TxDOT contract A00065079 bid tabulation
Bridge Replacement, COUNTY ROAD 351 (CR 351 @ BELL BRANCH to .). Let by Texas DOT on February 5, 2026, Erath, Fort Worth District. 12 bids received; low bid $625,625 by Delgado'S Contractors, LLC, -14% against the engineer's estimate of $731,019.
- Owner
- Texas DOT
- Letting
- 05 FEB 2026
- Pay items
- 51
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Delgado'S Contractors, LLC | $625,625 | Low | -14% |
| 2 | Tucan Contracting, LLC | $633,890 | +1.0% | -13% |
| 3 | Hodges and Son Construction Company, Inc. | $635,574 | +2.0% | -13% |
| 4 | Texas Steel Industrial Placing, LLC | $676,941 | +8.0% | -7.0% |
| 5 | Skyline Bridge LLC | $690,708 | +10% | -6.0% |
| 6 | STX Civil | $695,420 | +11% | -5.0% |
| 7 | THK Construction LLC | $696,560 | +11% | -5.0% |
| 8 | Knife River Corporation - South | $751,136 | +20% | +3.0% |
| 9 | Garret Shields Infrastructure | $765,613 | +22% | +5.0% |
| 10 | Scott Tucker Construction Company, LLC | $817,571 | +31% | +12% |
| 11 | Coppell Construction Co., Inc. | $875,581 | +40% | +20% |
| 12 | Castillo Aranda LLC | $938,482 | +50% | +28% |
Engineer's estimate: $731,019.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Delgado'S Contractors, LLC | 2. Tucan Contracting, LLC | 3. Hodges and Son Construction Company, Inc. | 4. Texas Steel Industrial Placing, LLC | 5. Skyline Bridge LLC | 6. STX Civil |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 4 | $5,000.00 | $1,500.00 | $412.50 | $4,000.00 | $2,000.00 | $4,400.00 | $3,500.00 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 5 | $400.00 | $500.00 | $1,177.00 | $1,000.00 | $1,900.00 | $800.00 | $2,000.00 |
| 3 | Excavation (roadway & channel) (110-7004) | CY | 593 | $30.00 | $40.00 | $33.00 | $15.00 | $20.00 | $18.00 | $10.00 |
| 4 | Embankment (final)(DC)(type B) (132-7004) | CY | 281 | $50.00 | $40.00 | $44.00 | $25.00 | $25.00 | $50.00 | $25.00 |
| 5 | Compost manuf topsoil (4") (161-7002) | SY | 696 | $3.00 | $7.00 | $5.50 | $4.50 | $5.00 | $5.00 | $5.00 |
| 6 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 696 | $1.00 | $1.00 | $2.75 | $3.00 | $3.00 | $2.00 | $0.25 |
| 7 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 696 | $1.00 | $0.90 | $1.10 | $2.00 | $3.00 | $2.00 | $0.25 |
| 8 | Vegetative watering (168-7001) | TGL | 49 | $26.00 | $50.00 | $55.00 | $1.00 | $1.00 | $1.00 | $100.00 |
| 9 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 786 | $28.00 | $27.00 | $27.50 | $35.00 | $30.00 | $50.00 | $60.00 |
| 10 | Asphalt (RC-250) (316-7016) | GAL | 236 | $30.00 | $20.00 | $57.20 | $25.00 | $20.00 | $60.00 | $8.00 |
| 11 | Aggregate (type-B, GR-5)(sac-B) (316-7175) | CY | 7 | $135.00 | $1,250.00 | $3,448.50 | $1,700.00 | $1,000.00 | $2,450.00 | $1,000.00 |
| 12 | SP mixes SP-C sac-B PG70-22 (exempt) (344-7038) | TON | 82 | $200.00 | $350.00 | $503.80 | $300.00 | $20.00 | $425.00 | $250.00 |
| 13 | Tack coat (344-7077) | GAL | 157 | $10.00 | $10.00 | $22.00 | $8.00 | $20.00 | $5.00 | $7.00 |
| 14 | Cem stabil BKFL (400-7010) | CY | 92 | $300.00 | $275.00 | $242.00 | $275.00 | $250.00 | $285.00 | $145.00 |
| 15 | Drilled shaft (36 in) (416-7006) | LF | 216 | $320.00 | $255.00 | $275.00 | $260.00 | $400.00 | $215.00 | $400.00 |
| 16 | Class C concrete (abutment)(HPC) (420-7013) | CY | 36.90 | $1,580.00 | $1,250.00 | $1,100.00 | $1,400.00 | $1,200.00 | $1,300.00 | $930.00 |
| 17 | Reinforced concrete slab (HPC) (422-7002) | SF | 1,560 | $32.00 | $30.00 | $27.50 | $30.00 | $25.00 | $31.00 | $30.00 |
| 18 | Approach slab (422-7013) | CY | 44.70 | $900.00 | $900.00 | $880.00 | $850.00 | $600.00 | $850.00 | $850.00 |
| 19 | Prestressed concrete girder (TX28) (425-7001) | LF | 237.93 | $300.00 | $280.00 | $211.20 | $280.00 | $400.00 | $300.00 | $470.00 |
| 20 | Riprap (mow strip)(4 in) (432-7013) | CY | 23.50 | $725.00 | $650.00 | $715.00 | $750.00 | $600.00 | $750.00 | $700.00 |
| 21 | Riprap (stone protection)(24 in) (432-7045) | CY | 184 | $190.00 | $245.00 | $187.00 | $200.00 | $160.00 | $190.00 | $175.00 |
| 22 | Rail (type SSTR)(HPC) (450-7025) | LF | 168 | $125.00 | $140.00 | $165.00 | $150.00 | $140.00 | $160.00 | $165.00 |
| 23 | Armor joint (sealed) (454-7003) | LF | 46 | $175.00 | $175.00 | $110.00 | $175.00 | $125.00 | $200.00 | $170.00 |
| 24 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $35,000 | $19,000 | $11,000 | $22,000 | $30,000 | $12,500 | $25,000 |
| 25 | Mobilization (500-7001) | LS | 1 | $61,911 | $44,000 | $65,000 | $55,000 | $67,633 | $65,000 | $50,000 |
| 26 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $10,000 | $1,250.00 | $1,100.00 | $2,000.00 | $1,000.00 | $3,100.00 | $1,850.00 |
| 27 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $8,000.00 | $7,700.00 | $11,000 | $20,000 | $8,000.00 | $6,400.00 |
| 28 | Rock filter dams (install) (type 1) (506-7001) | LF | 22 | $50.00 | $35.00 | $84.70 | $1.00 | $50.00 | $50.00 | $40.00 |
| 29 | Rock filter dams (remove) (506-7011) | LF | 22 | $20.00 | $5.00 | $27.50 | $1.00 | $10.00 | $10.00 | $1.00 |
| 30 | Construction exits (install) (type 1) (506-7020) | SY | 78 | $40.00 | $25.00 | $33.00 | $1.00 | $50.00 | $10.00 | $50.00 |
| 31 | Construction exits (remove) (506-7024) | SY | 78 | $15.00 | $5.00 | $15.40 | $1.00 | $10.00 | $1.00 | $10.00 |
| 32 | Temporary sediment control fence (install) (506-7039) | LF | 118 | $5.00 | $5.95 | $5.50 | $1.00 | $5.00 | $4.00 | $5.00 |
| 33 | Temporary sediment control fence (remove) (506-7041) | LF | 118 | $1.00 | $0.90 | $1.65 | $1.00 | $1.00 | $1.00 | $1.00 |
| 34 | Metal W-beam guard fence (timber post) (540-7001) | LF | 125 | $28.00 | $30.00 | $24.75 | $26.00 | $25.00 | $24.00 | $35.00 |
| 35 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 2 | $1,400.00 | $1,251.45 | $1,320.00 | $1,500.00 | $1,250.00 | $1,500.00 | $1,450.00 |
| 36 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,335.00 | $1,350.00 | $1,320.00 | $1,500.00 | $2,500.00 | $1,500.00 | $1,335.00 |
| 37 | Metal beam guard fence trans (non - sym) (540-7016) | EACH | 2 | $970.00 | $850.00 | $715.00 | $800.00 | $700.00 | $800.00 | $850.00 |
| 38 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,200.00 | $3,300.00 | $3,245.00 | $3,050.00 | $3,000.00 | $3,300.00 | $3,500.00 |
| 39 | Wire fence (remove) (552-7011) | LF | 77 | $15.00 | $5.00 | $4.40 | $5.00 | $5.00 | $10.00 | $1.00 |
| 40 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 4 | $900.00 | $1,000.00 | $440.00 | $950.00 | $800.00 | $1,250.00 | $800.00 |
| 41 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $175.00 | $250.00 | $82.50 | $50.00 | $500.00 | $200.00 | $100.00 |
| 42 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 6 | $33.00 | $30.00 | $22.00 | $20.00 | $45.00 | $35.00 | $25.00 |
| 43 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016) | EACH | 8 | $23.00 | $30.00 | $22.00 | $25.00 | $45.00 | $75.00 | $25.00 |
| 44 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 4 | $75.00 | $50.00 | $71.50 | $300.00 | $120.00 | $100.00 | $115.00 |
| 45 | Pavement sler 6" (666-7347) | LF | 427 | $1.00 | $1.75 | $1.65 | $1.50 | $1.50 | $2.00 | $2.00 |
| 46 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 750 | $1.00 | $2.75 | $2.75 | $2.50 | $2.50 | $3.00 | $3.15 |
| 47 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 750 | $1.00 | $2.75 | $2.75 | $2.50 | $2.50 | $3.00 | $3.15 |
| 48 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 10 | $6.00 | $7.00 | $6.88 | $7.00 | $6.25 | $10.00 | $8.00 |
| 49 | Pavement surface preparation for marking (6") (678-7002) | LF | 1,500 | $1.00 | $1.00 | $0.83 | $0.75 | $0.75 | $1.00 | $1.00 |
| 50 | Steel fence (remove) (5007-7001) | LF | 48 | $60.00 | $25.00 | $15.40 | $20.00 | $25.00 | $15.00 | $50.00 |
| 51 | Steel fence (install) (5007-7002) | LF | 163 | $120.00 | $100.00 | $75.35 | $60.00 | $150.00 | $125.00 | $130.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 5, 2026. Compiled by Mirage Metrics.