TxDOT contract A00136607 bid tabulation
Bridge Replacement, CR 216 (STR. (AA0156001) Salt Creek to Approx. .70 MI E of SH 72). Let by Texas DOT on June 4, 2025, Live Oak, Corpus Christi District. 7 bids received; low bid $4,876,307 by Relmco, Inc., -32% against the engineer's estimate of $7,223,073.
- Owner
- Texas DOT
- Letting
- 04 JUN 2025
- Pay items
- 88
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Relmco, Inc. | $4,876,307 | Low | -32% |
| 2 | Acme Bridge Company, Inc. | $5,221,047 | +7.0% | -28% |
| 3 | E-Z Bel Construction, LLC | $6,969,271 | +43% | -4.0% |
| 4 | Urban Infraconstruction LLC | $6,977,000 | +43% | -3.0% |
| 5 | J. Carroll Weaver, Inc. | $7,536,249 | +55% | +4.0% |
| 6 | CK Newberry, LLC | $7,751,280 | +59% | +7.0% |
| 7 | C. E. Barker, LTD. | $8,537,706 | +75% | +18% |
Engineer's estimate: $7,223,073.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Relmco, Inc. | 2. Acme Bridge Company, Inc. | 3. E-Z Bel Construction, LLC | 4. Urban Infraconstruction LLC | 5. J. Carroll Weaver, Inc. | 6. CK Newberry, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 16.55 | $40,000 | $13,500 | $5,270.00 | $7,200.00 | $25,000 | $4,960.31 | $10,000 |
| 2 | Removing concrete (miscellaneous) (104-7046) | SY | 320 | $175.00 | $30.00 | $14.50 | $65.00 | $20.00 | $17.60 | $50.00 |
| 3 | Remove (6") TRT/untrt base & asphalt pavement (105-7026) | SY | 514 | $20.00 | $11.60 | $9.00 | $7.00 | $12.98 | $12.00 | |
| 4 | Remove (8"-14") TRT/untrt base & asphalt pavement (105-7059) | SY | 1,948 | $31.00 | $20.00 | $14.50 | $11.00 | $11.00 | $12.98 | $15.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 4,804 | $35.00 | $15.00 | $22.20 | $18.00 | $30.00 | $12.98 | $20.00 |
| 6 | Excavation (channel) (110-7002) | CY | 2,214 | $40.00 | $15.00 | $25.60 | $22.00 | $45.00 | $12.98 | $30.00 |
| 7 | Embankment (final)(DC)(type B) (132-7004) | CY | 4,789 | $55.00 | $15.00 | $12.90 | $39.00 | $55.00 | $13.47 | $20.00 |
| 8 | Embankment (final)(DC)(type C) (132-7006) | CY | 1,621 | $40.00 | $37.60 | $35.00 | $55.00 | $13.47 | $15.00 | |
| 9 | Compost manuf topsoil (4") (161-7002) | SY | 4,189 | $7.00 | $9.43 | $3.20 | $3.00 | $9.50 | $10.26 | $10.00 |
| 10 | Straw/hay mulch seed(permanent_rural_clay) (164-7026) | SY | 4,189 | $1.00 | $1.40 | $1.35 | $2.00 | $0.65 | $1.14 | $1.50 |
| 11 | Straw/hay mulch seed (temporary_warm) (164-7029) | SY | 857 | $4.27 | $4.15 | $3.00 | $0.75 | $1.43 | $4.00 | |
| 12 | Straw/hay mulch seed (temporary_cool) (164-7030) | SY | 857 | $5.14 | $4.95 | $3.00 | $0.75 | $1.43 | $5.00 | |
| 13 | Straw/hay mulch seed (temporary_warm_cool) (164-7031) | SY | 2,476 | $1.00 | $1.77 | $1.70 | $3.00 | $0.75 | $1.31 | $2.00 |
| 14 | Vegetative watering (168-7001) | TGL | 106 | $100.00 | $50.00 | $111.00 | $102.00 | $60.00 | $71.50 | $30.00 |
| 15 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 831 | $150.00 | $145.00 | $125.00 | $120.00 | $200.00 | $152.39 | $165.00 |
| 16 | Prime coat (MC-30) (310-7004) | GAL | 721 | $10.00 | $6.00 | $10.90 | $20.00 | $10.00 | $14.58 | $10.00 |
| 17 | Prime coat (multi option) (310-7015) | GAL | 187 | $10.00 | $12.80 | $25.00 | $6.00 | $34.74 | $10.00 | |
| 18 | Asphalt(AC-15P, HFRS-2P or CRS-2P) (316-7070) | GAL | 255 | $8.00 | $11.20 | $25.00 | $6.00 | $34.74 | $10.00 | |
| 19 | Aggregate (type-PB, GR-3 or 3S)(sac-B) (316-7209) | CY | 45 | $185.00 | $195.00 | $625.00 | $1,200.00 | $220.00 | $1,464.79 | $1,100.00 |
| 20 | Aggregate (type-PB, GR-4S or 4)(sac-B) (316-7212) | CY | 39 | $150.00 | $195.00 | $701.00 | $1,300.00 | $190.00 | $1,464.78 | $1,200.00 |
| 21 | Asphalt (multi option) (316-7263) | GAL | 2,521 | $4.50 | $6.00 | $7.00 | $15.00 | $6.00 | $34.74 | $10.00 |
| 22 | Asphalt (multi option) (316-7275) | GAL | 310 | $10.00 | $10.20 | $18.50 | $6.00 | $34.74 | $10.00 | |
| 23 | Cem stabil BKFL (400-7010) | CY | 143 | $250.00 | $185.00 | $290.00 | $586.00 | $295.00 | $81.76 | $250.00 |
| 24 | Temporary special shoring (403-7001) | SF | 841 | $35.00 | $104.00 | $93.00 | $45.00 | $122.50 | $85.00 | |
| 25 | Foundaton loadtest(D4945)(drilld shaft) (405-7003) | EACH | 2 | $28,000 | $36,700 | $25,000 | $30,000 | $13,110 | $25,000 | |
| 26 | Drilled shaft (24 in) (416-7004) | LF | 240 | $295.00 | $184.00 | $340.00 | $185.00 | $299.93 | $385.00 | |
| 27 | Drilled shaft (30 in) (416-7005) | LF | 105 | $325.00 | $222.00 | $495.00 | $250.00 | $304.26 | $570.00 | |
| 28 | Drilled shaft (36 in) (416-7006) | LF | 1,643 | $420.00 | $335.00 | $250.00 | $497.00 | $265.00 | $289.42 | $575.00 |
| 29 | Class C concrete (abutment) (420-7012) | CY | 136.10 | $1,500.00 | $1,202.60 | $1,300.00 | $1,900.00 | $3,050.00 | $1,665.64 | $1,850.00 |
| 30 | Class C concrete (cap) (420-7022) | CY | 61.60 | $1,500.00 | $1,671.60 | $1,520.00 | $3,500.00 | $2,050.00 | $2,912.15 | $2,800.00 |
| 31 | Class C concrete (column) (420-7038) | CY | 48.30 | $1,800.00 | $1,220.80 | $2,060.00 | $3,308.00 | $2,275.00 | $2,831.27 | $1,800.00 |
| 32 | Reinforced concrete slab (422-7001) | SF | 5,070 | $36.97 | $32.50 | $35.00 | $28.00 | $162.33 | $40.00 | |
| 33 | Reinforced concrete slab (slab beam) (422-7007) | SF | 7,280 | $27.00 | $21.46 | $23.00 | $35.00 | $28.00 | $28.75 | $50.00 |
| 34 | Approach slab (422-7013) | CY | 115.70 | $900.00 | $650.00 | $817.00 | $1,350.00 | $925.00 | $1,400.99 | $1,000.00 |
| 35 | Retaining wall (temporary wall) (423-7012) | SF | 6,156 | $24.00 | $54.70 | $116.00 | $50.00 | $86.57 | $45.00 | |
| 36 | Prestressed concrete girder (TX28) (425-7001) | LF | 774 | $250.00 | $306.00 | $375.00 | $280.00 | $274.12 | $275.00 | |
| 37 | Prestressed concrete slab beam (5SB12) (425-7017) | LF | 740 | $250.00 | $250.00 | $287.00 | $398.00 | $280.00 | $251.45 | $300.00 |
| 38 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 642.50 | $250.00 | $283.00 | $350.00 | $280.00 | $277.78 | $285.00 | |
| 39 | Riprap (concrete)(4 in) (432-7001) | CY | 5.40 | $600.00 | $978.00 | $1,263.00 | $1,225.00 | $1,046.01 | $700.00 | |
| 40 | Riprap (mow strip)(4 in) (432-7013) | CY | 103.60 | $700.00 | $495.00 | $818.00 | $950.00 | $1,225.00 | $887.33 | $700.00 |
| 41 | Riprap (stone protection)(12 in) (432-7041) | CY | 1,183 | $320.00 | $150.00 | $184.00 | $180.00 | $185.00 | $229.75 | $350.00 |
| 42 | Riprap (stone protection)(18 in) (432-7043) | CY | 253 | $150.00 | $180.00 | $283.00 | $170.00 | $246.91 | $300.00 | |
| 43 | Rail (type T223) (450-7008) | LF | 1,070 | $175.00 | $95.00 | $98.00 | $210.00 | $235.00 | $231.31 | $250.00 |
| 44 | Armor joint (sealed) (454-7003) | LF | 44 | $180.00 | $251.00 | $212.00 | $265.00 | $193.59 | $275.00 | |
| 45 | Sealed expansion joint (4 in) (SEJ - B) (454-7006) | LF | 50 | $180.00 | $220.00 | $358.00 | $255.00 | $208.45 | $275.00 | |
| 46 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 3 | $35,000 | $35,000 | $20,200 | $57,024 | $73,000 | $46,549 | $65,000 |
| 47 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $80,000 | $95,300 | $57,024 | $110,000 | $101,875 | $90,000 | |
| 48 | Removing structure (abutment) (496-7014) | EACH | 2 | $8,500.00 | $5,290.00 | $23,133 | $4,000.00 | $8,447.76 | $10,000 | |
| 49 | Removing structure (ret wall) (496-7019) | LF | 6,276 | $10.00 | $5.90 | $1.00 | $12.00 | $11.26 | $16.00 | |
| 50 | Mobilization (500-7001) | LS | 1 | $660,827 | $435,000 | $475,000 | $520,000 | $317,626 | $662,602 | $650,000 |
| 51 | Barricades, signs and traffic handling (502-7001) | MO | 33 | $7,000.00 | $3,500.00 | $4,460.00 | $1,500.00 | $3,125.00 | $8,756.95 | $5,000.00 |
| 52 | Portable changeable message sign (503-7001) | DAY | 196 | $100.00 | $200.00 | $91.30 | $80.00 | $365.00 | $171.00 | $75.00 |
| 53 | TMA (stationary) (505-7001) | DAY | 73 | $200.00 | $250.00 | $144.00 | $50.00 | $840.00 | $570.00 | $350.00 |
| 54 | TMA (mobile operation) (505-7002) | HR | 120 | $90.00 | $50.00 | $116.00 | $25.00 | $145.00 | $74.10 | $750.00 |
| 55 | Rock filter dams (install) (type 2) (506-7002) | LF | 400 | $55.00 | $66.96 | $64.60 | $50.00 | $60.00 | $85.50 | $65.00 |
| 56 | Rock filter dams (remove) (506-7011) | LF | 400 | $20.00 | $12.43 | $12.00 | $15.00 | $10.00 | $11.40 | $13.00 |
| 57 | Construction exits (install) (type 1) (506-7020) | SY | 111 | $43.56 | $42.00 | $35.00 | $42.00 | $17.10 | $40.00 | |
| 58 | Construction exits (remove) (506-7024) | SY | 111 | $15.07 | $14.50 | $10.00 | $12.00 | $17.10 | $15.00 | |
| 59 | Temporary sediment control fence (install) (506-7039) | LF | 3,414 | $6.00 | $5.22 | $5.00 | $6.00 | $5.00 | $5.68 | $5.00 |
| 60 | Temporary sediment control fence (remove) (506-7041) | LF | 3,414 | $2.00 | $1.37 | $1.35 | $1.00 | $1.50 | $4.97 | $2.00 |
| 61 | Constructing detours (508-7001) | SY | 45 | $40.00 | $194.00 | $75.00 | $150.00 | $299.54 | $125.00 | |
| 62 | Constructing detours (ebss) (508-7002) | SY | 1,438 | $38.00 | $56.70 | $110.00 | $150.00 | $263.87 | $150.00 | |
| 63 | One-way traffic control (port traffic signal) (510-7003) | MO | 11 | $3,200.00 | $3,250.00 | $1,500.00 | $14,500 | $5,334.35 | $10,000 | |
| 64 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 775 | $35.00 | $21.70 | $38.00 | $95.00 | $30.57 | $100.00 | |
| 65 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 160 | $35.00 | $25.30 | $43.00 | $95.00 | $10.44 | $75.00 | |
| 66 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 775 | $28.00 | $22.50 | $23.00 | $22.00 | $7.77 | $20.00 | |
| 67 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 160 | $28.00 | $21.80 | $17.00 | $22.00 | $7.77 | $45.00 | |
| 68 | PTB (fur&inst)(SSCB or CSB)(type 1)or(steel) (512-7085) | LF | 571 | $30.00 | $18.70 | $18.00 | $90.00 | $30.94 | $60.00 | |
| 69 | PTB (remove)(SSCB or CSB)(type 1)or(steel) (512-7088) | LF | 571 | $30.00 | $18.50 | $18.00 | $16.00 | $46.41 | $55.00 | |
| 70 | Metal W-beam guard fence (steel post) (540-7002) | LF | 300 | $48.00 | $33.70 | $32.50 | $31.00 | $36.00 | $35.34 | $35.00 |
| 71 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 12 | $2,500.00 | $2,886.40 | $3,130.00 | $2,624.00 | $3,100.00 | $3,021.00 | $2,750.00 |
| 72 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 4 | $1,818.30 | $1,750.00 | $1,653.00 | $1,900.00 | $1,892.40 | $1,850.00 | |
| 73 | Guardrail end treatment (install) (544-7001) | EACH | 16 | $3,500.00 | $3,763.10 | $3,630.00 | $3,421.00 | $4,000.00 | $3,933.00 | $3,500.00 |
| 74 | Wire fence (type C) (552-7003) | LF | 203 | $51.70 | $49.90 | $47.00 | $17.00 | $53.58 | $50.00 | |
| 75 | Wire fence (remove) (552-7011) | LF | 203 | $4.40 | $4.25 | $4.00 | $6.00 | $4.56 | $4.00 | |
| 76 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 6 | $1,650.00 | $1,590.00 | $1,500.00 | $1,800.00 | $1,710.00 | $1,600.00 | |
| 77 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $275.00 | $265.00 | $250.00 | $290.00 | $285.00 | $275.00 | |
| 78 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 4 | $82.50 | $79.60 | $75.00 | $90.00 | $85.50 | $80.00 | |
| 79 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016) | EACH | 4 | $55.00 | $53.00 | $50.00 | $60.00 | $57.00 | $50.00 | |
| 80 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 5,040 | $0.59 | $0.57 | $1.00 | $1.00 | $0.62 | $0.75 | |
| 81 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 48 | $27.50 | $26.50 | $25.00 | $3.50 | $28.50 | $25.00 | |
| 82 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 1,440 | $1.21 | $1.15 | $1.15 | $1.80 | $1.25 | $1.25 | |
| 83 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 1,020 | $8.25 | $8.00 | $8.00 | $7.00 | $8.55 | $8.00 | |
| 84 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 49 | $27.50 | $26.50 | $25.00 | $3.00 | $28.50 | $25.00 | |
| 85 | Pavement surface preparation for marking (6") (678-7002) | LF | 390 | $3.30 | $3.20 | $3.00 | $78.00 | $3.42 | $3.00 | |
| 86 | Tip testing(drilled shaft) (4003-7001) | EACH | 3 | $4,200.00 | $6,070.00 | $8,500.00 | $12,325 | $14,440 | $10,000 | |
| 87 | Temporary construction access (4006-7001) | LS | 1 | $65,000 | $78,200 | $12,500 | $215,000 | $79,281 | $165,000 | |
| 88 | Temporary detour bridge (4012-7001) | EACH | 1 | $185,000 | $285,000 | $195,000 | $315,000 | $285,770 | $450,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way