ODOT contract 250124 bid tabulation

LIC-CR 804-00.96 (Church St) (MINOR RECONSTRUCTION). Let by Ohio DOT on February 27, 2025, LIC. 10 bids received; low bid $2,135,073 by Miller Bros Const Inc, -11% against the engineer's estimate of $2,400,000.

Owner
Ohio DOT
Letting
27 FEB 2025
Pay items
91
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Miller Bros Const Inc$2,135,073Low-11%
2Law General Contracting Inc$2,185,999+2.0%-9.0%
3Trucco Construction Co Inc$2,387,947+12%-1.0%
4Axis Civil Construction LLC$2,584,500+21%+8.0%
5Eclipse Co LLC$2,670,034+25%+11%
6Boss Excavating & Grading Inc$2,686,425+26%+12%
7Shelly & Sands Inc$2,714,151+27%+13%
8Danbert Incorporated$2,772,514+30%+16%
9Double Z Construction Company$2,873,018+35%+20%
10Complete General Construction Company$2,970,946+39%+24%
ODOT contract 250124: bids by rank

Engineer's estimate: $2,400,000.

Bid tabulation

LinePay itemUnitQuantity1. Miller Bros Const Inc2. Law General Contracting Inc3. Trucco Construction Co Inc4. Axis Civil Construction LLC5. Eclipse Co LLC6. Boss Excavating & Grading Inc
1Clearing and grubbing, as per plan (201E11001)LS1$18,000$7,144.00$2,500.00$10,000$5,000.00$6,880.00
2Pavement removed (202E23000)SY7,305$6.50$7.00$6.14$12.50$10.00$14.00
3Walk removed (202E30000)SF10,544$1.00$1.25$1.60$2.00$1.00$8.00
4Curb removed (202E32000)FT302$4.50$9.00$3.84$6.00$12.00$10.00
5Pipe removed, 24" and under (202E35100)FT579$80.00$41.00$46.93$20.00$22.00$14.00
6Guardrail removed (202E38000)FT53$14.50$39.00$15.00$8.00$10.00$3.00
7Manhole removed (202E58000)EACH1$1,000.00$825.00$678.44$1,500.00$436.00$312.00
8Catch basin removed (202E58100)EACH6$750.00$425.00$644.57$700.00$436.00$829.00
9Fence removed (202E75000)FT24$10.00$13.70$10.00$12.00$20.00$27.00
10Gate removed (202E75250)EACH1$250.00$82.00$1,500.00$290.00$250.00$662.00
11Excavation (203E10000)CY4,520$26.70$32.00$25.00$35.00$47.00$35.00
12Embankment (203E20000)CY357$26.70$16.00$17.04$35.00$25.00$15.00
13Subgrade compaction (204E10000)SY8,665$1.00$0.80$2.29$2.00$1.00$2.00
14Excavation of subgrade (204E13000)CY2,463$22.50$31.00$21.21$35.00$48.00$42.00
15Embankment (204E20000)CY198$19.00$21.50$18.18$35.00$50.00$22.00
16Granular material, type B (204E30010)CY2,265$66.00$54.00$72.19$72.00$106.00$52.00
17Proof rolling (204E45000)HR8$135.00$157.00$313.20$225.00$304.00$616.00
18Geotextile fabric (204E50000)SY1,493$1.85$1.75$1.94$1.80$1.00$4.00
19Geogrid (204E51000)SY1,254$2.85$3.00$1.73$3.50$2.00$5.00
20Gate, type CLT (607E61200)EACH1$6,850.00$3,000.00$6,850.00$6,850.00$4,500.00$3,360.00
214" concrete walk (608E10000)SF14,751$9.60$7.50$11.99$9.00$8.00$10.00
22Curb ramp (608E52000)SF703$23.50$24.00$25.97$18.00$14.00$20.00
23Detectable warning (608E53020)SF120$25.00$59.00$32.43$24.00$25.00$50.00
24Right-of-way monument, type B (623E40520)EACH44$125.00$144.00$126.51$95.00$627.00$164.00
25Special - bollard (690E50600)EACH9$575.00$691.00$575.00$575.00$1,500.00$2,700.00
26Topsoil furnished and placed (653E10000)CY727$85.00$55.00$66.39$50.00$80.00$81.00
27Soil analysis test (659E00100)EACH2$150.00$147.00$125.00$150.00$125.00$202.00
28Seeding and mulching, class 1 (659E00500)SY6,551$1.00$1.30$1.10$1.00$1.00$3.00
29Repair seeding and mulching (659E14000)SY328$1.00$1.00$0.80$1.00$1.00$7.00
30Commercial fertilizer (659E20000)TON0.88$1,250.00$1,055.00$898.22$1,250.00$898.00$2,688.00
31Lime (659E31000)ACRE1.35$150.00$182.00$155.50$150.00$156.00$672.00
32Water (659E35000)MGAL35$1.00$1.20$1.00$1.00$1.00$20.00
33Storm water pollution prevention plan (832E15000)LS1$2,500.00$5,286.00$2,000.00$2,500.00$2,450.00$3,182.00
34Storm water pollution prevention inspections (832E15002)LS1$7,350.00$11,747$4,800.00$8,100.00$4,080.00$3,200.00
35Storm water pollution prevention inspection software (832E15010)LS1$1,800.00$2,114.00$1,736.00$2,000.00$1,736.00$2,333.00
36Erosion control (832E30000)EACH2,000$1.00$1.00$1.00$1.00$1.00$1.00
374" base pipe underdrains (605E06000)FT3,409$10.00$9.00$7.77$14.00$25.00$15.00
384" base pipe underdrains, as per plan (605E06001)FT56$25.00$9.50$7.75$10.00$28.00$20.00
3912" conduit, type B (611E04400)FT1,079$70.00$93.00$155.00$145.00$119.00$150.00
4012" conduit, type C (611E04600)FT373$53.00$56.00$75.64$110.00$97.00$92.00
4118" conduit, type B (611E07400)FT34$134.00$130.00$135.33$150.00$157.00$215.00
4230" conduit, type B (611E13400)FT310$219.00$292.00$400.63$330.00$330.00$270.00
4314" X 23" conduit, type B, 706.04 (611E52202)FT127$197.00$220.00$390.66$330.00$457.00$286.00
44Catch basin, no. 2-3 (611E98510)EACH1$2,800.00$2,788.00$4,042.69$4,200.00$4,859.00$3,873.00
45Manhole, no. 3 (611E99574)EACH8$4,700.00$9,971.00$7,196.55$7,200.00$9,680.00$10,752
46Manhole reconstructed to grade (611E99660)EACH11$1,700.00$1,205.00$2,916.28$4,000.00$1,443.00$977.00
47Drainage structure, misc.: bulkhead (611E99900)EACH1$2,200.00$1,395.00$887.34$430.00$1,141.00$1,117.00
48Drainage structure, misc.: curb inlet, 600-2 (611E99900)EACH7$3,000.00$2,810.00$4,452.53$6,000.00$5,973.00$4,768.00
49Drainage structure, misc.: curb inlet, 600-2, deep (611E99900)EACH11$3,100.00$4,313.00$4,452.85$6,700.00$5,652.00$4,969.00
50Drainage structure, misc.: yard drain (611E99900)EACH21$1,400.00$1,141.00$2,048.07$1,700.00$3,153.00$2,169.00
51Low strength mortar backfill (613E41200)CY38$235.00$222.00$227.67$160.00$310.00$279.00
52Full depth pavement sawing (252E01500)FT818$3.00$2.00$2.50$2.00$3.00$3.00
53Pavement planing, asphalt concrete, 1.25" depth (254E01000)SY270$31.25$12.00$23.51$12.00$24.00$42.00
54Asphalt concrete base, PG64-22, (449) (301E56000)CY1,462$181.00$197.00$189.10$216.00$189.00$245.00
55Aggregate base (304E20000)CY1,400$87.00$80.00$88.00$115.00$95.00$51.00
56Tack coat (407E10000)GAL746$2.25$6.00$4.90$3.50$5.00$3.00
57Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000)CY243$259.00$247.00$214.10$255.00$214.00$348.00
58Asphalt concrete intermediate course, type 2, (448) (441E50300)CY320$217.00$223.00$202.10$255.00$202.00$291.00
596" non-reinforced concrete pavement, class QC 1P (452E10010)SY620$85.50$90.00$87.45$95.00$75.00$120.00
608" non-reinforced concrete pavement, class QC 1P (452E12010)SY90$99.00$106.00$110.06$105.00$87.00$145.00
61Combination curb and gutter, type 2, as per plan (609E12001)FT3,403$28.00$33.00$25.57$36.75$26.00$35.00
62Curb, type 6 (609E26000)FT65$65.00$85.00$40.14$38.75$55.00$82.00
63Fire hydrant adjusted to grade (638E10400)EACH3$3,900.00$1,200.00$1,998.14$4,000.00$2,029.00$2,540.00
64Valve box adjusted to grade, as per plan (638E10801)EACH39$265.00$103.00$544.93$445.00$721.00$900.00
65Special - 3/4" copper water service line, (city of (638E20766)FT137$32.00$33.00$167.17$75.00$31.00$35.00
66Special - 3/4" corporation stop, (city of newark S (638E20892)EACH4$980.00$111.00$707.60$520.00$402.00$287.00
67Special - service box, (city of newark standard DR (638E20904)EACH4$1,340.00$521.00$771.24$740.00$641.00$711.00
68Water work, misc.: waterline lowering (638E98000)EACH5$9,600.00$4,437.00$19,020$11,500$9,883.00$10,300
69Conduit, misc.: sanitary sewer service replaced (611E97200)EACH5$2,800.00$564.00$649.48$2,400.00$7,503.00$5,500.00
70Ground mounted support, no. 3 post, as per plan (630E03101)FT251.40$25.00$12.00$25.00$25.00$21.00$13.00
71Sign post reflector (630E08600)EACH9$55.00$41.00$55.00$55.00$73.00$47.00
72Sign, flat sheet (630E80100)SF115$28.00$24.00$28.00$28.00$24.00$27.00
73Removal of ground mounted sign and disposal (630E84900)EACH21$30.00$24.00$30.00$30.00$18.00$564.00
74Removal of ground mounted sign and reerection (630E85100)EACH1$250.00$53.00$250.00$250.00$72.00$61.00
75Removal of ground mounted post support and disposal (630E86002)EACH17$30.00$24.00$30.00$30.00$23.00$27.00
76Center line (644E00300)MI0.49$6,250.00$8,500.00$6,250.00$6,250.00$10,846$8,400.00
77Channelizing line, 8" (644E00400)FT167$2.30$3.00$2.30$2.30$3.00$3.00
78Stop line (644E00500)FT64$8.00$12.00$8.00$8.00$8.00$11.00
79Crosswalk line, 12" (644E00620)FT432$3.75$5.50$3.75$3.75$4.00$5.00
80School symbol marking, 72" (644E01100)EACH1$830.00$528.00$830.00$830.00$750.00$1,115.00
81Lane arrow (644E01300)EACH14$95.00$206.00$95.00$95.00$135.00$128.00
82Word on pavement, 72" (644E01400)EACH1$125.00$323.00$125.00$125.00$210.00$168.00
83Crosswalk line, 12", type B125, as per plan (647E20036)FT276$17.85$5.50$17.85$17.85$16.00$24.00
84Pull box, misc.: reset (625E31600)EACH3$825.00$700.00$788.41$400.00$4,000.00$1,344.00
85Law enforcement officer with patrol car for assistance (614E11110)HR16$90.00$88.00$130.27$65.00$65.00$161.00
86Detour signing (614E12420)LS1$3,750.00$5,873.00$3,750.00$3,750.00$3,750.00$14,065
87Water (616E10000)MGAL20$75.00$111.00$79.16$1.00$22.00$145.00
88Premium for contract performance bond and for payment bond (103E05000)LS1$18,000$25,000$15,327$18,000$29,000$26,881
89Maintaining traffic (614E11000)LS1$27,000$13,400$7,000.00$40,000$38,320$4,531.00
90Construction layout stakes and surveying (623E10000)LS1$29,200$32,000$18,260$15,000$12,866$35,816
91Mobilization (624E10000)LS1$106,000$154,969$100,000$65,000$67,882$38,500
ODOT contract 250124: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy