ODOT contract 260090 bid tabulation
MOT-Trotwood Olive Rd Walks SA22 (SPOT SAFETY). Let by Ohio DOT on February 19, 2026, MOT. 5 bids received; low bid $828,511 by Performance Site Development, -8.6% against the engineer's estimate of $906,000.
- Owner
- Ohio DOT
- Letting
- 19 FEB 2026
- Pay items
- 110
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Performance Site Development | $828,511 | Low | -9.0% |
| 2 | Brumbaugh Construction Inc | $844,632 | +2.0% | -7.0% |
| 3 | Double Jay Construction Inc | $943,828 | +14% | +4.0% |
| 4 | Perram Electric Inc | $1,113,500 | +34% | +23% |
| 5 | Complete General Construction Company | $1,157,319 | +40% | +28% |
Engineer's estimate: $906,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Performance Site Development | 2. Brumbaugh Construction Inc | 3. Double Jay Construction Inc | 4. Perram Electric Inc | 5. Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $44,150 | $46,000 | $45,550 | $32,500 | $50,000 |
| 2 | Pavement removed (202E23000) | SY | 613 | $6.40 | $17.00 | $17.45 | $11.00 | $45.00 |
| 3 | Walk removed (202E30000) | SF | 925 | $4.00 | $4.00 | $1.80 | $5.00 | $6.50 |
| 4 | Curb removed (202E32000) | FT | 210 | $11.00 | $15.00 | $15.10 | $17.50 | $28.00 |
| 5 | Guardrail removed (202E38000) | FT | 330 | $6.35 | $7.00 | $6.60 | $2.40 | $2.50 |
| 6 | Fence removed (202E75000) | FT | 70 | $6.35 | $12.00 | $11.10 | $14.00 | $9.50 |
| 7 | Excavation (203E10000) | CY | 431 | $29.55 | $30.00 | $30.10 | $50.00 | $150.00 |
| 8 | Embankment (203E20000) | CY | 345 | $25.00 | $38.00 | $31.20 | $45.00 | $11.50 |
| 9 | Subgrade compaction (204E10000) | SY | 417 | $4.00 | $3.00 | $2.95 | $3.25 | $11.50 |
| 10 | Guardrail, type MGS with long posts (606E15100) | FT | 682.50 | $28.36 | $28.00 | $29.70 | $26.40 | $26.00 |
| 11 | Anchor assembly, MGS type T (606E26550) | EACH | 3 | $1,392.00 | $1,400.00 | $1,458.00 | $1,420.00 | $1,420.00 |
| 12 | 4" concrete walk, as per plan (608E10001) | SF | 7,940 | $8.85 | $9.00 | $7.85 | $8.00 | $12.30 |
| 13 | 6" concrete walk (608E13000) | SF | 180 | $12.25 | $12.00 | $9.90 | $11.50 | $21.50 |
| 14 | 8" concrete walk (608E15000) | SF | 460 | $12.95 | $14.00 | $11.85 | $11.50 | $30.00 |
| 15 | Curb ramp (608E52000) | SF | 1,195 | $22.25 | $23.00 | $18.00 | $26.00 | $13.50 |
| 16 | Detectable warning (608E53020) | SF | 80 | $29.00 | $56.00 | $53.00 | $33.00 | $8.75 |
| 17 | Topsoil (659E00300) | CY | 360 | $68.30 | $60.00 | $71.50 | $30.00 | $47.00 |
| 18 | Seeding and mulching, class 2 (659E00510) | SY | 3,235 | $2.40 | $1.00 | $2.50 | $2.50 | $1.75 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.45 | $800.00 | $1,400.00 | $840.00 | $750.00 | $1,500.00 |
| 20 | Water (659E35000) | MGAL | 18 | $31.75 | $5.00 | $33.00 | $100.00 | $1.00 |
| 21 | Slope erosion protection (670E00500) | SY | 2,680 | $4.75 | $2.25 | $4.95 | $2.25 | $1.95 |
| 22 | Erosion control (832E30000) | EACH | 30,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | Concrete masonry (602E20000) | CY | 3.46 | $995.00 | $3,200.00 | $3,380.00 | $2,100.00 | $3,050.00 |
| 24 | 12" conduit, type B (611E04400) | FT | 200 | $97.60 | $87.00 | $74.20 | $110.00 | $235.00 |
| 25 | 12" conduit, type C (611E04600) | FT | 25 | $89.20 | $85.00 | $70.45 | $135.00 | $180.00 |
| 26 | 18" conduit, type B (611E07400) | FT | 110 | $114.85 | $104.00 | $92.95 | $135.00 | $250.00 |
| 27 | Manhole, no. 3 (611E99574) | EACH | 1 | $3,220.00 | $3,300.00 | $4,496.00 | $3,700.00 | $4,700.00 |
| 28 | Manhole adjusted to grade (611E99654) | EACH | 1 | $1,750.00 | $325.00 | $1,903.00 | $600.00 | $1,550.00 |
| 29 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 249 | $42.25 | $19.00 | $19.90 | $50.00 | $50.00 |
| 30 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 71 | $241.55 | $490.00 | $512.60 | $575.00 | $575.00 |
| 31 | Aggregate base (304E20000) | CY | 71 | $86.15 | $95.00 | $99.00 | $145.00 | $180.00 |
| 32 | Non-tracking tack coat (407E20000) | GAL | 87 | $31.55 | $12.00 | $13.20 | $10.00 | $10.00 |
| 33 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 36 | $1,087.85 | $532.00 | $556.60 | $975.00 | $975.00 |
| 34 | Asphalt concrete surface course, 12.5 MM, type A (449) (driveways) (442E22120) | CY | 14 | $787.55 | $554.00 | $578.60 | $1,460.00 | $1,460.00 |
| 35 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 28 | $115.00 | $105.00 | $127.25 | $125.00 | $135.00 |
| 36 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 85 | $126.00 | $11.00 | $122.95 | $125.00 | $130.00 |
| 37 | Combination curb and gutter, type 2 (609E12000) | FT | 200 | $53.00 | $60.00 | $63.85 | $88.00 | $78.50 |
| 38 | Curb, type 6 (609E26000) | FT | 590 | $39.00 | $45.00 | $43.15 | $56.00 | $38.00 |
| 39 | Fire hydrant removed and reset, as per plan (638E10501) | EACH | 1 | $1,125.00 | $4,900.00 | $2,660.00 | $3,300.00 | $2,600.00 |
| 40 | Ground mounted support, no. 3 post (630E03100) | FT | 145.50 | $18.95 | $20.00 | $19.80 | $23.90 | $17.00 |
| 41 | Sign post reflector (630E08600) | EACH | 8 | $47.26 | $64.00 | $49.50 | $125.00 | $45.00 |
| 42 | Sign hanger assembly, span wire (630E79000) | EACH | 13 | $302.42 | $298.00 | $317.00 | $160.00 | $500.00 |
| 43 | Sign support assembly, pole mounted, as per plan (630E79501) | EACH | 14 | $241.55 | $373.00 | $253.00 | $135.00 | $395.00 |
| 44 | Sign, flat sheet (630E80100) | SF | 160.25 | $26.26 | $20.00 | $27.60 | $30.00 | $26.00 |
| 45 | Sign, double faced, street name (630E80500) | EACH | 4 | $120.76 | $271.00 | $126.50 | $275.00 | $210.00 |
| 46 | Removal of ground mounted sign and storage (630E85000) | EACH | 4 | $21.20 | $22.00 | $22.00 | $110.00 | $35.00 |
| 47 | Removal of ground mounted sign and reerection (630E85100) | EACH | 4 | $26.26 | $71.00 | $27.50 | $220.00 | $65.00 |
| 48 | Removal of ground mounted post support and storage (630E86006) | EACH | 5 | $31.55 | $30.00 | $33.00 | $110.00 | $50.00 |
| 49 | Removal of ground mounted post support and reerection (630E86010) | EACH | 2 | $36.76 | $122.00 | $38.50 | $220.00 | $125.00 |
| 50 | Edge line, 6" (644E00104) | MI | 0.07 | $11,191 | $11,200 | $11,725 | $8,755.00 | $10,658 |
| 51 | Center line (644E00300) | MI | 0.40 | $10,501 | $10,500 | $11,000 | $10,175 | $10,000 |
| 52 | Channelizing line, 12" (644E00404) | FT | 350 | $2.16 | $2.00 | $2.20 | $2.25 | $2.00 |
| 53 | Stop line (644E00500) | FT | 49 | $8.46 | $8.00 | $8.80 | $5.25 | $8.00 |
| 54 | Crosswalk line, 24" (644E00630) | FT | 290 | $8.45 | $8.00 | $8.80 | $5.20 | $8.00 |
| 55 | Transverse/diagonal line (644E00700) | FT | 155 | $8.45 | $8.00 | $8.80 | $5.00 | $8.00 |
| 56 | Chevron marking (644E00720) | FT | 115 | $8.45 | $8.00 | $8.80 | $5.00 | $8.00 |
| 57 | Lane arrow (644E01300) | EACH | 5 | $157.75 | $158.00 | $165.00 | $175.00 | $150.00 |
| 58 | Removal of pavement marking (644E30000) | FT | 460 | $5.50 | $5.25 | $5.50 | $5.05 | $5.00 |
| 59 | Removal of pavement marking (644E30020) | EACH | 2 | $157.75 | $158.00 | $165.00 | $400.00 | $150.00 |
| 60 | Connection, fused pull apart (625E00450) | EACH | 2 | $89.26 | $89.00 | $203.35 | $175.00 | $150.00 |
| 61 | Connection, unfused pull apart (625E00460) | EACH | 2 | $72.46 | $73.00 | $201.35 | $170.00 | $150.00 |
| 62 | Bracket arm, 20' (625E18400) | EACH | 2 | $1,121.85 | $1,125.00 | $1,372.00 | $1,010.00 | $2,000.00 |
| 63 | No. 10 AWG 600 volt distribution cable (625E23306) | FT | 1,320 | $0.80 | $0.80 | $2.55 | $3.15 | $2.00 |
| 64 | No. 10 AWG pole and bracket cable (625E23400) | FT | 360 | $0.63 | $0.60 | $2.50 | $1.10 | $3.25 |
| 65 | Conduit, 2", 725.051 (625E25408) | FT | 780 | $1.25 | $1.25 | $6.70 | $12.90 | $11.25 |
| 66 | Conduit, jacked or drilled, 725.04, 4" (625E25902) | FT | 49 | $57.76 | $58.00 | $178.85 | $152.00 | $100.00 |
| 67 | Luminaire, conventional, solid state (LED), type I (625E26252) | EACH | 2 | $623.75 | $626.00 | $680.00 | $660.00 | $500.00 |
| 68 | Trench (625E29000) | FT | 780 | $17.35 | $17.00 | $14.05 | $14.00 | $12.00 |
| 69 | Pull box, 725.08, 18" (625E30700) | EACH | 2 | $866.26 | $868.00 | $1,067.00 | $2,050.00 | $1,300.00 |
| 70 | Pull box removed (625E31510) | EACH | 7 | $787.55 | $789.00 | $437.00 | $250.00 | $450.00 |
| 71 | Ground rod (625E32000) | EACH | 11 | $141.76 | $142.00 | $286.00 | $350.00 | $290.00 |
| 72 | Underground warning marking tape (625E36010) | FT | 780 | $1.45 | $1.40 | $1.75 | $1.30 | $3.00 |
| 73 | Sign lighting misc.: warning sign flasher assembly (631E97700) | EACH | 2 | $7,855.90 | $7,875.00 | $1,615.00 | $1,805.00 | $1,500.00 |
| 74 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006) | EACH | 10 | $753.60 | $755.00 | $1,252.00 | $970.00 | $1,150.00 |
| 75 | Vehicular signal head, (LED), 4-section, 12" lens, 1-way, polycarbonate (632E05064) | EACH | 4 | $1,023.76 | $1,026.00 | $1,426.00 | $1,070.00 | $1,300.00 |
| 76 | Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086) | EACH | 1 | $1,407.65 | $1,400.00 | $1,997.00 | $1,635.00 | $1,900.00 |
| 77 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 8 | $455.05 | $455.00 | $813.00 | $568.00 | $800.00 |
| 78 | Accessible pedestrian pushbutton, as per plan (632E20751) | EACH | 8 | $1,414.78 | $1,420.00 | $1,242.00 | $1,300.00 | $1,250.00 |
| 79 | Covering of vehicular signal head (632E25000) | EACH | 14 | $47.26 | $47.00 | $93.80 | $10.00 | $38.00 |
| 80 | Covering of pedestrian signal head (632E25010) | EACH | 8 | $47.26 | $47.00 | $93.80 | $5.00 | $32.00 |
| 81 | Messenger wire, 7 strand, 3/8" diameter with accessories (632E30200) | FT | 410 | $9.90 | $10.00 | $13.60 | $14.65 | $20.00 |
| 82 | Signal cable, 3 conductor, no. 14 AWG (632E40300) | FT | 200 | $0.72 | $0.75 | $2.50 | $3.35 | $2.50 |
| 83 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 3,200 | $1.15 | $1.15 | $3.05 | $3.57 | $3.00 |
| 84 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 2,120 | $1.50 | $1.50 | $3.70 | $3.90 | $3.75 |
| 85 | Strain pole foundation (632E64000) | EACH | 3 | $2,362.55 | $2,400.00 | $7,773.00 | $10,555 | $9,000.00 |
| 86 | Pedestal foundation (632E64020) | EACH | 8 | $787.55 | $790.00 | $1,312.00 | $1,610.00 | $1,500.00 |
| 87 | Power cable, 3 conductor, no. 8 AWG (632E67300) | FT | 60 | $2.95 | $2.90 | $4.05 | $6.25 | $5.00 |
| 88 | Strain pole, type TC-81.11, design 10 (632E86130) | EACH | 1 | $13,908 | $13,950 | $13,408 | $12,740 | $12,000 |
| 89 | Combination strain pole, type TC-81.11, design 10 (632E87130) | EACH | 1 | $14,717 | $14,750 | $14,101 | $13,285 | $12,000 |
| 90 | Combination strain pole, type TC-81.11, design 12 (632E87140) | EACH | 1 | $16,270 | $16,300 | $15,431 | $14,340 | $14,000 |
| 91 | Pedestal, 5', transformer base (632E89802) | EACH | 1 | $497.70 | $500.00 | $938.00 | $1,010.00 | $1,000.00 |
| 92 | Pedestal, 10', transformer base (632E89904) | EACH | 5 | $611.50 | $613.00 | $1,147.00 | $1,090.00 | $1,000.00 |
| 93 | Pedestal, 15', transformer base (632E90008) | EACH | 2 | $796.30 | $800.00 | $2,780.00 | $1,220.00 | $2,000.00 |
| 94 | Removal of traffic signal installation (632E90100) | EACH | 1 | $6,300.05 | $6,300.00 | $7,458.00 | $7,040.00 | $6,000.00 |
| 95 | Reuse of traffic control item: pull box (632E90104) | EACH | 1 | $787.60 | $790.00 | $746.00 | $490.00 | $275.00 |
| 96 | Reuse of strain pole (632E90208) | EACH | 1 | $787.60 | $790.00 | $1,645.00 | $2,420.00 | $825.00 |
| 97 | Cabinet, type TS-2, as per plan (633E65511) | EACH | 1 | $16,275 | $16,300 | $24,723 | $22,385 | $20,000 |
| 98 | Advance radar detection, as per plan (809E69001) | EACH | 2 | $10,734 | $10,750 | $10,794 | $10,150 | $9,300.00 |
| 99 | Stop line radar detection, as per plan (809E69101) | EACH | 4 | $10,308 | $10,300 | $10,415 | $10,075 | $9,000.00 |
| 100 | Atc controller, as per plan (809E69123) | EACH | 1 | $6,825.50 | $6,840.00 | $6,542.00 | $7,385.00 | $5,500.00 |
| 101 | Emergency vehicle preemption (809E69200) | EACH | 1 | $995.35 | $1,000.00 | $1,880.00 | $850.00 | $1,200.00 |
| 102 | Preempt receiving unit (809E69210) | EACH | 1 | $3,334.00 | $3,350.00 | $3,091.00 | $805.00 | $800.00 |
| 103 | Preempt detector cable (809E69220) | FT | 700 | $1.60 | $1.50 | $4.00 | $3.95 | $5.00 |
| 104 | Preempt phase selector (809E69230) | EACH | 1 | $5,452.90 | $5,470.00 | $1,480.00 | $2,455.00 | $6,000.00 |
| 105 | Preempt confirmation light (809E69240) | EACH | 1 | $1,143.60 | $1,150.00 | $1,143.00 | $2,855.00 | $750.00 |
| 106 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 25 | $89.30 | $100.00 | $99.00 | $120.00 | $100.00 |
| 107 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $17,025 | $7,010.00 | $7,202.00 | $20,059 | $7,000.00 |
| 108 | Maintaining traffic (614E11000) | LS | 1 | $18,995 | $40,000 | $77,452 | $189,008 | $70,000 |
| 109 | Construction layout stakes and surveying (623E10000) | LS | 1 | $19,995 | $15,000 | $9,878.00 | $8,000.00 | $10,000 |
| 110 | Mobilization (624E10000) | LS | 1 | $17,950 | $33,000 | $37,510 | $40,000 | $87,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 19, 2026. Compiled by Mirage Metrics.