FDOT contract T6601 bid tabulation

SR 916 (NW 138 ST) FROM E OF NW 67 AVE TO NW 57 AVE. Let by Florida DOT on March 26, 2025, Miami-Dade, District 6. 7 bids received; low bid $2,559,250 by Weekley Asphalt Paving, Inc..

Owner
Florida DOT
Letting
26 MAR 2025
Pay items
117
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Weekley Asphalt Paving, Inc.$2,559,250Low
2General Asphalt Company, LLC$2,669,406+4.0%
3Florida Engineering & Development Corp$2,769,573+8.0%
4Aum Construction Inc.$2,819,638+10%
5Roadway Construction, LLC$2,840,583+11%
6Ohla USA Inc$2,995,661+17%
7The Stout Group LLC$3,233,626+26%
FDOT contract T6601: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Weekley Asphalt Paving, Inc.2. General Asphalt Company, LLC3. Florida Engineering & Development Corp4. Aum Construction Inc.5. Roadway Construction, LLC6. Ohla USA Inc
0005Mobilization (0101-1)LS1$60,000$200,000$273,669$200,000$284,058$290,000
0010Maintenance of traffic (0102-1)DA1$339,000$250,000$197,948$150,000$538,251$355,000
0015Pedestrian or bicycle special detour (0102-4-1)SY1$21,240$5,000.00$34,860$5,000.00$100.00$18,786
0020Traffic control officer (0102-14)HR150$95.00$88.00$83.48$80.00$65.00$76.00
0025Work zone sign (0102-60)ED12,000$0.24$0.26$0.25$0.50$0.24$0.33
0030Temporary barrier, F&I, low profile, concrete (0102-71-13)LF432$59.90$50.60$47.38$70.00$0.01$79.68
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED8,700$0.14$0.15$0.14$0.20$0.14$0.19
0040Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD279,400$0.04$0.04$0.04$0.10$0.04$0.06
0045Temporary separator, F&I remove (0102-75-1)LF1,425$19.00$20.90$19.57$23.00$0.01$26.29
0050Arrow board / advance warning arrow panel (0102-76)ED480$5.15$5.67$5.30$7.00$5.15$7.13
0055Portable changeable message sign, temporary (0102-99)ED570$10.40$11.44$10.71$15.00$10.40$14.39
0060Temporary signalization and maintenance, intersection (0102-104)ED720$7.00$9.79$9.17$10.00$8.90$14.83
0065Temporary traffic detection and maintenance, intersection (0102-107-1)ED720$7.00$9.79$9.17$10.00$8.90$14.83
0070Type III barricade (0102-115)ED960$0.45$0.50$0.46$3.00$0.45$0.62
0075Removable tape, white, solid 6" (0102-913-21)GM0.11$26,400$12,650$27,192$20,000$11,500$12,000
0080Removable tape, white, symbol or arrow (0102-913-29)EACH1$697.00$330.00$717.91$750.00$300.00$315.00
0085Sediment barrier (0104-10-3)LF1,670$2.60$4.40$2.73$3.50$2.15$7.75
0090Inlet protection system (0104-18)EACH54$160.00$220.00$99.34$250.00$115.60$175.00
0095Litter removal (0107-1)ACRE38.36$50.00$0.01$115.16$100.00$0.01$65.00
0100Mowing (0107-2)ACRE29.13$50.00$0.01$120.90$100.00$0.01$82.00
0105Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$21,450$1.10$10,712$15,000$1,200.00$16,500
0110Monitor existing structures- vibration monitoring (0108-2)LS1$15,000$1.10$7,210.00$10,000$7,000.00$13,750
0115Clearing & grubbing (0110-1-1)ACRE1$109,300$30,250$72,297$20,000$12,512$290,000
0120Removal of existing concrete (0110-4-10)SY1,158$40.00$60.83$50.31$40.00$35.85$35.00
0125Tree protection barrier (0110-21)LF532$14.00$5.50$6.52$10.00$4.42$9.00
0130Tree root and branch pruning (0110-22)EACH1$500.00$2,750.00$10,300$5,000.00$1,500.00$1,750.00
0135Borrow excavation, truck measure (0120-2-2)CY0.90$900.00$1,100.00$308.66$2,000.00$702.12$4,387.69
0140Regular excavation (3-R projects only) (0120-71)LS1$5,000.00$2,420.00$90.93$3,500.00$861.28$3,955.60
0145Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY35,868$3.00$3.86$3.87$5.00$4.50$4.04
0150Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN2,959.10$195.00$224.66$226.66$260.00$210.00$160.00
0155Miscellaneous asphalt (0339-1)TN1.50$800.00$1,600.00$689.69$2,000.00$1,035.36$3,582.32
0160Manhole, adjust (0425-5)EACH24$750.00$880.00$981.80$1,500.00$550.00$850.00
0165Pipe handrail - guiderail, steel (0515-1-1)LF35$278.00$275.00$264.71$380.00$250.00$251.00
0170Pipe handrail - guiderail, relocate, steel (0515-1-41)LF31$100.00$99.00$55.62$150.00$90.00$91.00
0175Concrete curb & gutter, type E (0520-1-7)LF73$64.57$52.58$68.22$45.00$52.71$46.00
0180Concrete curb & gutter, type F (0520-1-10)LF768$64.57$33.99$52.13$45.00$46.57$75.00
0185Concrete sidewalk and driveways, 4" thick (0522-1)SY460$69.77$62.08$71.05$100.00$73.16$81.00
0190Concrete sidewalk and driveways, 6" thick (0522-2)SY593$90.91$83.25$92.18$110.00$101.98$100.00
