Removal and Repair of Deteriorated Asphalt Pavement, NYSDOT 633.14
Low bidders on NYSDOT contracts carried a median of $69.00 per SY for this item, from 06 JAN 2022 to 30 NOV 2023, across 41 low bids. Half of all 176 bids fell between $43.50 and $136.50.
- Owner
- New York State DOT
- Item
- 633.14
- Unit
- SY
- Data through
- 15 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 37 | 31 | $65.00 | 128 | $75.00 |
| 2023 | 15 | 10 | $95.00 | 48 | $77.50 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Region 05 | 4 | $22.50 | 34 | $40.00 |
| Region 10 | 7 | $33.00 | 33 | $75.00 |
| Region 01 | 11 | $75.00 | 29 | $95.00 |
| Region 04 | 7 | $75.00 | 27 | $110.00 |
| Region 09 | 5 | $96.50 | 13 | $97.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 10 to 134 | 10 | $118.10 |
| 240 to 549 | 10 | $55.00 |
| 558 to 900 | 10 | $82.50 |
| 1,100 to 12,300 | 11 | $33.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Rifenburg Construction Inc | 11 | 9 (82%) |
| H & L Contracting LLC | 7 | 7 (100%) |
| Cold Spring Construction Company | 10 | 4 (40%) |
| Bothar Construction LLC | 7 | 3 (43%) |
| Villager Construction Inc | 7 | 2 (29%) |
| Oakgrove Construction Inc | 6 | 2 (33%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 30 NOV 2023 | D265135 | Region 01 | 820 | $110.00 | $34.50 | 3 | Barrett Paving Materials Inc | NYSDOT |
| 09 NOV 2023 | D265104 | Region 04 | 814 | $75.00 | $180.00 | 3 | Cold Spring Construction Company | NYSDOT |
| 09 NOV 2023 | D265123 | Region 05 | 95 | n/a | $56.50 | 2 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 28 SEP 2023 | D265088 | Region 05 | 2,243 | n/a | $75.00 | 1 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 27 JUL 2023 | D265064 | Region 10 | 1,950 | $10.00 | $29.00 | 6 | Posillico Civil Inc | NYSDOT |
| 18 MAY 2023 | D265025 | Region 04 | 266 | $145.00 | $105.00 | 5 | Sealand Contractors Corp. | NYSDOT |
| 23 MAR 2023 | D264983 | Region 09 | 900 | $90.00 | $111.00 | 2 | Dalrymple Gravel & Contracting Co Inc | NYSDOT |
| 23 MAR 2023 | D264994 | Region 01 | 645 | n/a | $100.59 | 2 | Peckham Road Corp | NYSDOT |
| 23 MAR 2023 | D264998 | Region 11 | 44 | $400.00 | $500.00 | 7 | Westmoreland Construction Inc | NYSDOT |
| 23 MAR 2023 | D265000 | Region 05 | 532 | n/a | $90.00 | 1 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 23 MAR 2023 | D265001 | Region 05 | 395 | $60.00 | $60.00 | 1 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 09 MAR 2023 | D264969 | Region 01 | 472 | $100.00 | $78.00 | 2 | Callanan Industries Inc | NYSDOT |
| 09 MAR 2023 | D265002 | Region 06 | 581 | $69.00 | $69.00 | 3 | D&H Excavating Inc | NYSDOT |
| 02 FEB 2023 | D264945 | Region 10 | 750 | $100.00 | $95.00 | 6 | Liberty II Sweeping and Maintenance Inc | NYSDOT |
| 19 JAN 2023 | D264946 | Region 05 | 1,700 | n/a | $25.00 | 4 | Union Concrete & Construction Corp | NYSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the NYSDOT explorer.
How these prices were read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NYSDOT's own: this item is compared with NYSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NYSDOT letting of 15 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.