FDOT contract T7569 bid tabulation
SR 43 (US 301) FROM MANATEE CO LINE TO S OF SR 674 (SUN... Let by Florida DOT on March 26, 2025, Hillsborough, District 7. 4 bids received; low bid $13,589,072 by Ajax Paving Industries of Florida LLC.
- Owner
- Florida DOT
- Letting
- 26 MAR 2025
- Pay items
- 153
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ajax Paving Industries of Florida LLC | $13,589,072 | Low |
| 2 | Superior Asphalt, Inc. | $15,476,217 | +14% |
| 3 | Preferred Materials Inc. | $15,491,942 | +14% |
| 4 | Watson Civil Construction, Inc. | $17,673,736 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ajax Paving Industries of Florida LLC | 2. Superior Asphalt, Inc. | 3. Preferred Materials Inc. | 4. Watson Civil Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $1,325,000 | $565,000 | $1,298,415 | $940,000 |
| 0010 | Mobilization (0101-1) | LS | 1 | $40,000 | $220,000 | $538,193 | $820,000 |
| 0015 | Maintenance of traffic (0102-1) | DA | 1 | $1,175,000 | $477,750 | $803,937 | $1,200,000 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $65,000 | $265,000 | $124,428 | $1,000,000 |
| 0025 | Special detour- temporary pavement (0102-2200) | SY | 1 | $75,000 | $161,000 | $21,951 | $161,000 |
| 0030 | Special detour- temporary pavement (0102-2200) | SY | 1 | $75,000 | $350,000 | $19,692 | $154,000 |
| 0035 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $13,500 | $9,900.00 | $2,309.50 | $30,000 |
| 0040 | Traffic control officer (0102-14) | HR | 8,416 | $75.00 | $112.00 | $84.27 | $86.00 |
| 0045 | Work zone sign (0102-60) | ED | 71,406 | $0.22 | $0.25 | $0.22 | $0.33 |
| 0050 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 1,152 | $45.00 | $45.00 | $52.67 | $50.00 |
| 0055 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 1,056 | $15.00 | $14.00 | $18.96 | $18.00 |
| 0060 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 86,482 | $0.05 | $0.15 | $0.07 | $0.11 |
| 0065 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 420 | $0.07 | $0.10 | $0.19 | $0.26 |
| 0070 | Arrow board / advance warning arrow panel (0102-76) | ED | 28 | $15.00 | $6.00 | $5.27 | $7.20 |
| 0075 | Temporary raised/retroreflective pavement marker, type D (0102-78-1) | EACH | 6,722 | $4.34 | $4.50 | $3.95 | $3.90 |
| 0080 | Portable changeable message sign, temporary (0102-99) | ED | 4,928 | $10.41 | $10.60 | $10.01 | $14.00 |
| 0085 | Temporary signalization and maintenance, intersection (0102-104) | ED | 380 | $6.81 | $41.00 | $5.41 | $110.00 |
| 0090 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 380 | $9.97 | $41.00 | $7.92 | $20.00 |
| 0095 | Type III barricade (0102-115) | ED | 460 | $0.27 | $0.30 | $0.37 | $0.50 |
| 0100 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 418 | $46.27 | $50.00 | $29.49 | $28.50 |
| 0105 | Sediment barrier (0104-10-3) | LF | 12,697 | $1.04 | $4.00 | $3.11 | $1.40 |
| 0110 | Inlet protection system (0104-18) | EACH | 1 | $245.51 | $300.00 | $245.76 | $145.00 |
| 0115 | Litter removal (0107-1) | ACRE | 1,408.89 | $45.69 | $35.00 | $28.97 | $28.50 |
| 0120 | Mowing (0107-2) | ACRE | 1,336.96 | $45.69 | $40.00 | $70.35 | $68.00 |
| 0125 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $100,000 | $403,150 | $277,504 | $440,000 |
| 0130 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $100,000 | $395,000 | $422,022 | $300,000 |
| 0135 | Removal of existing concrete (0110-4-10) | SY | 8 | $135.00 | $810.00 | $82.40 | $60.00 |
| 0140 | Mailbox, F&I single (0110-7-1) | EACH | 14 | $376.34 | $375.00 | $396.93 | $551.00 |
| 0145 | Regular excavation (0120-1) | CY | 13,852.70 | $38.00 | $36.00 | $75.42 | $60.00 |
| 0150 | Embankment (0120-6) | CY | 7,903.20 | $48.00 | $40.00 | $60.34 | $60.00 |
| 0155 | Geosynthetic reinforced embankment (0145-3) | SY | 522 | $30.00 | $61.00 | $29.50 | $18.00 |
| 0160 | Type B stabilization (0160-4) | SY | 13,864 | $28.00 | $25.50 | $69.70 | $45.00 |
| 0165 | Optional base, base group 01 (0285-701) | SY | 6,528 | $19.90 | $64.50 | $91.14 | $47.00 |
| 0170 | Optional base, base group 02 (0285-702) | SY | 92 | $75.85 | $125.00 | $92.50 | $59.00 |
| 0175 | Optional base, base group 06 (0285-706) | SY | 63 | $111.77 | $175.00 | $89.03 | $88.00 |
| 0180 | Optional base, base group 08 (0285-708) | SY | 71 | $90.80 | $375.00 | $93.05 | $160.00 |
| 0185 | Optional base, base group 09 (0285-709) | SY | 4,618 | $55.01 | $75.00 | $100.38 | $74.40 |
| 0190 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 49,005 | $4.76 | $4.00 | $3.50 | $4.10 |
| 0195 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 381 | $20.28 | $21.00 | $8.06 | $23.00 |
| 0200 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 25,894 | $1.23 | $7.00 | $5.40 | $4.45 |
| 0205 | Milling existing asphalt pavement, 4" avg depth (0327-70-7) | SY | 52,278 | $6.43 | $4.70 | $3.30 | $4.65 |
| 0210 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 13,671.10 | $145.83 | $163.75 | $138.74 | $149.00 |
| 0215 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 11,454 | $176.78 | $181.00 | $168.48 | $170.00 |
| 0220 | Miscellaneous asphalt (0339-1) | TN | 34.50 | $157.17 | $820.00 | $722.11 | $562.00 |
| 0225 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 1 | $10,603 | $12,350 | $7,847.87 | $11,000 |
| 0230 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 100 | $251.82 | $325.00 | $230.86 | $290.00 |
| 0235 | Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218) | LF | 160 | $291.13 | $360.00 | $293.49 | $300.00 |
| 0240 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 300 | $229.20 | $315.00 | $229.39 | $295.00 |
| 0245 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 51 | $342.90 | $345.00 | $301.77 | $394.00 |
| 0250 | Straight concrete endwalls, single, 0 degrees, round (0430-524100) | EACH | 1 | $9,197.64 | $20,000 | $19,371 | $5,000.00 |
| 0255 | Mitered end section, optional round, 18" CD (0430-982125) | EACH | 4 | $3,019.46 | $6,440.00 | $4,150.16 | $4,300.00 |
| 0260 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 6 | $3,019.46 | $6,550.00 | $4,150.16 | $4,700.00 |
| 0265 | Mitered end section, optional round, 24" SD (0430-984129) | EACH | 2 | $3,270.13 | $6,900.00 | $4,551.56 | $4,900.00 |
| 0270 | Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625) | EACH | 6 | $3,140.15 | $6,550.00 | $4,152.68 | $4,700.00 |
| 0275 | Bridge deck expansion joint, rehabilitation, poured joint backer rod (0458-1-21) | LF | 336 | $46.27 | $78.00 | $51.61 | $52.00 |
| 0280 | Polymer nosing for bridge expansion joint (0458-2) | CF | 115.20 | $925.52 | $1,000.00 | $821.59 | $823.00 |
| 0285 | Concrete curb, type D (0520-2-4) | LF | 70 | $35.00 | $130.00 | $55.76 | $46.00 |
| 0290 | Shoulder gutter- concrete (0520-6) | LF | 1,283 | $42.00 | $92.50 | $51.44 | $35.00 |
| 0295 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 8 | $165.84 | $675.00 | $146.19 | $70.00 |
| 0300 | Detectable warnings (0527-2) | SF | 20 | $23.14 | $130.00 | $30.97 | $82.00 |
| 0305 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 62.60 | $344.73 | $1,150.00 | $718.34 | $262.00 |
| 0310 | Bedding stone (0530-74) | TN | 52.10 | $202.03 | $1,260.00 | $751.64 | $319.00 |
| 0315 | Guardrail -roadway, general (0536-1-1) | LF | 1,081 | $23.55 | $26.00 | $26.66 | $20.50 |
| 0320 | Guardrail transition to rigid barrier, F&I- index 536- 002, approach TL-3 (0536-8122) | EACH | 4 | $3,771.69 | $5,175.00 | $4,192.92 | $3,300.00 |
| 0325 | Guardrail removal (0536-73) | LF | 538 | $2.77 | $3.50 | $3.25 | $2.40 |
| 0330 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 4 | $3,860.01 | $3,800.00 | $3,812.71 | $3,375.00 |
| 0335 | Performance turf, sod (0570-1-2) | SY | 65,577 | $4.82 | $5.75 | $3.16 | $7.90 |
| 0340 | Conduit, furnish & install, open trench (0630-2-11) | LF | 31 | $108.26 | $41.00 | $86.04 | $51.20 |
| 0345 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 1 | $2,094.43 | $2,800.00 | $1,664.52 | $1,320.00 |
| 0350 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 2 | $2,515.66 | $2,900.00 | $1,999.29 | $2,200.00 |
| 0355 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 2 | $3,140.22 | $2,350.00 | $2,495.65 | $2,050.00 |
| 0360 | Traffic monitoring site cabinet, furnish & install, type 3, pedestal mount (0695-7132) | EACH | 1 | $7,684.03 | $10,000 | $6,106.79 | $7,500.00 |
| 0365 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 18.63 | $1,735.35 | $1,800.00 | $1,579.98 | $1,550.00 |
| 0370 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 515 | $1.62 | $2.00 | $1.47 | $1.45 |
| 0375 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 920 | $1.73 | $2.00 | $1.58 | $1.55 |
| 0380 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 230 | $1.85 | $2.00 | $1.69 | $1.65 |
| 0385 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 0.29 | $561.10 | $1,000.00 | $501.89 | $487.00 |
| 0390 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.78 | $809.83 | $1,000.00 | $734.50 | $712.00 |
| 0395 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 11 | $46.27 | $45.00 | $42.13 | $41.00 |
| 0400 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 96 | $40.49 | $40.00 | $36.87 | $36.00 |
| 0405 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 21.72 | $1,735.35 | $1,750.00 | $1,579.76 | $1,550.00 |
| 0410 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 1,656 | $1.73 | $2.00 | $1.58 | $1.55 |
| 0415 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.69 | $809.83 | $1,000.00 | $734.13 | $712.00 |
| 0420 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $79,000 | $79,000 | $79,000 | $79,000 |
| 0425 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0430 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 18.28 | $676.78 | $2,600.00 | $1,879.58 | $2,100.00 |
| 0435 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 46 | $595.80 | $605.00 | $542.46 | $490.00 |
| 0440 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 49 | $1,648.58 | $1,675.00 | $1,500.98 | $1,650.00 |
| 0445 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 2 | $2,313.80 | $2,350.00 | $2,106.64 | $2,450.00 |
| 0450 | Single column ground sign assembly, relocate (0700-1500) | EACH | 23 | $26.61 | $27.00 | $24.23 | $409.00 |
| 0455 | Single column ground sign assembly, remove (0700-1600) | EACH | 80 | $92.55 | $95.00 | $84.27 | $20.50 |
| 0460 | Multi-column ground sign assembly, F&I ground mount, 30.0 SF (0700-2113) | EACH | 1 | $7,959.47 | $8,100.00 | $7,246.84 | $8,200.00 |
| 0465 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 2 | $2.31 | $2.50 | $2.11 | $1,535.00 |
| 0470 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 29 | $231.37 | $190.00 | $168.53 | $200.00 |
| 0475 | Tubular marker, 36" yellow (0704-1-4) | EACH | 2 | $173.54 | $235.00 | $210.67 | $77.00 |
| 0480 | Object marker, type 1 (0705-10-1) | EACH | 37 | $173.54 | $175.00 | $158.00 | $266.00 |
| 0485 | Object marker, type 2 (0705-10-2) | EACH | 8 | $173.54 | $175.00 | $158.00 | $128.00 |
| 0490 | Object marker, type 4 (0705-10-4) | EACH | 6 | $80.98 | $175.00 | $158.00 | $307.00 |
| 0495 | Delineator, flexible tubular (0705-11-1) | EACH | 52 | $185.10 | $82.50 | $73.73 | $77.00 |
| 0500 | Raised pavement marker, type B (0706-1-3) | EACH | 3,357 | $4.34 | $4.50 | $3.95 | $3.90 |
| 0505 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 126 | $4.63 | $5.00 | $4.21 | $4.10 |
| 0510 | Painted pavement markings, surface (0710-90) | LS | 1 | $64,297 | $65,350 | $58,540 | $54,000 |
| 0515 | Painted pavement markings, surface (0710-90) | LS | 1 | $12,147 | $12,350 | $11,060 | $9,000.00 |
| 0520 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 515 | $3.62 | $3.75 | $3.30 | $3.20 |
| 0525 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 920 | $5.44 | $5.50 | $4.95 | $4.85 |
| 0530 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 269 | $7.24 | $7.50 | $6.59 | $6.40 |
| 0535 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.60 | $2,718.71 | $2,800.00 | $2,442.19 | $2,400.00 |
| 0540 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 3 | $122.64 | $125.00 | $111.65 | $109.00 |
| 0545 | Thermoplastic, standard, arrow (0711-11170) | EACH | 78 | $62.47 | $65.00 | $56.88 | $56.00 |
| 0550 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 2,632 | $5.07 | $5.15 | $4.61 | $4.50 |
| 0555 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.68 | $2,718.71 | $3,000.00 | $2,449.70 | $2,375.00 |
| 0560 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 381 | $18.30 | $19.00 | $16.66 | $16.20 |
| 0565 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 8 | $230.22 | $235.00 | $209.61 | $204.00 |
| 0570 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 8 | $97.18 | $100.00 | $88.48 | $86.00 |
| 0575 | Thermoplastic, preformed, 24" white with 4" black contrast crosswalk on concrete pavement, 32" (0711-14526) | LF | 90 | $24.44 | $25.00 | $22.26 | $22.00 |
| 0580 | Thermoplastic, preformed, 12" white with 4" black contrast crosswalk on concrete pavement, 20" (0711-14528) | LF | 173 | $15.30 | $15.50 | $13.92 | $14.00 |
| 0585 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 13.19 | $5,218.77 | $5,350.00 | $4,749.00 | $4,650.00 |
| 0590 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.29 | $1,304.99 | $1,500.00 | $1,167.30 | $1,135.00 |
| 0595 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 16.20 | $4,893.69 | $4,975.00 | $4,454.99 | $4,350.00 |
| 0600 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 824 | $2.60 | $3.00 | $2.37 | $2.35 |
| 0605 | Conduit, furnish & install, open trench (0630-2-11) | LF | 5 | $67.96 | $45.00 | $54.01 | $67.00 |
| 0610 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 1 | $2,094.43 | $2,765.00 | $1,664.52 | $1,320.00 |
| 0615 | Electrical service wire, (0639-2-6) | LF | 34 | $11.58 | $3.00 | $9.21 | $8.70 |
| 0620 | Strain pole, wood, remove (0643-600) | EACH | 1 | $2,778.75 | $1,235.00 | $2,208.38 | $1,750.00 |
| 0625 | Loop assembly- F&I, type A (0660-2101) | AS | 3 | $3,147.38 | $3,250.00 | $2,501.34 | $1,750.00 |
| 0630 | Loop assembly, F&I, type B (0660-2102) | AS | 2 | $2,170.29 | $3,000.00 | $1,724.81 | $1,700.00 |
| 0635 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 1 | $7,674.14 | $8,250.00 | $6,098.93 | $9,300.00 |
| 0640 | Internally illuminated sign, remove (0700-5-60) | EACH | 1 | $231.57 | $90.00 | $184.04 | $547.00 |
| 0645 | Enhanced highway sign AC powered, remove - ground mount (0700-141902) | EACH | 1 | $1,389.38 | $1,765.00 | $1,104.19 | $1,800.00 |
| 0650 | Enhanced highway sign solar powered, F&I ground mount, W/beacon, UP to 12 SF of static sign panels (0700-142111) | EACH | 1 | $12,095 | $14,700 | $9,612.36 | $10,500 |
| 0655 | Sediment barrier (0104-10-3) | LF | 3,930 | $1.04 | $5.00 | $3.11 | $1.35 |
| 0660 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $150,000 | $45,000 | $242,263 | $100,000 |
| 0665 | Removal of existing concrete (0110-4-10) | SY | 17 | $41.25 | $475.00 | $81.11 | $70.00 |
| 0670 | Tree removal (0110-23) | EACH | 140 | $1,503.97 | $1,530.00 | $684.66 | $1,900.00 |
| 0675 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0680 | Utility pipe,remove & dispose, 8- 19.9" (1050-16004) | LF | 4,241 | $28.92 | $95.00 | $29.49 | $165.00 |
| 0685 | Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 6" (1050-51206) | LF | 106 | $112.74 | $220.00 | $173.80 | $181.00 |
| 0690 | Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 12" (1050-51212) | LF | 4,207 | $191.75 | $240.00 | $145.36 | $243.00 |
| 0695 | Utility fittings, ductile iron, furnish & install elbow, (1055-51112) | EACH | 6 | $2,127.54 | $1,835.00 | $947.99 | $2,200.00 |
| 0700 | Utility fittings, ductile iron, furnish & install tee, 12" (1055-51212) | EACH | 6 | $2,881.83 | $2,500.00 | $1,579.98 | $2,300.00 |
| 0703 | Utility fittings, ductile iron, furnish & install reducer, 12" (1055-51312) | EACH | 2 | $2,200.00 | $2,940.00 | $710.99 | $2,000.00 |
| 0705 | Utility fittings, ductile iron, furnish & install, 12" (1055-51512) | EACH | 3 | $1,593.05 | $1,620.00 | $695.19 | $910.00 |
| 0710 | Utility fittings, ductile iron, furnish & install Y, 12" (1055-51612) | EACH | 2 | $3,284.44 | $4,300.00 | $1,790.65 | $3,400.00 |
| 0715 | Utility fixture, valve assembly, furnish and install, 6" (1080-24106) | EACH | 4 | $4,874.02 | $6,820.00 | $3,159.96 | $2,900.00 |
| 0720 | Utility fixture, valve assembly, furnish and install, 12" (1080-24112) | EACH | 20 | $9,455.33 | $10,200 | $6,319.92 | $6,400.00 |
| 0725 | Utility fixture, valve assembly, adjust/modify (1080-24500) | EACH | 3 | $2,798.54 | $14,100 | $26,333 | $34,000 |
| 0730 | Utility fixture- blowoff assembly, furnish and install, (1080-25112) | EACH | 5 | $3,304.11 | $5,115.00 | $4,213.28 | $2,700.00 |
| 0735 | Utility fixture, vac/air furnish and INSTALL12" (1080-26112) | EACH | 3 | $4,648.42 | $10,650 | $8,426.56 | $4,400.00 |
| 0740 | Utility fixture, mechanical restraint, furnish & install, 10" (1080-29110) | EACH | 8 | $1,247.14 | $1,295.00 | $136.93 | $585.00 |
| 0745 | Utility fixture, mechanical restraint, furnish & install, 12" (1080-29112) | EACH | 79 | $826.03 | $1,295.00 | $184.33 | $590.00 |
| 0750 | Utility fixture- sample point, furnish & install, 12" (1080-32112) | EACH | 7 | $1,058.56 | $2,470.00 | $3,054.63 | $1,600.00 |
| 0755 | Fire hydrant, F&I, traffic, 3 way 2 hose, 1PUMPER, 6" (1644-136-08) | EACH | 2 | $9,444.92 | $14,900 | $6,846.58 | $7,100.00 |
| 0760 | Fire hydrant, salvage & store (1644-400) | EACH | 2 | $1,272.59 | $3,530.00 | $1,053.32 | $1,100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of March 26, 2025. Compiled by Mirage Metrics.