934.24 | $3,500.00 | $1,877.90 | $2,931.00 |
| 0470 | Pull & splice box, install (0635-2-30) | EACH | 4 | $1,500.00 | $890.45 | $833.79 | $1,000.00 | $809.50 | $930.00 |
| 0475 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 4 | $6,800.00 | $6,334.57 | $5,931.46 | $7,500.00 | $5,758.70 | $5,660.00 |
| 0480 | Electrical power service, remove underground (0639-1620) | AS | 3 | $300.00 | $586.19 | $548.89 | $950.00 | $532.90 | $1,150.00 |
| 0485 | Electrical service wire, & install (0639-2-1) | LF | 1,575 | $12.00 | $11.66 | $10.92 | $10.00 | $10.60 | $10.25 |
| 0490 | Electrical service wire, (0639-2-6) | LF | 1,473 | $1.00 | $0.55 | $0.52 | $1.00 | $0.50 | $0.60 |
| 0495 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 4 | $3,500.00 | $3,245.55 | $3,039.02 | $2,000.00 | $2,950.50 | $3,330.00 |
| 0500 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 4 | $2,900.00 | $2,862.64 | $2,680.47 | $2,500.00 | $2,602.40 | $3,075.00 |
| 0505 | Aluminum signals pole, (0646-1-11) | EACH | 9 | $1,800.00 | $2,207.37 | $2,066.90 | $2,000.00 | $2,006.70 | $3,000.00 |
| 0510 | Aluminum signals pole, remove (0646-1-60) | EACH | 6 | $250.00 | $586.19 | $548.89 | $500.00 | $532.90 | $275.00 |
| 0515 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 8 | $1,100.00 | $746.79 | $699.27 | $1,500.00 | $678.90 | $1,150.00 |
| 0520 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 1 | $1,300.00 | $1,603.58 | $1,501.53 | $2,200.00 | $1,457.80 | $1,880.00 |
| 0525 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 1 | $250.00 | $97.68 | $91.46 | $500.00 | $88.80 | $203.00 |
| 0530 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 13 | $5,500.00 | $5,296.83 | $4,959.76 | $5,000.00 | $4,815.30 | $5,200.00 |
| 0535 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 13 | $2,200.00 | $2,709.85 | $2,537.41 | $3,600.00 | $2,463.50 | $4,061.00 |
| 0540 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 10 | $650.00 | $333.30 | $312.09 | $450.00 | $303.00 | $550.00 |
| 0545 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 1 | $350.00 | $97.68 | $91.46 | $50.00 | $88.80 | $67.50 |
| 0550 | Traffic controller assembly, furnish & install model 2070 (0670-5140) | AS | 3 | $38,000 | $55,952 | $52,392 | $48,000 | $50,866 | $44,621 |
| 0555 | Traffic controller assembly, remove controller with (0670-5600) | AS | 3 | $500.00 | $781.55 | $731.82 | $1,500.00 | $710.50 | $1,550.00 |
| 0560 | Network device, cellular (0684-90102) | EACH | 3 | $3,200.00 | $1,907.29 | $1,785.92 | $2,000.00 | $1,733.90 | $3,325.00 |
| 0565 | Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13) | EACH | 1 | $11,907 | $21,357 | $19,998 | $17,500 | $19,415 | $17,000 |
| 0570 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 3 | $700.00 | $1,007.71 | $943.58 | $1,250.00 | $916.10 | $921.00 |
| 0575 | Internally illuminated sign, furnish & install overhead mount, UP to 12 SF (0700-5-21) | EACH | 6 | $3,500.00 | $6,365.15 | $5,960.10 | $3,500.00 | $5,786.50 | $3,370.00 |
| 0580 | Internally illuminated sign, remove (0700-5-60) | EACH | 6 | $500.00 | $195.47 | $183.03 | $500.00 | $177.70 | $940.00 |
| 0585 | Enhanced highway sign AC powered, F&I ground mount, W/beacon, UP to 12 SF of static sign panels (0700-141111) | EACH | 1 | $12,000 | $14,895 | $13,948 | $18,000 | $13,541 | $7,800.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of March 26, 2025. Compiled by Mirage Metrics.