TxDOT contract A00136607 bid tabulation

Bridge Replacement, CR 216 (STR. (AA0156001) Salt Creek to Approx. .70 MI E of SH 72). Let by Texas DOT on June 4, 2025, Live Oak, Corpus Christi District. 7 bids received; low bid $4,876,307 by Relmco, Inc., -32% against the engineer's estimate of $7,223,073.

Owner
Texas DOT
Letting
04 JUN 2025
Pay items
88
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Relmco, Inc.$4,876,307Low-32%
2Acme Bridge Company, Inc.$5,221,047+7.0%-28%
3E-Z Bel Construction, LLC$6,969,271+43%-4.0%
4Urban Infraconstruction LLC$6,977,000+43%-3.0%
5J. Carroll Weaver, Inc.$7,536,249+55%+4.0%
6CK Newberry, LLC$7,751,280+59%+7.0%
7C. E. Barker, LTD.$8,537,706+75%+18%
TxDOT contract A00136607: bids by rank

Engineer's estimate: $7,223,073.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Relmco, Inc.2. Acme Bridge Company, Inc.3. E-Z Bel Construction, LLC4. Urban Infraconstruction LLC5. J. Carroll Weaver, Inc.6. CK Newberry, LLC
1Preparing row (100-7002)STA16.55$40,000$13,500$5,270.00$7,200.00$25,000$4,960.31$10,000
2Removing concrete (miscellaneous) (104-7046)SY320$175.00$30.00$14.50$65.00$20.00$17.60$50.00
3Remove (6") TRT/untrt base & asphalt pavement (105-7026)SY514$20.00$11.60$9.00$7.00$12.98$12.00
4Remove (8"-14") TRT/untrt base & asphalt pavement (105-7059)SY1,948$31.00$20.00$14.50$11.00$11.00$12.98$15.00
5Excavation (roadway) (110-7001)CY4,804$35.00$15.00$22.20$18.00$30.00$12.98$20.00
6Excavation (channel) (110-7002)CY2,214$40.00$15.00$25.60$22.00$45.00$12.98$30.00
7Embankment (final)(DC)(type B) (132-7004)CY4,789$55.00$15.00$12.90$39.00$55.00$13.47$20.00
8Embankment (final)(DC)(type C) (132-7006)CY1,621$40.00$37.60$35.00$55.00$13.47$15.00
9Compost manuf topsoil (4") (161-7002)SY4,189$7.00$9.43$3.20$3.00$9.50$10.26$10.00
10Straw/hay mulch seed(permanent_rural_clay) (164-7026)SY4,189$1.00$1.40$1.35$2.00$0.65$1.14$1.50
11Straw/hay mulch seed (temporary_warm) (164-7029)SY857$4.27$4.15$3.00$0.75$1.43$4.00
12Straw/hay mulch seed (temporary_cool) (164-7030)SY857$5.14$4.95$3.00$0.75$1.43$5.00
13Straw/hay mulch seed (temporary_warm_cool) (164-7031)SY2,476$1.00$1.77$1.70$3.00$0.75$1.31$2.00
14Vegetative watering (168-7001)TGL106$100.00$50.00$111.00$102.00$60.00$71.50$30.00
15FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176)CY831$150.00$145.00$125.00$120.00$200.00$152.39$165.00
16Prime coat (MC-30) (310-7004)GAL721$10.00$6.00$10.90$20.00$10.00$14.58$10.00
17Prime coat (multi option) (310-7015)GAL187$10.00$12.80$25.00$6.00$34.74$10.00
18Asphalt(AC-15P, HFRS-2P or CRS-2P) (316-7070)GAL255$8.00$11.20$25.00$6.00$34.74$10.00
19Aggregate (type-PB, GR-3 or 3S)(sac-B) (316-7209)CY45$185.00$195.00$625.00$1,200.00$220.00$1,464.79$1,100.00
20Aggregate (type-PB, GR-4S or 4)(sac-B) (316-7212)CY39$150.00$195.00$701.00$1,300.00$190.00$1,464.78$1,200.00
21Asphalt (multi option) (316-7263)GAL2,521$4.50$6.00$7.00$15.00$6.00$34.74$10.00
22Asphalt (multi option) (316-7275)GAL310$10.00$10.20$18.50$6.00$34.74$10.00
23Cem stabil BKFL (400-7010)CY143$250.00$185.00$290.00$586.00$295.00$81.76$250.00
24Temporary special shoring (403-7001)SF841$35.00$104.00$93.00$45.00$122.50$85.00
25Foundaton loadtest(D4945)(drilld shaft) (405-7003)EACH2$28,000$36,700$25,000$30,000$13,110$25,000
26Drilled shaft (24 in) (416-7004)LF240$295.00$184.00$340.00$185.00$299.93$385.00
27Drilled shaft (30 in) (416-7005)LF105$325.00$222.00$495.00$250.00$304.26$570.00
28Drilled shaft (36 in) (416-7006)LF1,643$420.00$335.00$250.00$497.00$265.00$289.42$575.00
29Class C concrete (abutment) (420-7012)CY136.10$1,500.00$1,202.60$1,300.00$1,900.00$3,050.00$1,665.64$1,850.00
30Class C concrete (cap) (420-7022)CY61.60$1,500.00$1,671.60$1,520.00$3,500.00$2,050.00$2,912.15$2,800.00
31Class C concrete (column) (420-7038)CY48.30$1,800.00$1,220.80$2,060.00$3,308.00$2,275.00$2,831.27$1,800.00
32Reinforced concrete slab (422-7001)SF5,070$36.97$32.50$35.00$28.00$162.33$40.00
33Reinforced concrete slab (slab beam) (422-7007)SF7,280$27.00$21.46$23.00$35.00$28.00$28.75$50.00
34Approach slab (422-7013)CY115.70$900.00$650.00$817.00$1,350.00$925.00$1,400.99$1,000.00
35Retaining wall (temporary wall) (423-7012)SF6,156$24.00$54.70$116.00$50.00$86.57$45.00
36Prestressed concrete girder (TX28) (425-7001)LF774$250.00$306.00$375.00$280.00$274.12$275.00
37Prestressed concrete slab beam (5SB12) (425-7017)LF740$250.00$250.00$287.00$398.00$280.00$251.45$300.00
38Prestressed concrete slab beam (5SB15) (425-7019)LF642.50$250.00$283.00$350.00$280.00$277.78$285.00
39Riprap (concrete)(4 in) (432-7001)CY5.40$600.00$978.00$1,263.00$1,225.00$1,046.01$700.00
40Riprap (mow strip)(4 in) (432-7013)CY103.60$700.00$495.00$818.00$950.00$1,225.00$887.33$700.00
41Riprap (stone protection)(12 in) (432-7041)CY1,183$320.00$150.00$184.00$180.00$185.00$229.75$350.00
42Riprap (stone protection)(18 in) (432-7043)CY253$150.00$180.00$283.00$170.00$246.91$300.00
43Rail (type T223) (450-7008)LF1,070$175.00$95.00$98.00$210.00$235.00$231.31$250.00
44Armor joint (sealed) (454-7003)LF44$180.00$251.00$212.00$265.00$193.59$275.00
45Sealed expansion joint (4 in) (SEJ - B) (454-7006)LF50$180.00$220.00$358.00$255.00$208.45$275.00
46Removing structure (bridge 0 - 99 FT length) (496-7009)EACH3$35,000$35,000$20,200$57,024$73,000$46,549$65,000
47Removing structure (bridge 100 - 499 FT length) (496-7010)EACH1$80,000$95,300$57,024$110,000$101,875$90,000
48Removing structure (abutment) (496-7014)EACH2$8,500.00$5,290.00$23,133$4,000.00$8,447.76$10,000
49Removing structure (ret wall) (496-7019)LF6,276$10.00$5.90$1.00$12.00$11.26$16.00
50Mobilization (500-7001)LS1$660,827$435,000$475,000$520,000$317,626$662,602$650,000
51Barricades, signs and traffic handling (502-7001)MO33$7,000.00$3,500.00$4,460.00$1,500.00$3,125.00$8,756.95$5,000.00
52Portable changeable message sign (503-7001)DAY196$100.00$200.00$91.30$80.00$365.00$171.00$75.00
53TMA (stationary) (505-7001)DAY73$200.00$250.00$144.00$50.00$840.00$570.00$350.00
54TMA (mobile operation) (505-7002)HR120$90.00$50.00$116.00$25.00$145.00$74.10$750.00
55Rock filter dams (install) (type 2) (506-7002)LF400$55.00$66.96$64.60$50.00$60.00$85.50$65.00
56Rock filter dams (remove) (506-7011)LF400$20.00$12.43$12.00$15.00$10.00$11.40$13.00
57Construction exits (install) (type 1) (506-7020)SY111$43.56$42.00$35.00$42.00$17.10$40.00
58Construction exits (remove) (506-7024)SY111$15.07$14.50$10.00$12.00$17.10$15.00
59Temporary sediment control fence (install) (506-7039)LF3,414$6.00$5.22$5.00$6.00$5.00$5.68$5.00
60Temporary sediment control fence (remove) (506-7041)LF3,414$2.00$1.37$1.35$1.00$1.50$4.97$2.00
61Constructing detours (508-7001)SY45$40.00$194.00$75.00$150.00$299.54$125.00
62Constructing detours (ebss) (508-7002)SY1,438$38.00$56.70$110.00$150.00$263.87$150.00
63One-way traffic control (port traffic signal) (510-7003)MO11$3,200.00$3,250.00$1,500.00$14,500$5,334.35$10,000
64Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF775$35.00$21.70$38.00$95.00$30.57$100.00
65Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF160$35.00$25.30$43.00$95.00$10.44$75.00
66Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF775$28.00$22.50$23.00$22.00$7.77$20.00
67Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF160$28.00$21.80$17.00$22.00$7.77$45.00
68PTB (fur&inst)(SSCB or CSB)(type 1)or(steel) (512-7085)LF571$30.00$18.70$18.00$90.00$30.94$60.00
69PTB (remove)(SSCB or CSB)(type 1)or(steel) (512-7088)LF571$30.00$18.50$18.00$16.00$46.41$55.00
70Metal W-beam guard fence (steel post) (540-7002)LF300$48.00$33.70$32.50$31.00$36.00$35.34$35.00
71Metal beam guard fence trans (thrie-beam) (540-7005)EACH12$2,500.00$2,886.40$3,130.00$2,624.00$3,100.00$3,021.00$2,750.00
72Metal beam guard fence trans (TL2) (540-7006)EACH4$1,818.30$1,750.00$1,653.00$1,900.00$1,892.40$1,850.00
73Guardrail end treatment (install) (544-7001)EACH16$3,500.00$3,763.10$3,630.00$3,421.00$4,000.00$3,933.00$3,500.00
74Wire fence (type C) (552-7003)LF203$51.70$49.90$47.00$17.00$53.58$50.00
75Wire fence (remove) (552-7011)LF203$4.40$4.25$4.00$6.00$4.56$4.00
76Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH6$1,650.00$1,590.00$1,500.00$1,800.00$1,710.00$1,600.00
77Remove SM RD SN sup&AM (644-7073)EACH2$275.00$265.00$250.00$290.00$285.00$275.00
78Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH4$82.50$79.60$75.00$90.00$85.50$80.00
79Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016)EACH4$55.00$53.00$50.00$60.00$57.00$50.00
80Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF5,040$0.59$0.57$1.00$1.00$0.62$0.75
81Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF48$27.50$26.50$25.00$3.50$28.50$25.00
82Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF1,440$1.21$1.15$1.15$1.80$1.25$1.25
83Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270)LF1,020$8.25$8.00$8.00$7.00$8.55$8.00
84Reflectorized pavement marker type II-A-A (672-7004)EACH49$27.50$26.50$25.00$3.00$28.50$25.00
85Pavement surface preparation for marking (6") (678-7002)LF390$3.30$3.20$3.00$78.00$3.42$3.00
86Tip testing(drilled shaft) (4003-7001)EACH3$4,200.00$6,070.00$8,500.00$12,325$14,440$10,000
87Temporary construction access (4006-7001)LS1$65,000$78,200$12,500$215,000$79,281$165,000
88Temporary detour bridge (4012-7001)EACH1$185,000$285,000$195,000$315,000$285,770$450,000
TxDOT contract A00136607: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy