TxDOT contract A00133118 bid tabulation

Widen Road - Add Lanes, SH 99 (IH 10(W) to West Road). Let by Texas DOT on April 8, 2026, Harris, Houston District. 10 bids received; low bid $119,970,903 by Ser Construction Partners, LLC, -12% against the engineer's estimate of $135,992,054.

Owner
Texas DOT
Letting
08 APR 2026
Pay items
175
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Ser Construction Partners, LLC$119,970,903Low-12%
2Webber, LLC$123,649,965+3.0%-9.0%
3Posillico Civil, Inc.$124,689,845+4.0%-8.0%
4MC2 Civil, LLC$127,970,000+7.0%-6.0%
5James Construction Group, LLC$132,896,173+11%-2.0%
6Pulice Construction, Inc.$132,992,475+11%-2.0%
7Zachry Construction Corporation$134,004,995+12%-1.0%
8Isi Contracting, Inc.$139,881,918+17%+3.0%
9Harper Brothers Construction LLC$143,791,907+20%+6.0%
10Granite Construction Company$155,750,774+30%+15%
TxDOT contract A00133118: bids by rank

Engineer's estimate: $135,992,054.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Ser Construction Partners, LLC2. Webber, LLC3. Posillico Civil, Inc.4. MC2 Civil, LLC5. James Construction Group, LLC6. Pulice Construction, Inc.
1Preparing row (100-7002)STA747.06$4,500.00$6,550.00$15,650$5,000.00$15,000$15,905$13,500
2Removing concrete (pavement) (104-7001)SY57,821.54$15.00$14.20$24.00$14.00$18.00$14.36$8.65
3Removing concrete (mowstrip) (104-7005)LF74,847.10$17.00$0.60$2.50$0.55$3.50$0.58$2.03
4Removing concrete (riprap) (104-7006)SY3,326.27$19.00$5.00$30.00$1.33$10.00$1.41$4.21
5Removing concrete (rail) (104-7036)LF10,795.41$35.00$1.90$30.00$58.00$5.00$1.13$19.99
6Remove (4"-10") TRT/untrt base & asphalt pavement (105-7055)SY85,509.99$15.00$4.70$5.50$1.50$3.00$0.59$2.46
7Excavation (roadway) (110-7001)CY290,940$10.00$13.00$19.00$4.00$5.00$15.40$15.00
8Excavation (channel) (110-7002)CY15,380$15.00$8.60$20.00$14.00$15.00$20.00$15.00
9Embankment (final)(DC)(type C) (132-7006)CY6,461$30.00$11.00$20.00$17.00$9.00$17.00$3.00
10Block sodding (162-7002)SY541,321$3.50$3.00$3.40$3.40$3.60$3.40$3.30
11Broadcast seed (temporary_warm_cool) (164-7007)SY5,426$0.25$0.10$0.15$0.14$0.15$0.14$0.14
12Drill seed (temporary_warm_cool) (164-7015)SY108,274$0.30$0.20$0.15$0.13$0.15$0.13$0.13
13Straw/hay mulch (164-7065)SY113,700$0.35$0.30$0.20$0.22$0.22$0.22$0.22
14Fertilizer (166-7001)ACRE135.47$640.00$918.00$588.00$585.00$600.00$587.73$599.72
15Vegetative watering (168-7001)TGL16,256.40$20.00$5.00$43.25$16.00$20.00$41.08$25.00
16Lime (com or QK)(slurry) or QK(dry) (260-7001)TON5,980$330.00$335.60$1.00$330.00$1.00$345.92$325.00
17Lime TRT (existing material)(8") (260-7007)SY332,301$5.50$1.90$5.30$5.00$5.00$5.90$3.00
18Cement (275-7001)TON4,485$205.00$167.30$1.00$175.00$1.00$21.00$160.00
19Cem TRT(PLNT MX)(CL N)(type E)(GR 4)(6") (276-7343)SY332,301$15.00$17.30$15.40$25.00$18.00$18.32$17.00
20Asphalt TRT base (GR 4)(PG 64) (292-7014)TON36,544$140.00$80.00$122.00$140.00$110.00$10.00$143.87
21Concrete pavement (CRCP) (12") (360-7006)SY332,222$100.00$83.90$69.50$100.00$81.00$92.64$86.50
22Cem stabil BKFL (400-7010)CY3,349$90.00$52.00$50.00$65.00$58.00$52.89$60.00
23Cement stab backfill (inlet or MH) (400-7011)CY931$80.00$52.00$50.00$60.00$58.00$52.89$65.00