0195Detectable warnings (0527-2)SF346$49.00$46.34$43.31$40.00$30.72$36.00
0200Guardrail -roadway, general (0536-1-1)LF103$29.00$28.60$25.75$55.00$26.00$27.00
0205Pipe rail for guardrail (0536-6)LF50$26.00$25.30$29.61$45.00$23.00$24.00
0210Special guardrail post- post for shallow mount (0536-7-3)EACH3$220.00$216.70$412.00$250.00$197.00$197.00
0215Special guardrail post- frangible leave-out for mounting through concrete surface (0536-7-4)EACH5$173.00$170.50$566.50$350.00$155.00$155.00
0220Guardrail removal (0536-73)LF59$10.00$7.70$7.21$5.00$7.00$7.50
0225Guardrail end treatment- parallel approach terminal (0536-85-24)EACH1$3,900.00$3,795.00$4,326.00$6,000.00$3,450.00$3,450.00
0230Performance turf, sod (0570-1-2)SY41$28.00$6.05$10.26$30.00$95.54$16.60
0235Conduit, furnish & install, directional bore (0630-2-12)LF33$50.00$41.69$39.04$38.00$37.90$41.00
0240Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH2$1,600.00$1,360.81$1,274.22$1,500.00$1,237.10$1,481.00
0245Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130)LS1$3,000.00$3,000.00$3,000.00$3,000.00$3,000.00$3,000.00
0250Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH4$3,700.00$2,170.41$2,032.29$2,000.00$1,973.10$2,657.00
0255Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH4$3,500.00$2,316.49$2,169.08$1,800.00$2,105.90$2,455.00
0260Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132)EACH1$5,200.00$7,969.06$7,461.94$8,000.00$7,244.60$7,700.00
0265Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000$50,000$50,000$50,000
0270Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH10$495.00$533.50$509.85$750.00$495.00$511.00
0275Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH6$2,350.00$1,485.00$2,420.50$1,700.00$2,350.00$1,602.00
0280Single column ground sign assembly, F&I ground mount, SF sheeting area for back to back signs (0700-1114)EACH1$2,550.00$1,925.00$2,626.50$5,000.00$2,550.00$3,205.00
0285Single column ground sign assembly, install (0700-1400)EACH1$995.00$330.00$1,024.85$1,300.00$995.00$457.00
0290Single column ground sign assembly, remove (0700-1600)EACH22$10.00$49.50$10.30$100.00$10.00$30.00
0295Sign panel, relocate, UP to 12 SF (0700-3501)EACH1$375.00$385.00$386.25$500.00$375.00$150.00
0300Object marker, type 1 (0705-10-1)EACH9$270.00$280.50$278.10$350.00$270.00$103.00
0305Delineator, flexible tubular (0705-11-1)EACH1$90.00$110.00$92.70$300.00$90.00$110.00
0310Raised pavement marker, type B (0706-1-3)EACH1,077$5.00$4.40$5.15$7.00$4.00$4.20
0315Painted pavement markings, standard, yellow, island nose (0710-11290)SF36$2.00$4.40$2.06$20.00$4.00$4.20
0320Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF51$2.00$4.95$2.06$20.00$4.50$4.70
0325Painted pavement markings, surface (0710-90)LS1$26,295$17,752$27,084$25,000$16,138$16,750
0330Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF1,395$2.40$3.62$2.47$5.00$3.29$3.50
0335Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF108$3.60$5.43$3.71$5.00$4.94$5.20
0340Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF474$4.80$7.24$4.94$6.00$6.58$6.90
0345Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.19$2,300.00$3,025.00$2,368.98$8,000.00$2,661.29$2,775.00
0350Thermoplastic, standard, message or symbol (0711-11160)EACH8$120.00$84.70$123.60$200.00$77.00$80.00
0355Thermoplastic, standard, arrow (0711-11170)EACH64$80.00$61.60$82.40$100.00$56.00$59.00
0360Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF293$3.60$5.05$3.71$5.00$4.59$4.80
0365Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.03$6,336.00$3,025.00$6,526.13$15,000$2,661.29$2,775.00
0370Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF780$19.00$18.45$19.57$23.00$16.77$17.50
0375Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM2.97$6,336.00$5,500.00$6,526.08$6,500.00$4,993.28$5,200.00
0380Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.13$6,600.00$7,330.40$6,798.02$10,000$6,346.67$6,600.00
0385Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM1.65$2,300.00$1,375.00$2,369.00$6,500.00$1,248.49$1,300.00
0390Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133)GM0.06$3,168.00$2,750.00$3,263.09$15,000$2,272.73$2,360.00
0395Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM2.17$6,336.00$5,153.50$6,526.08$6,500.00$4,665.56$4,850.00
0400Conduit, furnish & install, directional bore (0630-2-12)LF51$45.00$38.39$35.95$38.00$34.90$37.00
0405Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH12$1,600.00$1,438.03$1,346.52$1,500.00$1,307.30$1,485.00
0410Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$6,500.00$5,596.91$5,240.74$5,000.00$5,088.10$6,100.00
0415Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$3,200.00$3,154.25$2,953.53$2,000.00$2,867.50$3,075.00
0420Lighting conductors, F&I, insulated, no 4 to no 2 (0715-1-13)LF273$5.00$14.52$13.60$10.00$13.20$4.60
0425Load center, F&I, secondary voltage (0715-7-11)EACH1$15,000$14,743$13,804$15,000$13,402$14,950
0430Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH10$1,500.00$1,349.59$1,263.71$1,500.00$1,226.90$1,640.00
0435Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 15' arm length (0715-61352)EACH1$12,000$8,348.56$7,817.19$15,000$7,589.60$8,000.00
0440Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH1$1,000.00$763.84$715.23$750.00$694.40$1,221.00
0445Conduit, furnish & install, directional bore (0630-2-12)LF2,878$35.00$54.34$50.88$38.00$49.40$41.00
0450Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI3$12,500$9,839.28$9,213.14$12,000$8,944.80$9,930.00
0455Signal cable, remove- intersection (0632-7-6)PI3$500.00$781.55$731.82$750.00$710.50$1,764.00
0460Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH64$1,500.00$1,360.81$1,274.21$1,500.00$1,237.10$1,481.00
0465Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH3$3,200.00$2,065.69$1,934.24$3,500.00$1,877.90$2,931.00
0470Pull & splice box, install (0635-2-30)EACH4$1,500.00$890.45$833.79$1,000.00$809.50$930.00
0475Electrical power service, F&I, underground, meter by contractor (0639-1122)AS4$6,800.00$6,334.57$5,931.46$7,500.00$5,758.70$5,660.00
0480Electrical power service, remove underground (0639-1620)AS3$300.00$586.19$548.89$950.00$532.90$1,150.00
0485Electrical service wire, & install (0639-2-1)LF1,575$12.00$11.66$10.92$10.00$10.60$10.25
0490Electrical service wire, (0639-2-6)LF1,473$1.00$0.55$0.52$1.00$0.50$0.60
0495Electrical service disconnect, F&I, pole mount (0639-3-11)EACH4$3,500.00$3,245.55$3,039.02$2,000.00$2,950.50$3,330.00
0500Prestressed concrete pole, type P-II service pole (0641-2-12)EACH4$2,900.00$2,862.64$2,680.47$2,500.00$2,602.40$3,075.00
0505Aluminum signals pole, (0646-1-11)EACH9$1,800.00$2,207.37$2,066.90$2,000.00$2,006.70$3,000.00
0510Aluminum signals pole, remove (0646-1-60)EACH6$250.00$586.19$548.89$500.00$532.90$275.00
0515Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS8$1,100.00$746.79$699.27$1,500.00$678.90$1,150.00
0520Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS1$1,300.00$1,603.58$1,501.53$2,200.00$1,457.80$1,880.00
0525Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS1$250.00$97.68$91.46$500.00$88.80$203.00
0530Vehicle detection system- furnish & install cabinet equipment (0660-4-11)EACH13$5,500.00$5,296.83$4,959.76$5,000.00$4,815.30$5,200.00
0535Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH13$2,200.00$2,709.85$2,537.41$3,600.00$2,463.50$4,061.00
0540Pedestrian detector, furnish & install, standard (0665-1-11)EACH10$650.00$333.30$312.09$450.00$303.00$550.00
0545Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH1$350.00$97.68$91.46$50.00$88.80$67.50
0550Traffic controller assembly, furnish & install model 2070 (0670-5140)AS3$38,000$55,952$52,392$48,000$50,866$44,621
0555Traffic controller assembly, remove controller with (0670-5600)AS3$500.00$781.55$731.82$1,500.00$710.50$1,550.00
0560Network device, cellular (0684-90102)EACH3$3,200.00$1,907.29$1,785.92$2,000.00$1,733.90$3,325.00
0565Uninterruptible power supply, furnish and install, line interactive with cabinet (0685-1-13)EACH1$11,907$21,357$19,998$17,500$19,415$17,000
0570Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH3$700.00$1,007.71$943.58$1,250.00$916.10$921.00
0575Internally illuminated sign, furnish & install overhead mount, UP to 12 SF (0700-5-21)EACH6$3,500.00$6,365.15$5,960.10$3,500.00$5,786.50$3,370.00
0580Internally illuminated sign, remove (0700-5-60)EACH6$500.00$195.47$183.03$500.00$177.70$940.00
0585Enhanced highway sign AC powered, F&I ground mount, W/beacon, UP to 12 SF of static sign panels (0700-141111)EACH1$12,000$14,895$13,948$18,000$13,541$7,800.00
FDOT contract T6601: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of March 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy