ODOT contract 250228 bid tabulation
STA-SR 687-02.30 (MINOR RECONSTRUCTION). Let by Ohio DOT on April 24, 2025, STA. 2 bids received; low bid $1,785,586 by Wenger Excavating Inc, +1.3% against the engineer's estimate of $1,763,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 158
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Wenger Excavating Inc | $1,785,586 | Low | +1.0% |
| 2 | S E T Inc | $2,169,311 | +21% | +23% |
Engineer's estimate: $1,763,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Wenger Excavating Inc | 2. S E T Inc |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $4,550.00 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 1,207 | $28.00 | $20.00 |
| 3 | Traffic island removed (202E30800) | SY | 50 | $28.00 | $25.00 |
| 4 | Curb removed (202E32000) | FT | 1,971 | $12.00 | $6.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 404 | $21.00 | $20.00 |
| 6 | Manhole removed (202E58000) | EACH | 1 | $1,450.00 | $1,200.00 |
| 7 | Catch basin removed (202E58100) | EACH | 7 | $885.00 | $1,100.00 |
| 8 | Removal misc.: inspection well (202E98100) | EACH | 3 | $425.00 | $800.00 |
| 9 | Removal misc.: conduit (202E98200) | FT | 50 | $20.00 | $25.00 |
| 10 | Excavation (203E10000) | CY | 1,852 | $24.00 | $30.00 |
| 11 | Embankment (203E20000) | CY | 30 | $22.00 | $40.00 |
| 12 | Embankment, as per plan (203E20001) | CY | 10 | $22.00 | $75.00 |
| 13 | Subgrade compaction (204E10000) | SY | 2,957 | $6.50 | $3.00 |
| 14 | Excavation of subgrade (204E13000) | CY | 255 | $34.00 | $30.00 |
| 15 | Granular material, type B (204E30010) | CY | 255 | $55.00 | $85.00 |
| 16 | Proof rolling (204E45000) | HR | 5 | $265.00 | $250.00 |
| 17 | Geotextile fabric (204E50000) | SY | 798 | $2.00 | $2.00 |
| 18 | Monument assembly removed and reset (623E40000) | EACH | 2 | $650.00 | $1,200.00 |
| 19 | Special - as-built construction plans (690E91000) | LS | 1 | $6,695.00 | $6,000.00 |
| 20 | Special - survey control verification (690E98400) | LS | 1 | $2,250.00 | $4,000.00 |
| 21 | Longitudinal channelizing device, as per plan (831E00101) | FT | 501 | $92.00 | $80.00 |
| 22 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 2 | $315.00 | $400.00 |
| 23 | Soil analysis test (659E00100) | EACH | 2 | $225.00 | $150.00 |
| 24 | Topsoil (659E00300) | CY | 143 | $26.00 | $90.00 |
| 25 | Seeding and mulching (659E10000) | SY | 1,286 | $3.50 | $5.00 |
| 26 | Commercial fertilizer (659E20000) | TON | 0.18 | $1,010.00 | $1,000.00 |
| 27 | Lime (659E31000) | ACRE | 0.27 | $520.00 | $200.00 |
| 28 | Water (659E35000) | MGAL | 6.90 | $15.00 | $50.00 |
| 29 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,550.00 | $4,500.00 |
| 30 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $8,250.00 | $6,500.00 |
| 31 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $13,568 | $14,000 |
| 32 | Erosion control (832E30000) | EACH | 20,740 | $1.00 | $1.00 |
| 33 | 6" unclassified pipe underdrains (605E13300) | FT | 50 | $21.00 | $25.00 |
| 34 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 1,518 | $21.00 | $20.00 |
| 35 | Aggregate drains (605E31100) | FT | 50 | $16.00 | $25.00 |
| 36 | 4" conduit, type E (611E00400) | FT | 15 | $12.00 | $25.00 |
| 37 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 100 | $21.00 | $35.00 |
| 38 | 6" conduit, type F (611E01500) | FT | 50 | $21.00 | $20.00 |
| 39 | 12" conduit, type B (611E04400) | FT | 9 | $88.50 | $200.00 |
| 40 | 15" conduit, type B (611E05900) | FT | 20 | $104.50 | $200.00 |
| 41 | 15" conduit, type B, as per plan (611E05901) | FT | 8 | $115.00 | $250.00 |
| 42 | 18" conduit, type B (611E07400) | FT | 377 | $106.00 | $135.00 |
| 43 | 24" conduit, type B (611E10400) | FT | 18 | $118.00 | $250.00 |
| 44 | Conduit, misc.: type F for drainage discharge cont (611E97400) | FT | 50 | $40.00 | $120.00 |
| 45 | Conduit, misc.:type E for drainage discharge cont (611E97400) | FT | 50 | $40.00 | $120.00 |
| 46 | Catch basin, no. 3 (611E98150) | EACH | 3 | $8,225.00 | $4,500.00 |
| 47 | Catch basin, no. 3A (611E98180) | EACH | 3 | $6,420.00 | $3,500.00 |
| 48 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 1 | $1,850.00 | $4,000.00 |
| 49 | Manhole, no. 3 (611E99574) | EACH | 2 | $9,215.00 | $5,500.00 |
| 50 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 4 | $1,835.00 | $3,500.00 |
| 51 | Manhole reconstructed to grade (611E99660) | EACH | 2 | $3,255.00 | $4,000.00 |
| 52 | Precast reinforced concrete outlet (611E99710) | EACH | 3 | $625.00 | $400.00 |
| 53 | Inspection well (611E99720) | EACH | 3 | $560.00 | $1,100.00 |
| 54 | Pavement planing, asphalt concrete, 1.25" (254E01000) | SY | 8,435 | $4.85 | $4.50 |
| 55 | Full depth pavement sawing (255E20000) | FT | 1,815 | $5.00 | $4.00 |
| 56 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 455 | $265.00 | $270.00 |
| 57 | Asphalt concrete base, PG64-22, (449), (driveways) (301E56100) | CY | 18 | $325.00 | $270.00 |
| 58 | Aggregate base (304E20000) | CY | 516 | $72.00 | $85.00 |
| 59 | Non-tracking tack coat (407E20000) | GAL | 794 | $5.35 | $4.00 |
| 60 | Fine graded polymer asphalt concrete, type B, (449) (424E14100) | CY | 382 | $325.00 | $320.00 |
| 61 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 121 | $285.00 | $265.00 |
| 62 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 6 | $385.00 | $560.00 |
| 63 | 8" non-reinforced concrete pavement, class QC MS (452E12050) | SY | 509 | $125.00 | $110.00 |
| 64 | Curb, type 3-A (609E20000) | FT | 136 | $28.00 | $13.00 |
| 65 | Curb, type 6 (609E26000) | FT | 1,873 | $36.00 | $23.00 |
| 66 | Special - pavement overlay fabric composite (690E12060) | SY | 941 | $48.00 | $37.00 |
| 67 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 10 | $225.00 | $4,000.00 |
| 68 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 4 | $1,125.00 | $4,500.00 |
| 69 | RPM (621E00100) | EACH | 102 | $55.00 | $110.00 |
| 70 | Raised pavement marker removed (621E54000) | EACH | 50 | $38.00 | $40.00 |
| 71 | Ground mounted support, no. 2 post (630E02100) | FT | 120 | $22.00 | $20.00 |
| 72 | Sign post reflector (630E08600) | EACH | 2 | $68.00 | $50.00 |
| 73 | Sign support assembly, pole mounted (630E79500) | EACH | 8 | $135.00 | $125.00 |
| 74 | Sign, flat sheet (630E80100) | SF | 57 | $22.55 | $25.00 |
| 75 | Removal of ground mounted sign and disposal (630E84900) | EACH | 6 | $20.50 | $30.00 |
| 76 | Removal of ground mounted sign and reerection (630E85100) | EACH | 10 | $85.00 | $60.00 |
| 77 | Removal of ground mounted post support and disposal (630E86002) | EACH | 10 | $25.00 | $25.00 |
| 78 | Removal of ground mounted post support and reerection (630E86010) | EACH | 7 | $88.00 | $50.00 |
| 79 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 2 | $28.00 | $250.00 |
| 80 | Removal of pole mounted sign and reerection (630E87520) | EACH | 9 | $56.00 | $60.00 |
| 81 | Edge line, 6" (646E10010) | MI | 0.07 | $3,125.00 | $4,500.00 |
| 82 | Lane line, 6" (646E10110) | MI | 0.31 | $1,265.00 | $2,500.00 |
| 83 | Center line (646E10200) | MI | 0.40 | $5,335.00 | $6,000.00 |
| 84 | Channelizing line, 12" (646E10310) | FT | 3,419 | $2.95 | $2.50 |
| 85 | Stop line (646E10400) | FT | 245 | $8.85 | $12.00 |
| 86 | Transverse/diagonal line (646E10600) | FT | 45 | $7.35 | $12.00 |
| 87 | Island marking (646E10800) | SF | 392 | $7.75 | $20.00 |
| 88 | Lane arrow (646E20300) | EACH | 36 | $133.00 | $200.00 |
| 89 | Dotted line, 6" (646E20504) | FT | 113 | $2.25 | $3.00 |
| 90 | Conduit, 2", 725.04 (625E25400) | FT | 9 | $34.60 | $30.00 |
| 91 | Conduit, 3", 725.04 (625E25500) | FT | 42 | $51.50 | $40.00 |
| 92 | Conduit, 4", 725.04 (625E25600) | FT | 80 | $62.00 | $50.00 |
| 93 | Conduit, jacked or drilled, 725.04, (4") (625E25902) | FT | 475 | $115.00 | $80.00 |
| 94 | Luminaire, conventional, solid state (LED) , (type (625E26252) | EACH | 8 | $515.00 | $650.00 |
| 95 | Trench (625E29000) | FT | 131 | $14.00 | $20.00 |
| 96 | Pull box, 725.08, 18" (625E30700) | EACH | 8 | $1,285.00 | $1,000.00 |
| 97 | Pull box, 725.08, 24" (625E30706) | EACH | 2 | $1,455.00 | $1,300.00 |
| 98 | Pull box removed (625E31510) | EACH | 8 | $340.00 | $200.00 |
| 99 | Ground rod (625E32000) | EACH | 10 | $310.00 | $250.00 |
| 100 | Underground warning/marking tape, as per plan (625E36011) | FT | 606 | $1.80 | $2.00 |
| 101 | Luminaire removed (625E75506) | EACH | 8 | $120.00 | $125.00 |
| 102 | Luminaire support removed (625E75520) | EACH | 8 | $125.00 | $450.00 |
| 103 | Arc flash calculations and label, (everhard road) (625E76000) | EACH | 1 | $2,215.00 | $1,100.00 |
| 104 | Arc flash calculations and label, (frank ave) (625E76000) | EACH | 1 | $2,215.00 | $1,100.00 |
| 105 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006) | EACH | 14 | $1,225.00 | $1,000.00 |
| 106 | Vehicular signal head, (LED), 4-section, 12" lens, 1-way, polycarbonate (632E05064) | EACH | 2 | $1,560.00 | $1,300.00 |
| 107 | Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086) | EACH | 12 | $1,780.00 | $1,500.00 |
| 108 | Covering of vehicular signal head (632E25000) | EACH | 28 | $25.00 | $60.00 |
| 109 | Messenger wire, 7 strand, 3/8" diameter with accessories (632E30200) | FT | 769 | $16.85 | $11.00 |
| 110 | Tether wire, with accessories (632E30600) | FT | 769 | $29.25 | $11.00 |
| 111 | Signal cable, 4 conductor, no. 14 AWG (632E40400) | FT | 1,214 | $8.45 | $3.50 |
| 112 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 2,110 | $5.85 | $4.00 |
| 113 | Strain pole foundation (632E64000) | EACH | 8 | $5,220.00 | $7,500.00 |
| 114 | Power cable, 2 conductor, no. 4 AWG (632E69200) | FT | 434 | $6.00 | $5.00 |
| 115 | Power service, as per plan (632E70001) | EACH | 2 | $4,860.00 | $4,500.00 |
| 116 | Combination strain pole, type TC-81.11, design 10 (632E87130) | EACH | 4 | $15,350 | $15,000 |
| 117 | Combination strain pole, type TC-81.11, design 12 (632E87140) | EACH | 4 | $17,950 | $16,000 |
| 118 | Removal of traffic signal installation, as per plan (632E90101) | EACH | 2 | $6,220.00 | $7,500.00 |
| 119 | Signalization, misc.: traffic signal coordination (632E90300) | LS | 1 | $3,565.00 | $2,000.00 |
| 120 | Cabinet, type TS-2, as per plan (633E65511) | EACH | 2 | $21,250 | $22,000 |
| 121 | Cabinet foundation, as per plan (633E67101) | EACH | 2 | $2,365.00 | $2,500.00 |
| 122 | Controller work pad, as per plan (633E67201) | EACH | 2 | $795.00 | $600.00 |
| 123 | Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001) | EACH | 2 | $6,520.00 | $6,500.00 |
| 124 | Advance radar detection, as per plan (809E69001) | EACH | 6 | $950.00 | $1,100.00 |
| 125 | Stop line radar detection, as per plan (809E69101) | EACH | 8 | $925.00 | $1,100.00 |
| 126 | Traffic compacted surface, type A or B (410E12000) | CY | 100 | $26.00 | $105.00 |
| 127 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 120 | $98.00 | $90.00 |
| 128 | Special - work zone traffic signal (614E11300) | EACH | 2 | $19,075 | $50,000 |
| 129 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $225.00 | $300.00 |
| 130 | Portable changeable message sign, as per plan (614E18601) | SNMT | 18 | $865.00 | $950.00 |
| 131 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 0.10 | $680.00 | $850.00 |
| 132 | Work zone lane line, class I, 6", 740.06, type I (614E20210) | MI | 0.02 | $680.00 | $16,000 |
| 133 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 0.08 | $680.00 | $1,100.00 |
| 134 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.66 | $1,400.00 | $2,500.00 |
| 135 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.26 | $1,400.00 | $25,000 |
| 136 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.49 | $845.00 | $2,000.00 |
| 137 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.32 | $845.00 | $11,000 |
| 138 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 3,040 | $0.95 | $1.50 |
| 139 | Work zone channelizing line, class I, 12", 740.06, type I (614E23410) | FT | 982 | $0.95 | $5.50 |
| 140 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 822 | $0.95 | $1.50 |
| 141 | Work zone dotted line, class I, 6", 642 paint (614E24202) | FT | 674 | $0.80 | $2.50 |
| 142 | Work zone transverse/diagonal line, class I, 642 paint (614E25200) | FT | 350 | $4.15 | $11.00 |
| 143 | Work zone transverse/diagonal line, class I, 740.0 (614E25400) | FT | 1,000 | $4.15 | $14.00 |
| 144 | Work zone stop line, class I, 642 paint (614E26200) | FT | 383 | $3.90 | $8.00 |
| 145 | Work zone stop line, class III, 642 paint (614E26610) | FT | 55 | $3.75 | $8.00 |
| 146 | Work zone arrow, class I, 642 paint (614E30200) | EACH | 31 | $55.00 | $125.00 |
| 147 | Work zone arrow, class I, 740.06, type I (614E30400) | EACH | 2 | $55.00 | $350.00 |
| 148 | Business entrance sign, as per plan (614E40051) | EACH | 10 | $205.00 | $125.00 |
| 149 | Water (616E10000) | MGAL | 55 | $12.00 | $50.00 |
| 150 | Calcium chloride (616E20000) | TON | 0.10 | $1,250.00 | $1,500.00 |
| 151 | Special - work involving petroleum contaminated soil (690E65016) | TON | 5 | $295.00 | $500.00 |
| 152 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $25,465 | $25,000 |
| 153 | Maintaining traffic (614E11000) | LS | 1 | $34,542 | $215,000 |
| 154 | Field office, type B (619E16010) | MNTH | 12 | $1,650.00 | $2,000.00 |
| 155 | Construction layout stakes and surveying (623E10000) | LS | 1 | $12,850 | $30,000 |
| 156 | Mobilization (624E10000) | LS | 1 | $42,155 | $125,000 |
| 200 | Bracket arm, 6' (625E17950) | EACH | 8 | $985.00 | $800.00 |
| 201 | Atc controller, as per plan (809E69123) | EACH | 2 | $6,525.00 | $7,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.