24Flowable backfill (401-7001)CY479$400.00$162.80$240.00$315.00$230.00$319.88$180.00
25Trench excavation protection (402-7001)LF6,294$5.00$0.10$5.00$2.00$1.00$1.10$25.79
26Temporary special shoring (403-7001)SF538$60.00$27.50$10.00$160.00$20.00$12.03$10.00
27Drilled shaft (42 in) (416-7007)LF18,208$380.00$296.50$331.00$325.00$395.00$315.01$320.00
28Drilled shaft (non - reinforced) (12 in) (416-7024)LF7$175.00$92.50$53.75$100.00$100.00$53.72$54.82
29Drilled shaft (sign mounts) (24 in) (416-7028)LF652$260.00$155.00$162.00$155.00$165.00$161.56$119.56
30Class C concrete (cap) (420-7022)CY902.20$1,600.00$1,778.20$1,800.00$1,345.00$1,700.00$1,840.33$1,200.00
31Class C concrete (column) (420-7038)CY553.60$1,600.00$1,056.50$1,400.00$1,415.00$1,600.00$1,045.78$1,550.00
32Class C concrete (footing) (420-7044)CY19.60$1,500.00$1,282.20$1,900.00$1,685.00$1,500.00$1,480.95$1,300.00
33Class C concrete (sign column) (420-7057)CY53.62$1,500.00$1,352.30$2,000.00$2,300.00$1,900.00$2,277.09$1,500.00
34Reinforced concrete slab (extend slab) (422-7003)SF485,666$30.00$23.30$26.00$22.00$33.00$31.30$25.50
35Prestressed concrete girder (TX28) (425-7001)LF260$299.40$217.00$380.00$200.00$236.08$250.00
36Prestressed concrete girder (TX34) (425-7002)LF738.20$250.00$270.40$190.00$385.00$200.00$208.57$200.00
37Prestressed concrete girder (TX46) (425-7004)LF2,628$244.20$200.00$330.00$200.00$221.90$205.00
38Prestressed concrete girder (TX54) (425-7005)LF38,017.34$230.00$240.90$193.00$323.00$210.00$221.32$210.00
39Prestressed concrete girder (TX62) (425-7006)LF5,548.94$255.00$238.40$222.00$320.00$230.00$240.69$220.00
40Prestressed concrete U-beam (U54) (425-7043)LF631.02$795.60$477.00$365.00$550.00$506.41$500.00
41Riprap (concrete)(4 in) (432-7001)CY2$750.00$827.80$5,000.00$615.00$1,593.26$2,272.54$867.54
42Riprap (concrete)(6 in) (432-7003)CY4$549.10$5,000.00$525.00$1,000.00$737.35$891.64
43Riprap (concrete)(CL B) (432-7005)CY835$800.00$432.70$600.00$350.00$550.00$539.06$855.49
44Riprap (mow strip)(4 in) (432-7013)CY11$800.00$591.60$5,000.00$680.00$550.00$725.66$921.76
45Riprap (stone common)(dry)(6 in) (432-7029)CY6$300.00$355.80$5,000.00$240.00$360.00$511.27$155.00
46Riprap (concrete)(CL B)(RR8&RR9) (432-7055)CY8.20$900.00$662.10$5,000.00$490.00$1,200.00$709.87$891.64
47Cleaning & sealing existing joint (SEJ) (438-7013)LF6,030$40.00$16.70$110.00$92.00$50.00$56.45$59.39
48Rail (type SSTR) (450-7024)LF23,653.20$85.00$52.00$63.75$30.00$68.00$65.29$70.00
49Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF2,227$260.00$171.30$260.00$310.00$180.00$191.73$285.00
50Sealed expansion joint (5 in) (SEJ - M) (454-7005)LF160$171.30$285.00$310.00$180.00$191.73$331.43
51RC pipe (CL III)(24 in) (464-7005)LF5,095$105.00$100.10$120.00$120.00$101.00$91.93$150.00
52RC pipe (CL III)(30 in) (464-7007)LF1,267$170.00$119.20$180.00$134.00$143.00$125.20$170.00
53RC pipe (CL III)(42 in) (464-7010)LF318$275.00$197.30$250.00$160.00$220.00$180.27$200.00
54Inlet (complete)(PSL)(RC)(3FTX3FT) (465-7070)EACH1$3,604.70$5,000.00$4,860.00$3,700.00$3,762.10$6,000.00
55Inlet (complete)(type AZ2G)(hou) (465-7317)EACH120$9,000.00$10,199$11,000$11,150$9,000.00$10,481$14,000
56JCT box (complete)(special) (465-7332)EACH4$22,000$26,248$15,000$16,000$20,000$19,061$25,000
57Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325)EACH1$2,000.00$1,470.00$80,000$1,265.00$1,800.00$1,913.44$5,000.00
58Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326)EACH15$2,000.00$1,648.50$2,250.00$1,400.00$1,900.00$2,019.93$5,000.00
59Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348)EACH2$4,000.00$4,012.50$4,000.00$2,630.00$2,800.00$2,699.50$5,000.00
60Set (type II) (42 in) (RCP) (6: 1) (P) (467-7380)EACH2$6,500.00$10,706$5,000.00$15,300$15,000$11,319$15,000
61Adjusting inlets (479-7002)EACH4$1,500.00$539.80$15,000$1,110.00$1,800.00$2,841.34$2,000.00
62Adjusting inlets (cap) (479-7006)EACH42$1,700.00$623.40$2,000.00$1,875.00$1,500.00$3,150.68$2,000.00
63Removing structure (inlet) (496-7002)EACH88$1,000.00$443.10$1,600.00$360.00$500.00$1,044.56$2,000.00
64Removing structure (set) (496-7004)EACH39$330.00$91.60$1,200.00$400.00$500.00$696.37$2,000.00
65Removing structure (pipe) (496-7007)LF2,124$30.00$19.60$75.00$20.00$20.00$16.83$140.00
66Mobilization (500-7001)LS1$12,353,699$12,000,000$12,000,000$9,770,000$12,300,000$13,264,000$13,299,248
67Barricades, signs and traffic handling (502-7001)MO48$15,000$11,000$1,000.00$3,000.00$19,000$33,153$15,000
68Portable changeable message sign (503-7001)DAY360$200.00$61.20$150.00$200.00$65.00$101.39$145.18
69TMA (mobile operation) (505-7003)DAY360$225.00$524.30$250.00$850.07$700.00$660.80$230.59
70Rock filter dams (install) (type 2) (506-7002)LF4,285$50.00$81.60$47.00$47.00$48.00$46.93$47.89
71Rock filter dams (install) (type 3) (506-7003)LF80$102.00$123.00$123.00$125.00$123.14$125.65
72Rock filter dams (remove) (506-7011)LF4,365$15.00$20.40$13.40$13.50$14.00$13.44$13.71
73Construction exits (install) (type 1) (506-7020)SY5,000$27.00$28.20$41.75$50.00$42.00$41.80$42.65
74Construction exits (remove) (506-7024)SY5,000$10.00$6.40$12.20$12.20$12.00$12.20$12.45
75Temporary sediment control fence (install) (506-7039)LF53,539$4.00$1.80$3.25$3.25$3.50$3.23$3.30
76Temporary SDMT cont fence (inlet protection) (506-7040)LF9,490$5.50$5.10$7.00$7.00$7.00$7.01$7.15
77Temporary sediment control fence (remove) (506-7041)LF63,029$1.00$0.60$0.95$1.00$1.00$0.96$0.98
78Biodegradable erosion control logs (install) (12") (506-7044)LF5,102$6.00$6.10$5.60$5.65$6.00$5.61$5.72
79Biodegradable erosion control logs (remove) (506-7046)LF5,102$1.50$2.00$1.20$1.20$1.00$1.19$1.21
80Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013)LF62,250$15.00$14.90$11.79$8.00$11.00$12.49$8.00
81Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF99,719$11.00$9.70$0.01$6.50$7.00$6.25$5.00
82Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037)LF62,250$14.90$10.51$8.00$10.00$12.49$8.00
83Permanent CTB (single slope) (type 1) (42 ) (514-7001)LF41,517$90.00$65.20$75.46$60.00$76.00$63.75$75.00
84Permanent CTB (single slope)(42)(mod) (514-7004)LF776$300.00$294.30$669.00$190.00$200.00$396.84$330.91
85Permanent CTB (tran SSCB to SSTR) (mod) (514-7038)LF1,800$350.00$470.30$657.00$140.00$500.00$226.30$500.00
86Permanent CTB (single slope)(type 1)(special) (514-7053)LF18,544$300.00$283.30$196.00$114.00$200.00$181.28$270.00
87Metal W-beam guard fence (timber post) (540-7001)LF100$35.00$33.20$32.50$38.40$40.00$32.50$40.77
88Downstream anchor terminal section (540-7015)EACH1$1,600.00$1,785.00$1,750.00$1,475.00$1,500.00$1,750.00$1,566.20
89Remove metal beam guard fence (542-7001)LF3,067.91$4.00$2.60$2.50$3.00$4.00$2.50$3.19
90Remove terminal anchor section (542-7002)EACH12$250.00$255.00$250.00$220.00$250.00$250.00$233.60
91Cable barrier terminal sec (install)(TL-3) (543-7017)EACH1$6,000.00$5,100.00$4,720.00$4,720.00$5,000.00$4,956.00$5,011.84
92Cable barrier (remove) (543-7037)LF61,842.51$3.00$4.60$3.85$3.85$4.00$4.04$4.09
93Cable barrier terminal section (remove) (543-7038)EACH70$500.00$397.80$385.00$385.00$400.00$404.25$408.80
94Guardrail end treatment (install) (544-7001)EACH1$3,500.00$3,927.00$3,850.00$4,205.00$4,500.00$3,850.00$4,465.00
95Guardrail end treatment (remove) (544-7003)EACH12$300.00$204.00$200.00$330.00$350.00$200.00$350.40
96Crash cushion attenuator (remove) (545-7004)EACH37$1,300.00$1,020.00$1,000.00$885.00$1,000.00$1,000.00$939.72
97Crash cushion attenuator (install)(L)(N)(TL3) (545-7006)EACH42$27,000$22,083$21,650$25,500$27,000$21,650$27,077
98Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH1$10,000$8,313.00$8,150.00$8,280.00$9,000.00$8,150.00$8,791.96
99Conduit (PVC) (schedule 80) (1 1/2") (618-7052)LF1,119$10.00$15.60$22.30$13.15$10.00$9.53$13.42
100Conduit (PVC) (schedule 80) (1 1/2") (bore) (618-7053)LF2,595$20.00$20.40$21.00$18.48$16.00$15.03$18.86
101Conduit (PVC) (schedule 80) (3") (618-7060)LF101$21.00$23.50$94.50$16.64$65.00$59.41$16.98
102Conduit (prepare) (618-7090)LF288$4.50$1.00$2.10$10.65$3.00$2.64$10.87
103Ground box type A (122311)W/apron (624-7002)EACH8$1,100.00$1,428.00$1,390.00$1,189.64$1,200.00$1,130.78$1,213.92
104Ground box type C (162911)W/apron (624-7006)EACH4$1,500.00$1,632.00$1,430.00$1,240.84$1,400.00$1,325.49$1,266.16
105Aluminum signs (type G) (636-7002)SF3,427.50$50.00$35.70$38.60$31.95$40.00$38.36$34.47
106Aluminum signs (type O) (636-7003)SF436$50.00$41.80$26.80$36.23$36.00$34.41$36.97
107Replace existing aluminum signs(type A) (636-7004)SF131.50$38.00$32.60$29.15$33.25$36.00$34.14$35.88
108Replace existing aluminum signs(type G) (636-7005)SF1,753.25$45.00$38.80$45.12$39.10$48.00$45.21$36.97
109Replace existing aluminum signs(type O) (636-7006)SF5,930.75$40.00$41.80$28.15$36.23$36.00$33.64$36.97
110Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH22$700.00$596.70$753.00$745.00$800.00$585.00$803.85
111Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH50$790.00$770.10$811.00$960.00$1,000.00$755.00$1,035.83
112Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH50$840.00$1,004.70$1,003.00$1,185.00$1,200.00$985.00$1,278.60
113Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH2$1,200.00$984.30$1,615.00$1,215.00$1,300.00$965.00$1,310.98
114Install small roadside sign support and assembly TYS80(1)SB(T) (644-7040)EACH4$1,200.00$1,004.70$1,095.00$1,975.00$2,000.00$985.00$2,131.01
115Install LRSS (struct steel) (647-7001)LB25,462.60$9.00$6.10$5.75$6.50$6.00$5.76$7.01
116Remove lrsa (647-7003)EACH39$600.00$255.00$390.00$735.00$400.00$390.19$338.69
117Install overhead sign support(35 FT cant)(span only) (650-7041)EACH1$27,500$31,620$43,410$35,834$42,000$41,677$36,566
118Install overhead sign support(40 FT cant)(span only) (650-7048)EACH1$33,150$44,550$37,137$44,000$43,531$37,895
119Remove overhd sign sup (650-7193)EACH1$3,570.00$13,080$1,618.15$11,000$10,541$1,651.17
120Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH1,011$23.00$21.40$21.00$24.00$25.00$21.00$25.90
121Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH53$25.00$33.20$32.50$30.00$33.00$32.50$32.37
122Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031)EACH24$25.00$21.40$21.00$24.00$25.00$21.00$25.90
123Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032)EACH934$20.00$21.90$21.50$24.00$25.00$21.50$25.90
124Install OM SM RD sign (1-OM-type 1)Y (658-7088)EACH1$66.30$82.50$59.00$60.00$1,500.00$63.66
125Install OM LG RD sign (2-OM-type 1)Y (658-7090)EACH40$50.00$91.80$95.00$82.00$90.00$97.53$88.48
126Install OM LG RD sign (3-OM-type 1)Y (658-7091)EACH2$127.50$115.00$109.00$120.00$130.24$117.61
127Replace OM LG RD sign (2-OM-type 1)Y (658-7103)EACH23$55.00$91.80$95.00$101.00$110.00$93.34$108.98
128Replace OM LG RD sign (3-OM-type 1)Y (658-7104)EACH1$80.00$127.50$115.00$128.00$150.00$130.24$138.11
129Work zone pavement marking removing (W)4"(broken) (662-7061)LF43,958$1.25$1.20$1.70$1.15$1.20$1.15$1.74
130Work zone pavement marking removing (W)4"(solid) (662-7064)LF163,595$0.75$1.20$0.90$1.15$1.20$1.15$0.94
131Work zone pavement marking removing (W)8"(solid) (662-7072)LF24,905$2.00$2.40$1.85$2.35$2.40$2.35$1.88
132Work zone pavement marking removing (W)12"(lane drop) (662-7074)LF1,599$3.00$4.10$5.10$4.00$4.20$4.00$5.22
133Work zone pavement marking removing (W)12"(solid) (662-7075)LF3,750$4.00$4.10$3.50$4.00$4.20$4.00$3.58
134Work zone pavement marking removing (W)(arrow) (662-7082)EACH8$200.00$76.50$155.00$75.00$80.00$75.00$158.16
135Work zone pavement marking removing (W)(word) (662-7092)EACH8$225.00$76.50$185.00$75.00$80.00$75.00$188.78
136Work zone pavement marking removing (Y)4"(solid) (662-7097)LF159,513$1.00$1.20$0.90$1.15$1.20$1.15$0.94
137Reflectorized pavement marking type III (W)(6")(DOT) (666-7238)LF3,922$1.70$1.20$2.50$1.20$1.25$1.20$2.55
138Reflectorized pavement marking type III (W)(8")(solid) (666-7239)LF32,764$2.00$1.10$2.75$1.05$1.10$1.05$2.81
139Reflectorized pavement marking type III (W)(12")(solid) (666-7242)LF8,981$3.00$5.10$5.00$5.00$5.25$5.00$5.10
140Reflectorized pavement marking type III (W)(12")(DOT) (666-7243)LF2,643$3.75$5.10$5.00$5.00$5.25$5.00$5.10
141Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266)LF148,259$0.95$0.80$0.80$0.78$0.80$0.78$0.84
142Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270)LF148,236$1.50$0.80$0.80$0.78$0.80$0.78$0.84
143Pavement sler 6" (666-7347)LF296,495$0.15$0.20$0.20$0.20$0.20$0.20$0.18
144Pavement sler (arrow) (666-7353)EACH22$25.00$25.50$5.00$25.00$25.00$25.00$5.10
145Pavement sler (word) (666-7354)EACH27$40.00$25.50$5.00$25.00$25.00$25.00$5.10
146Pavement sler (double arrow) (666-7356)EACH4$40.00$25.50$5.00$25.00$25.00$25.00$5.10
147Pavement sler (symbol) (666-7363)EACH5$51.00$55.00$50.00$50.00$50.00$56.12
148Prefabricated PM type C (W)(arrow) (668-7091)EACH22$250.00$214.20$360.00$210.00$220.00$210.00$367.25
149Prefabricated PM type C (W)(double arrow) (668-7093)EACH4$310.00$306.00$387.00$300.00$300.00$300.00$395.25
150Prefabricated PM type C (W)(word) (668-7103)EACH27$300.00$219.30$371.00$215.00$220.00$215.00$378.70
151Prefabricated PM type C (multi)(shield) (668-7135)EACH5$2,550.00$3,630.00$2,500.00$2,500.00$2,500.00$3,708.06
152Reflectorized pavement marker type II-C-R (672-7006)EACH6,580$5.50$6.10$6.00$6.00$6.00$6.00$6.12
153Eliminating existing PM & markers (6") (677-7002)LF297,306$0.45$0.40$0.30$0.38$0.40$0.38$0.29
154Eliminating existing PM & markers (8") (677-7004)LF32,764$0.80$0.50$0.85$0.50$0.50$0.50$0.86
155Eliminating existing PM & markers (10") (677-7005)LF40,650$1.00$0.80$1.15$0.75$0.80$0.75$1.19
156Eliminating existing PM & markers (12") (677-7006)LF5,650$1.50$0.90$1.65$0.90$1.00$0.90$1.68
157Eliminating existing PM & markers (arrow) (677-7009)EACH18$55.00$51.00$70.00$50.00$50.00$50.00$71.43
158Eliminating existing PM & markers (double arrow) (677-7010)EACH1$51.00$75.00$50.00$50.00$50.00$76.53
159Eliminating existing PM & markers (word) (677-7015)EACH26$50.00$51.00$75.00$50.00$50.00$50.00$76.53
160Eliminating existing PM & markers (shield) (677-7022)EACH4$51.00$250.00$50.00$50.00$50.00$255.10
161Pavement surface preparation for marking (6") (678-7002)LF300,417$0.15$0.10$0.05$0.01$0.03$0.01$0.03
162Pavement surface preparation for marking (8") (678-7004)LF32,764$0.10$0.10$0.05$0.02$0.05$0.02$0.04
163Pavement surface preparation for marking (10") (678-7005)LF74,670$0.15$0.10$0.05$0.03$0.06$0.03$0.05
164Pavement surface preparation for marking (12") (678-7006)LF11,624$0.50$0.10$0.05$0.10$0.10$0.10$0.06
165Pavement surface preparation for marking (arrow) (678-7009)EACH22$11.00$15.30$1.00$15.00$15.00$15.00$1.02
166Pavement surface preparation for marking (double arrow) (678-7010)EACH4$15.00$15.30$1.00$15.00$15.00$15.00$1.02
167Pavement surface preparation for marking (word) (678-7016)EACH27$20.00$15.30$1.00$15.00$15.00$15.00$1.02
168Pavement surface preparation for marking (shield) (678-7025)EACH5$15.30$1.00$15.00$15.00$15.00$1.02
169Full - width mowing (730-7019)CYC16$4,000.00$6,903.40$7,500.00$27,000$10,000$10,111$11,405
170Litter removal (734-7002)CYC48$2,000.00$2,888.60$5,000.00$4,000.00$5,000.00$934.39$6,899.31
171Clean / sweep-outside main lane-area(1) (738-7029)CYC48$2,500.00$1,670.80$3,000.00$3,000.00$3,000.00$500.00$7,548.56
172Ditch clean / reshaping(CU YD in place) (760-7002)CY20,429$20.00$47.80$4.25$9.00$16.00$22.98$23.65
173Wide flange pavement terminals (3003-7001)LF1,522$550.00$620.90$750.00$950.00$750.00$831.73$1,176.95
174Ground box (prepare) (6013-7006)EACH10$400.00$663.00$233.00$255.69$450.00$409.07$260.91
175Prefb PV MK W/wnty type B(W)6"(broken)CNTST (6064-7003)LF74,670$12.00$15.30$10.50$15.00$11.00$15.00$10.71
TxDOT contract A00133118: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of April 8, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy