TxDOT contract A00061098 bid tabulation
Bridge Replacement, COUNTY ROAD 454 (CR 454 @ Bosque River to .). Let by Texas DOT on June 5, 2025, Erath, Fort Worth District. 9 bids received; low bid $866,897 by STX Civil, -18% against the engineer's estimate of $1,055,744.
- Owner
- Texas DOT
- Letting
- 05 JUN 2025
- Pay items
- 45
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | STX Civil | $866,897 | Low | -18% |
| 2 | Hodges and Son Construction Company, Inc. | $930,246 | +7.0% | -12% |
| 3 | Talbert Companies LLC | $990,346 | +14% | -6.0% |
| 4 | Knife River Corporation - South | $1,034,057 | +19% | -2.0% |
| 5 | Coppell Construction Co., Inc. | $1,063,681 | +23% | +1.0% |
| 6 | Scott Tucker Construction Company, LLC | $1,101,907 | +27% | +4.0% |
| 7 | C. E. Barker, LTD. | $1,126,215 | +30% | +7.0% |
| 8 | Texas Steel Industrial Placing, LLC | $1,136,752 | +31% | +8.0% |
| 9 | Urban Infraconstruction LLC | $1,300,000 | +50% | +23% |
Engineer's estimate: $1,055,744.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. STX Civil | 2. Hodges and Son Construction Company, Inc. | 3. Talbert Companies LLC | 4. Knife River Corporation - South | 5. Coppell Construction Co., Inc. | 6. Scott Tucker Construction Company, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 3.17 | $5,000.00 | $1,800.00 | $12,000 | $4,005.75 | $15,000 | $15,000 | $11,413 |
| 2 | Remove (8"-14") TRT/untrt base & asphalt pavement (105-7059) | SY | 548 | $18.00 | $12.00 | $10.00 | $16.33 | $16.00 | $20.00 | $24.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 671 | $30.00 | $30.00 | $30.00 | $42.18 | $50.00 | $42.00 | $73.00 |
| 4 | Embankment (final)(DC)(type B) (132-7004) | CY | 52 | $60.00 | $40.00 | $50.00 | $72.81 | $50.00 | $82.00 | $128.00 |
| 5 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 168 | $2.50 | $1.00 | $15.00 | $8.18 | $11.00 | $16.00 | $9.00 |
| 6 | Broadcast seed (temporary_warm) (164-7005) | SY | 84 | $2.50 | $1.00 | $1.00 | $6.54 | $22.00 | $28.00 | $8.00 |
| 7 | Broadcast seed (temporary_cool) (164-7006) | SY | 84 | $2.50 | $1.00 | $1.00 | $6.54 | $22.00 | $28.00 | $8.00 |
| 8 | Vegetative watering (168-7001) | TGL | 25 | $100.00 | $50.00 | $1.00 | $49.05 | $75.00 | $50.00 | $415.00 |
| 9 | Proof rolling (216-7001) | HR | 4 | $100.00 | $120.00 | $20.00 | $126.61 | $85.00 | $150.00 | $349.00 |
| 10 | FL BS (compacted in place)(type A GR 1-2) (10") (247-7090) | SY | 559 | $90.00 | $180.00 | $75.00 | $40.18 | $53.00 | $48.00 | $34.00 |
| 11 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 10 | $330.00 | $650.00 | $400.00 | $514.14 | $350.00 | $500.00 | $403.00 |
| 12 | Lime TRT (existing material)(8") (260-7007) | SY | 559 | $14.00 | $12.00 | $35.00 | $14.58 | $20.00 | $20.00 | $86.00 |
| 13 | Prime coat (AE-P) (310-7001) | GAL | 168 | $7.00 | $12.00 | $25.00 | $21.80 | $16.00 | $20.00 | $34.00 |
| 14 | SP mixes SP-C sac-A PG70-28 (344-7024) | TON | 97 | $300.00 | $450.00 | $250.00 | $429.46 | $400.00 | $394.00 | $418.00 |
| 15 | Cem stabil BKFL (400-7010) | CY | 81 | $290.00 | $220.00 | $300.00 | $305.20 | $380.00 | $300.00 | $294.00 |
| 16 | Drilled shaft (36 in) (416-7006) | LF | 256 | $500.00 | $380.00 | $275.00 | $272.50 | $400.00 | $360.00 | $414.00 |
| 17 | Class C concrete (abutment)(HPC) (420-7013) | CY | 36.40 | $2,000.00 | $1,100.00 | $1,800.00 | $1,853.00 | $2,500.00 | $1,500.00 | $1,143.00 |
| 18 | Reinforced concrete slab (HPC) (422-7002) | SF | 1,920 | $40.00 | $28.00 | $45.00 | $34.88 | $50.00 | $48.00 | $51.00 |
| 19 | Approach slab (HPC) (422-7014) | CY | 48.50 | $965.00 | $850.00 | $1,000.00 | $872.00 | $850.00 | $900.00 | $1,044.00 |
| 20 | Prestressed concrete girder (TX28) (425-7001) | LF | 238 | $325.00 | $450.00 | $285.00 | $213.23 | $400.00 | $340.00 | $480.00 |
| 21 | Riprap (mow strip)(4 in) (432-7013) | CY | 21 | $800.00 | $650.00 | $750.00 | $815.90 | $1,000.00 | $900.00 | $1,210.00 |
| 22 | Riprap (stone protection)(24 in) (432-7045) | CY | 468 | $300.00 | $250.00 | $200.00 | $218.00 | $150.00 | $255.00 | $234.00 |
| 23 | Rail (type T631) (450-7020) | LF | 152 | $125.00 | $160.00 | $90.00 | $137.00 | $140.00 | $100.00 | $136.00 |
| 24 | Armor joint (sealed) (454-7003) | LF | 56 | $225.00 | $120.00 | $200.00 | $228.90 | $150.00 | $145.00 | $99.00 |
| 25 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $60,000 | $16,500 | $80,000 | $10,900 | $40,000 | $80,000 | $54,354 |
| 26 | Mobilization (500-7001) | LS | 1 | $95,980 | $68,000 | $80,000 | $206,700 | $100,000 | $100,000 | $110,178 |
| 27 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $10,000 | $2,800.00 | $6,000.00 | $10,900 | $3,000.00 | $13,000 | $3,054.00 |
| 28 | Portable changeable message sign (503-7002) | EACH | 2 | $15,000 | $5,000.00 | $15,000 | $17,440 | $25,000 | $10,000 | $11,164 |
| 29 | Rock filter dams (install) (type 2) (506-7002) | LF | 61 | $60.00 | $40.00 | $1.00 | $41.42 | $75.00 | $66.00 | $50.00 |
| 30 | Rock filter dams (remove) (506-7011) | LF | 61 | $20.00 | $10.00 | $1.00 | $21.80 | $20.00 | $50.00 | $29.00 |
| 31 | Temporary sediment control fence (install) (506-7039) | LF | 411 | $6.50 | $5.00 | $1.00 | $4.91 | $18.00 | $7.50 | $7.00 |
| 32 | Temporary sediment control fence (remove) (506-7041) | LF | 411 | $3.00 | $1.00 | $1.00 | $2.37 | $3.00 | $3.20 | $3.00 |
| 33 | Metal W-beam guard fence (steel post) (540-7002) | LF | 186 | $35.00 | $60.00 | $30.00 | $38.54 | $40.00 | $29.00 | $48.00 |
| 34 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $2,800.00 | $3,200.00 | $3,191.52 | $3,700.00 | $3,200.00 | $3,504.00 |
| 35 | Wire fence (type C) (552-7003) | LF | 249 | $55.00 | $25.00 | $25.00 | $40.88 | $40.00 | $30.00 | $47.00 |
| 36 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 2 | $1,000.00 | $450.00 | $1,500.00 | $872.00 | $1,100.00 | $999.00 | $1,033.00 |
| 37 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $200.00 | $1.00 | $50.00 | $109.00 | $100.00 | $130.00 | $241.00 |
| 38 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 6 | $45.00 | $300.00 | $30.00 | $37.01 | $55.00 | $25.00 | $73.00 |
| 39 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 549 | $1.20 | $1.25 | $5.00 | $5.45 | $4.70 | $4.00 | $5.00 |
| 40 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 604 | $0.90 | $1.25 | $5.00 | $5.45 | $4.70 | $4.00 | $5.00 |
| 41 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 549 | $3.25 | $1.60 | $5.00 | $7.63 | $4.70 | $4.00 | $5.00 |
| 42 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 604 | $2.70 | $1.60 | $5.00 | $7.63 | $4.70 | $4.00 | $5.00 |
| 43 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 8 | $17.00 | $8.00 | $50.00 | $43.60 | $60.00 | $50.00 | $50.00 |
| 44 | Pavement surface preparation for marking (6") (678-7002) | LF | 240 | $1.25 | $1.00 | $2.00 | $6.54 | $1.15 | $1.00 | $2.00 |
| 45 | Post and cable fence (removal) (772-7001) | LF | 237 | $2.50 | $1.00 | $12.00 | $10.85 | $6.75 | $9.00 | $23.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.