TDOT contract CNZ265 bid tabulation
The resurfacing on i-240 from near s. perkins road (l.m. 12.71) to near park avenue (l.m. 15.00). Let by Tennessee DOT on October 3, 2025, Shelby County. 3 bids received; low bid $3,436,910 by APAC-Tennessee, Inc..
- Owner
- Tennessee DOT
- Letting
- 03 OCT 2025
- Pay items
- 47
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | APAC-Tennessee, Inc. | $3,436,910 | Low |
| 2 | Lehman-Roberts Company | $3,763,868 | +10% |
| 3 | Standard Construction Company, Inc. | $4,020,663 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. APAC-Tennessee, Inc. | 2. Lehman-Roberts Company | 3. Standard Construction Company, Inc. |
|---|---|---|---|---|---|---|
| 1 | Removal of asphalt pavement (202-03.01) | SY | 200 | $63.00 | $63.91 | $75.00 |
| 2 | Water (203-06) | MG | 3 | $350.00 | $18.87 | $25.00 |
| 3 | Brooming & degrassing shoulders (208-01.05) | LM | 9.20 | $1,700.00 | $1,544.14 | $2,750.00 |
| 4 | Mineral aggregate, type B base, grading (C or D) (303-02) | TON | 298 | $86.00 | $85.01 | $70.00 |
| 5 | Asphalt concrete mix (PG76-22) (BPMB-HM) grading A (307-03.01) | TON | 92 | $275.00 | $236.66 | $315.00 |
| 6 | Trackless tack coat (403-02.01) | TON | 91 | $654.00 | $1,196.10 | $1,250.00 |
| 7 | Acs mix (PG64-22) grading E shoulder (411-01.07) | TON | 4,254 | $132.50 | $130.31 | $139.50 |
| 8 | Longitudinal joint sealant (411-01.21) | LM | 22.10 | $1,900.00 | $3,225.07 | $3,360.00 |
| 9 | Acs mix(PG76-22) grading D (411-03.10) | TON | 9,225 | $154.50 | $143.83 | $148.75 |
| 10 | Scoring shoulders (continuous) (16IN width) (411-12.01) | LM | 9.20 | $2,700.00 | $3,092.19 | $997.50 |
| 11 | Cold planing bituminous pavement (415-01.01) | TON | 13,452 | $14.75 | $31.80 | $37.70 |
| 12 | Full depth PCC pavement repair high early (502-03.25) | CY | 25 | $1,005.00 | $3,375.42 | $1,039.50 |
| 13 | Sawing concrete pavement (full depth) (502-04.01) | LF | 240 | $28.00 | $55.40 | $28.90 |
| 14 | Load transfer dowels (502-04.02) | EACH | 168 | $23.00 | $99.75 | $23.65 |
| 15 | Transverse tie-bars (502-04.03) | EACH | 28 | $22.00 | $92.71 | $22.55 |
| 16 | Sawing & resealing joints (silicone sealant) (502-08.10) | LF | 204 | $12.00 | $25.70 | $12.10 |
| 17 | Traffic control (712-01) | LS | 1 | $185,000 | $245,000 | $310,000 |
| 18 | Flexible drums (channelizing) (712-04.01) | EACH | 616 | $40.60 | $40.72 | $39.90 |
| 19 | Warning lights (type C) (712-05.03) | EACH | 154 | $16.24 | $16.29 | $1.05 |
| 20 | Signs (construction) (712-06) | SF | 2,118 | $10.15 | $10.18 | $6.25 |
| 21 | Signs (construction)(reduced speed warning) (712-06.16) | EACH | 4 | $502.43 | $503.87 | $577.50 |
| 22 | Temporary barricades (type III) (712-07.03) | LF | 24 | $25.38 | $25.45 | $15.75 |
| 23 | Arrow board (type C) (712-08.03) | EACH | 4 | $1,522.50 | $1,526.87 | $997.50 |
| 24 | Speed feedback sign assembly (712-08.08) | EACH | 2 | $4,567.50 | $4,580.60 | $4,200.00 |
| 25 | Digital speed limit sign assembly (712-08.09) | EACH | 2 | $7,105.00 | $7,125.38 | $3,990.00 |
| 26 | Queue protection truck (712-08.12) | DAY | 75 | $812.00 | $814.33 | $1,102.50 |
| 27 | Changeable message sign unit (713-16.01) | EACH | 4 | $5,070.00 | $5,084.47 | $4,725.00 |
| 28 | Snowplowable raised pavement markers (BI-dir)(2 color) (716-01.23) | EACH | 1,292 | $50.50 | $50.39 | $51.50 |
| 29 | Removal of snowplowable reflective marker (716-01.30) | EACH | 829 | $12.00 | $15.71 | $21.00 |
| 30 | Plastic pavement marking (cross-walk) (716-02.03) | LF | 154 | $30.30 | $30.24 | $30.90 |
| 31 | Plastic pavement marking (turn lane arrow) (716-02.06) | EACH | 2 | $353.50 | $352.74 | $360.50 |
| 32 | Plastic pavement marking (24" barrier line) (716-02.07) | LF | 2,830 | $30.30 | $30.24 | $30.90 |
| 33 | Plastic word pavement marking (only) (716-03.01) | EACH | 2 | $505.00 | $503.92 | $515.00 |
| 34 | Plastic pavement marking (straight-turn arrow) (716-04.01) | EACH | 9 | $505.00 | $503.92 | $515.00 |
| 35 | Plastic pavement marking (exit only arrow) (716-04.07) | EACH | 9 | $454.50 | $453.53 | $463.50 |
| 36 | Plastic pavement marking (lane reduction arrow) (716-04.14) | EACH | 4 | $505.00 | $503.92 | $515.00 |
| 37 | Painted pavement marking (6" line) (716-05.20) | LM | 12 | $3,636.00 | $3,628.20 | $3,708.00 |
| 38 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 13.40 | $9,191.00 | $9,171.29 | $9,373.00 |
| 39 | Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03) | LF | 1,212 | $4.14 | $4.13 | $4.20 |
| 40 | Enhanced flatline thermo PVMT MRKNG (6IN dotted line) (716-12.05) | LF | 669 | $4.14 | $4.13 | $4.20 |
| 41 | Enhanced flat line thermo (8IN line) (716-12.06) | LF | 6,466 | $4.14 | $4.13 | $4.20 |
| 42 | Enhanced flat line thermo (12IN line) (716-12.09) | LF | 1,627 | $15.15 | $15.12 | $15.45 |
| 43 | Enhanced flat line thermo (12IN dotted) (716-12.10) | LF | 1,348 | $15.15 | $15.12 | $15.45 |
| 44 | Mobilization (717-01) | LS | 1 | $220,000 | $195,000 | $295,000 |
| 45 | Conduit 2" diameter (PVC schedule 40) (730-12.02) | LF | 165 | $30.60 | $30.24 | $31.50 |
| 46 | Saw slot (730-14.02) | LF | 675 | $8.16 | $20.16 | $8.40 |
| 47 | Loop wire (730-14.03) | LF | 1,000 | $2.04 | $2.02 | $2.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.