FDOT contract T7560 bid tabulation

SR 39 (PAUL S BUCHMAN HWY) FROM N OF CENTRAL AVE TO US 301.. Let by Florida DOT on April 30, 2025, Pasco, District 7. 7 bids received; low bid $5,146,581 by Pigott Asphalt and Sitework LLC.

Owner
Florida DOT
Letting
30 APR 2025
Pay items
124
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Pigott Asphalt and Sitework LLC$5,146,581Low
2Superior Asphalt, Inc.$5,922,001+15%
3C.W. Roberts Contracting, Inc.$5,978,651+16%
4Watson Civil Construction, Inc.$6,012,380+17%
5Hubbard Construction Company$6,061,537+18%
6Preferred Materials Inc.$6,271,802+22%
7Ajax Paving Industries of Florida LLC$9,457,706+84%
FDOT contract T7560: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Pigott Asphalt and Sitework LLC2. Superior Asphalt, Inc.3. C.W. Roberts Contracting, Inc.4. Watson Civil Construction, Inc.5. Hubbard Construction Company6. Preferred Materials Inc.
0005Mobilization (0101-1)LS1$480,000$714,451$577,380$600,000$484,881$621,400
0010Maintenance of traffic (0102-1)DA1$346,000$345,000$446,922$699,000$384,806$329,500
0015Special detour- temporary pavement (0102-2200)SY1$75,000$100,420$84,906$103,000$149,679$35,000
0020Special detour- temporary earthwork/base (0102-2300)CY1$50,000$24,240$39,472$40,000$16,386$25,000
0025Commercial material for temporary driveway maintenance (0102-3)CY205.10$100.00$76.50$157.09$88.00$87.78$259.04
0030Traffic control officer (0102-14)HR356$100.00$125.00$94.97$96.00$109.24$88.00
0035Work zone sign (0102-60)ED15,940$0.30$0.30$0.27$0.33$0.25$0.23
0040Temporary barrier, F&I, anchored (0102-71-15)LF1,638$42.00$39.00$41.58$37.00$49.90$20.00
0045Temporary barrier, relocate, anchored (0102-71-25)LF1,350$20.00$15.00$16.05$14.20$18.68$8.00
0050Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED27,167$0.10$0.15$0.12$0.15$0.11$0.10
0055Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD1,265$1.00$0.10$0.08$0.10$0.09$0.09
0060Arrow board / advance warning arrow panel (0102-76)ED529$10.00$5.20$5.77$7.00$5.85$5.50
0065Temporary crash cushion, redirective option (0102-89-1)LO7$1,500.00$1,177.20$4,572.49$1,120.00$1,050.68$1,154.96
0070Portable changeable message sign, temporary (0102-99)ED1,238$12.00$11.90$11.54$14.00$11.70$11.00
0075Temporary signalization and maintenance, intersection (0102-104)ED520$25.00$20.00$22.01$30.00$29.64$4.17
0080Temporary traffic detection and maintenance, intersection (0102-107-1)ED520$25.00$1.10$1.19$10.00$21.34$4.17
0082Existing ITS maintenance (0102-112)DA260$110.00$350.00$383.16$420.00$237.10$357.49
0085Type III barricade (0102-115)ED1,142$0.50$0.30$0.29$0.35$0.41$0.38
0090Temporary raised rumble per day, includes all sets and relocations (0102-909)DA260$40.00$28.65$57.71$70.00$37.45$35.20
0095Sediment barrier (0104-10-3)LF5,307$2.50$1.35$1.11$2.00$1.03$2.58
0100Soil tracking prevention device (0104-15)EACH2$3,500.00$8,865.00$3,880.97$4,600.00$3,449.74$9,029.69
0105Inlet protection system (0104-18)EACH14$250.00$135.00$140.05$125.00$201.24$137.50
0110Litter removal (0107-1)ACRE277.46$10.00$47.25$53.97$51.00$51.09$48.13
0115Mowing (0107-2)ACRE246.77$50.00$79.50$90.78$85.00$85.92$80.96
0120Clearing & grubbing (0110-1-1)ACRE1$86,500$127,500$126,407$300,000$100,654$265,457
0125Removal of existing concrete (0110-4-10)SY140$65.00$45.45$75.10$33.00$52.67$68.84
0130Mailbox, F&I single (0110-7-1)EACH9$300.00$135.00$250.27$410.00$329.64$424.30
0135Regular excavation (0120-1)CY834.60$25.00$55.55$46.10$21.00$46.82$68.38
0140Subsoil excavation (0120-4)CY1,951.50$12.00$56.10$68.44$20.00$46.82$91.18
0145Embankment (0120-6)CY2,461.90$10.00$45.90$44.66$30.00$39.79$102.86
0150Type B stabilization (0160-4)SY6,994$12.00$37.85$32.06$35.00$32.77$43.47
0155Optional base, base group 01 type B 12.5 (0285-701)SY1,532$75.00$42.05$50.43$47.00$37.65$76.70
0160Optional base, base group 09 type B 12.5 (0285-709)SY1,036$85.00$62.35$57.37$67.00$103.27$114.91
0165Turnout construction- asphalt/driveway base- asphalt material (0286-2)TN363.60$75.00$242.00$393.09$234.00$162.15$475.97
0170Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY25,318$2.50$3.70$4.82$2.75$8.26$3.41
0175Milling existing asphalt pavement, 4" avg depth (0327-70-7)SY37,561$2.50$4.65$5.62$4.35$7.01$2.68
0180Milling existing asphalt pavement, 6" avg depth (0327-70-23)SY1,157$12.00$12.05$21.71$6.70$13.69$17.82
0185Superpave asphaltic conc, traffic C (0334-1-13)TN6,014.80$178.50$168.00$134.92$141.00$166.09$134.68
0190Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN5,440.90$175.00$182.00$169.89$178.00$178.89$164.50
0195Miscellaneous asphalt (0339-1)TN37.30$250.00$552.70$1,072.14$265.00$1,349.18$671.50
0200Inlets, DT bot, type H, <10' (0425-1581)EACH5$12,500$13,635$12,203$7,300.00$15,800$12,761
0205Inlets, closed flume (0425-1910)EACH2$12,000$9,690.00$6,896.46$12,400$11,119$10,547
0210Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218)LF120$195.00$151.50$170.40$186.00$175.56$237.43
0215Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF4$250.00$151.50$892.04$254.00$175.56$291.00
0220Pipe culvert,optional material,round, 24"S/CD (0430-175124)LF1,968$200.00$153.00$168.83$167.00$175.56$266.44
0225Pipe culvert, opt material, shape - elip/arch, 30"S/CD (0430-175230)LF4$1,000.00$357.00$2,461.10$689.00$409.64$668.43
0230Mitered end section, optional round, 18" CD (0430-982125)EACH1$2,500.00$2,525.00$4,101.59$2,000.00$2,925.99$3,898.61
0235Mitered end section, optional round, 24" CD (0430-982129)EACH2$2,600.00$2,525.00$7,884.01$2,500.00$2,925.99$4,205.58
0240Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625)EACH4$3,500.00$2,550.00$4,395.57$2,300.00$2,925.99$3,796.27
0245Pipe handrail - guiderail, aluminum (0515-1-2)LF13$150.00$77.35$79.98$74.00$84.43$122.89
0250Concrete curb & gutter, type F (0520-1-10)LF181$75.00$56.10$141.15$126.00$68.83$57.26
0255Concrete sidewalk and driveways, 6" thick (0522-2)SY129$120.00$131.30$202.80$110.00$152.15$153.09
0260Concrete ditch pavement, 4", reinforced (0524-1-29)SY34$100.00$252.50$198.86$150.00$292.60$171.76
0265Detectable warnings (0527-2)SF68$35.00$28.20$78.69$50.00$70.22$34.92
0270Guardrail -roadway, general (0536-1-1)LF789$25.00$24.95$25.79$24.00$27.22$33.97
0275Guardrail removal (0536-73)LF238$10.00$2.45$2.50$2.35$2.64$3.19
0280Guardrail end treatment- parallel approach terminal (0536-85-24)EACH6$3,200.00$3,195.00$3,301.74$3,050.00$3,485.39$4,105.53
0285Performance turf, sod (0570-1-2)SY9,276$4.00$4.89$7.46$6.95$6.19$4.45
0290Performance turf, sod and shoulder treatment index (0570-1-3)SY8,170$5.00$10.97$8.30$7.60$10.24$7.92
0295Conduit, furnish & install, open trench (0630-2-11)LF28$10.00$27.50$30.34$27.20$22.52$86.80
0300Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH2$1,250.00$1,375.00$1,511.22$1,360.00$2,222.77$1,447.23
0305Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1)EACH4$2,500.00$2,650.00$2,916.53$2,659.00$3,909.70$2,156.54
0310Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12)EACH4$1,500.00$2,190.00$2,410.80$2,200.00$3,497.16$1,911.70
0315Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132)EACH2$6,500.00$7,230.00$7,966.60$7,200.00$9,393.71$7,441.64
0320Raised pavement marker, type B (0706-1-3)EACH2,325$5.00$4.35$5.25$4.50$5.25$4.40
0325Painted pavement markings, standard, white, solid, 6" (0710-11101)GM7.58$1,500.00$2,160.00$2,627.97$2,240.00$1,575.61$2,199.34
0330Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF810$1.00$1.85$2.23$1.91$1.17$1.87
0335Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF175$2.00$1.95$2.36$13.20$2.33$1.98
0340Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF1,198$3.00$2.05$2.49$2.15$3.50$2.09
0345Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM0.02$1,000.00$567.00$626.82$534.00$1,060.91$525.00
0350Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.71$1,000.00$777.60$947.74$797.00$1,154.22$783.02
0355Painted pavement markings, standard, white, message or symbol (0710-11160)EACH3$100.00$48.60$59.07$51.00$99.23$49.50
0360Painted pavement markings, standard, white, arrows (0710-11170)EACH52$50.00$43.20$52.50$45.00$52.53$44.00
0365Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM7.42$1,500.00$2,160.00$2,626.98$2,240.00$1,574.96$2,198.44
0370Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF499$2.00$1.94$2.36$2.05$2.33$1.98
0375Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.08$1,000.00$777.60$910.96$777.00$1,125.18$763.37
0380Initial contingency amount, DO not bid (0999-25)LS1$54,000$54,000$54,000$54,000$54,000$54,000
0385Ground-in rumble strips, 8" sinusoidal (0546-72-3)GM6.33$1,600.00$1,650.00$3,164.53$2,350.00$2,379.01$4,671.16
0390Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH14$600.00$567.00$733.08$610.00$612.90$659.98
0395Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH5$2,500.00$2,376.00$2,795.23$1,420.00$2,568.33$1,539.95
0400Single column ground sign assembly, relocate (0700-1500)EACH1$1,200.00$1,296.00$577.23$152.00$1,400.89$164.99
0405Single column ground sign assembly, remove (0700-1600)EACH17$25.00$27.00$72.15$51.00$29.19$55.00
0410Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH14$400.00$399.60$342.01$405.00$431.95$439.98
0415Sign panel, furnish & install ground mount, 12-20 SF (0700-3102)EACH10$550.00$540.00$1,451.73$607.00$583.71$659.98
0420Sign panel, furnish & install ground mount, 21-30 SF (0700-3103)EACH2$1,000.00$864.00$1,844.25$910.00$933.94$989.96
0425Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH4$1,200.00$1,080.00$1,178.03$1,015.00$1,167.42$1,099.96
0430Sign panel, remove, UP to 12 SF (0700-3601)EACH18$200.00$189.00$43.29$51.00$204.30$55.00
0435Sign panel, remove, 12-20 SF (0700-3602)EACH10$150.00$135.00$101.02$51.50$145.93$55.00
0440Sign panel, remove, 21-30 SF (0700-3603)EACH2$200.00$162.00$144.30$52.00$175.12$55.00
0445Tubular marker, 36" yellow (0704-1-4)EACH24$250.00$216.00$353.55$203.00$291.86$219.99
0450Object marker, type 1 (0705-10-1)EACH5$350.00$162.00$281.40$152.00$379.41$164.99
0455Object marker, type 3 (0705-10-3)EACH4$350.00$162.00$281.40$153.00$379.42$165.00
0460Raised pavement marker, type B (0706-1-3)EACH1,599$5.00$4.35$5.25$4.50$5.25$4.40
0465Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF40$10.00$5.40$6.56$5.60$11.67$5.50
0470Painted pavement markings, surface (0710-90)LS1$35,000$48,000$58,339$47,000$37,941$48,888
0475Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF810$5.00$3.50$4.21$3.60$4.67$3.53
0480Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF175$6.00$5.20$6.33$5.40$5.84$5.30
0485Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF388$7.00$6.95$8.43$7.20$7.00$7.06
0490Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (6/10) gap 6" (0711-11141)GM0.71$5,000.00$2,430.00$2,878.28$2,490.00$5,194.05$2,446.95
0495Thermoplastic, standard, message or symbol (0711-11160)EACH3$250.00$81.00$98.44$84.00$262.67$82.50
0500Thermoplastic, standard, arrow (0711-11170)EACH49$100.00$59.40$72.19$61.50$105.07$60.50
0505Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF499$5.00$4.85$5.87$5.05$5.84$4.92
0510Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (2/4) dotted guide line, 6" (0711-11241)GM0.11$5,000.00$2,430.00$3,108.77$2,470.00$5,069.12$2,388.07
0515Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF752$17.00$16.45$19.98$17.00$18.68$16.74
0520Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM6.18$5,500.00$5,310.00$6,459.79$5,500.00$6,068.64$5,404.56
0525Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM0.02$5,000.00$1,330.00$1,466.82$1,400.00$3,714.55$1,228.64
0530Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM5.81$5,500.00$4,975.00$6,047.93$5,150.00$6,062.24$5,059.44
0535Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1)SF651$6.00$2.15$2.63$2.25$6.42$2.20
0540Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.12$50,000$38,880$46,101$40,000$36,446$39,706
0545Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.12$50,000$38,880$46,101$40,000$36,446$39,706
0550Itsfm subsurface documentation- project length (0611-1-1)MI2.77$3,500.00$1,825.00$2,008.14$1,800.00$3,892.86$1,832.86
0555Itsfm location documentation- intersection (0611-2-1)EACH1$2,650.00$1,825.00$2,007.41$1,800.00$3,044.90$1,838.16
0560Conduit, furnish & install, open trench (0630-2-11)LF253$10.00$26.00$28.56$28.00$31.71$58.18
0565Conduit, furnish & install, directional bore (0630-2-12)LF392$50.00$67.50$74.37$71.00$47.42$68.67
0570Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$20,000$16,695$18,395$16,700$13,019$14,097
0575Signal cable, remove- intersection (0632-7-6)PI1$650.00$3,335.00$3,673.32$3,300.00$1,778.21$1,447.01
0580Fiber optic cable locator (0633-6)DA260$5.00$250.00$274.87$280.00$423.81$419.11
0585Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH8$1,500.00$1,375.00$1,511.22$1,360.00$1,894.39$1,447.23
0590Aluminum signals pole, (0646-1-11)EACH8$2,500.00$2,556.00$3,296.12$3,000.00$3,482.93$2,603.58
0595Aluminum signals pole, remove (0646-1-60)EACH7$300.00$532.80$367.69$330.00$652.01$542.63
0600Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS8$750.00$990.00$1,092.36$977.00$1,398.27$1,030.48
0605Pedestrian detector, furnish & install, accessible (0665-1-12)EACH8$5,600.00$1,610.00$1,771.81$1,600.00$503.83$1,817.21
0610Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH4$7,500.00$5,300.00$5,841.38$5,250.00$7,684.26$8,607.23
0615Internally illuminated sign, remove (0700-5-60)EACH4$400.00$333.75$367.69$329.00$533.46$361.76
FDOT contract T7560: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of April 30, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way