TDOT contract CN264023 bid tabulation

The resurfacing on s.r. 54 from cane creek (l.m. 6.21) to s.r. 22 (l.m. 10.74). Let by Tennessee DOT on March 20, 2026, Weakley County. 2 bids received; low bid $2,397,873 by Ford Construction Company.

Owner
Tennessee DOT
Letting
20 MAR 2026
Pay items
40
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ford Construction Company$2,397,873Low
2Murray Paving, Inc.$2,589,481+8.0%
TDOT contract CN264023: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ford Construction Company2. Murray Paving, Inc.
1Removal of rigid pavement, sidewalk, etc. (202-03)SY3$125.00$360.00
2Removal of asphalt pavement (202-03.01)SY200$35.00$30.00
3Removal of curb and gutter (curb ramp) (202-08.15)LF23$15.35$160.00
4Water (203-06)MG8$1.00$1.00
5Brooming & degrassing shoulders (208-01.05)LM9$1,100.00$1,250.00
6Mineral aggregate, type B base, grading (D) (303-02)TON1,310$33.00$49.85
7Asphalt concrete mix (PG64-22) (BPMB-HM) grading A (307-01.01)TON92$160.00$165.00
8Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08)TON8,657$105.00$107.50
9Trackless tack coat (403-02.01)TON63$800.00$945.00
10Acs mix(PG64-22) grading D (411-01.10)TON5,360$123.00$124.85
11Longitudinal joint sealant (411-01.21)LM4.50$3,000.00$3,000.00
12Scoring for rumble stripe (non-continuous) (4IN width) (411-12.04)LM5.30$1,720.00$1,720.00
13Cold planing bituminous pavement (415-01.01)TON13,332$22.50$29.50
14Concrete sidewalk (4 ") (701-01.01)SF21$76.00$25.00
15Concrete curb ramp (retrofit) (701-02.01)SF100$76.00$45.00
16Concrete curb (702-01)CY1.30$2,200.00$725.00
17Concrete combined curb & gutter (702-03)CY1.30$2,200.00$725.00
18Guardrail transition 27IN to 31IN (705-02.10)EACH9$100.00$100.00
19GR terminal (energy absorbing) MASH TL-2 (705-06.30)EACH9$3,350.00$3,400.00
20Guardrail removed (706-01)LF450$2.00$4.00
21Traffic control (712-01)LS1$24,000$1.00
22Flexible drums (channelizing) (712-04.01)EACH40$1.00$38.00
23Signs (construction) (712-06)SF1,480$5.75$6.50
24Snowplowable raised pavement markers (BI-dir) (1 color) (716-01.21)EACH348$48.00$48.00
25Snowplowable raised pavment markers (mono-dir)(1 color) (716-01.22)EACH32$48.00$48.00
26Removal of snowplowable reflective marker (716-01.30)EACH180$7.00$25.00
27Plastic pavement marking (stop line) (716-02.05)LF280$30.00$30.00
28Plastic pavement marking (turn lane arrow) (716-02.06)EACH14$250.00$250.00
29Plastic pavement marking (8" dotted line) (716-02.08)LF70$4.00$4.00
30Plastic pavement marking (8IN line) (716-02.12)LM0.10$21,120$21,120
31Plastic pavement marking (transverse shoulder) (716-04.04)LF1,000$16.00$16.00
32Plastic pavement marking (straight arrow) (716-04.05)EACH5$250.00$250.00
33Painted pavement marking (stop line) (716-05.05)LF280$18.00$18.00
34Painted pavement marking (6" line) (716-05.20)LM32$2,200.00$2,200.00
35Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02)LM16$7,900.00$7,900.00
36Mobilization (717-01)LS1$40,000$95,500
37Conduit 1" diameter (PVC schedule 40) (730-12.01)LF50$10.00$10.00
38Shielded detector cable (730-14.01)LF50$3.00$3.00
39Saw slot (730-14.02)LF956$6.00$6.00
40Loop wire (730-14.03)LF2,352$1.00$1.00
TDOT contract CN264023: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of March 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy