TxDOT contract A00186047 bid tabulation
Bridge Replacement, COUNTY ROAD 325 (FCR 461 @ Hog Creek to (MAP #2064)). Let by Texas DOT on April 7, 2026, Falls, Waco District. 12 bids received; low bid $1,047,281 by Blacksmith Ventures LLC, -25% against the engineer's estimate of $1,388,814.
- Owner
- Texas DOT
- Letting
- 07 APR 2026
- Pay items
- 46
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Blacksmith Ventures LLC | $1,047,281 | Low | -25% |
| 2 | Skyline Bridge LLC | $1,087,358 | +4.0% | -22% |
| 3 | Knife River Corporation - South | $1,137,696 | +9.0% | -18% |
| 4 | Hodges and Son Construction Company, Inc. | $1,141,772 | +9.0% | -18% |
| 5 | Garret Shields Infrastructure | $1,173,570 | +12% | -15% |
| 6 | C & W Southern LLC | $1,273,226 | +22% | -8.0% |
| 7 | R Construction Civil, LLC | $1,328,617 | +27% | -4.0% |
| 8 | Big Creek Construction, LTD. | $1,338,188 | +28% | -4.0% |
| 9 | Tucan Contracting, LLC | $1,360,924 | +30% | -2.0% |
| 10 | Jordan Foster Construction, LLC | $1,374,444 | +31% | -1.0% |
| 11 | E-Z Bel Construction, LLC | $1,663,163 | +59% | +20% |
| 12 | James Construction Group, LLC | $1,742,525 | +66% | +25% |
Engineer's estimate: $1,388,814.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Blacksmith Ventures LLC | 2. Skyline Bridge LLC | 3. Knife River Corporation - South | 4. Hodges and Son Construction Company, Inc. | 5. Garret Shields Infrastructure | 6. C & W Southern LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 6.51 | $2,250.00 | $1,000.00 | $465.00 | $3,750.00 | $2,300.00 | $1,000.00 | $3,000.00 |
| 2 | Remove (0"-10") TRT/untrt base & asphalt pavement (105-7050) | SY | 1,450 | $8.00 | $18.96 | $6.75 | $5.05 | $5.00 | $7.00 | $15.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 98 | $30.00 | $1.00 | $14.00 | $40.00 | $35.00 | $40.00 | $45.00 |
| 4 | Excavation (channel) (110-7002) | CY | 1,819 | $23.00 | $1.00 | $10.50 | $10.00 | $12.00 | $40.00 | $15.00 |
| 5 | Embankment (final)(OC)(type B) (132-7003) | CY | 1,266 | $35.00 | $38.00 | $31.00 | $10.00 | $12.00 | $40.00 | $20.00 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 3,909 | $1.00 | $0.25 | $4.25 | $0.65 | $2.00 | $5.00 | $5.00 |
| 7 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 3,909 | $1.00 | $0.25 | $0.80 | $0.75 | $1.00 | $0.20 | $0.50 |
| 8 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 3,909 | $0.50 | $0.25 | $0.80 | $0.65 | $1.00 | $0.10 | $0.50 |
| 9 | Vegetative watering (168-7001) | TGL | 64 | $25.00 | $0.25 | $1.00 | $30.00 | $1.00 | $25.00 | $5.00 |
| 10 | Soil ret BLKT(chan_temporary_2 PSF) (169-7029) | SY | 783 | $4.00 | $2.00 | $4.25 | $5.25 | $2.50 | $2.00 | $2.50 |
| 11 | Proof rolling (216-7001) | HR | 10 | $120.00 | $200.00 | $100.00 | $1.00 | $1.00 | $100.00 | $250.00 |
| 12 | FL BS (compacted in place)(type D GR 3)(final pos) (247-7189) | CY | 308 | $75.00 | $100.00 | $130.00 | $82.00 | $90.00 | $25.00 | $118.50 |
| 13 | Emuls asphalt (BS or subgr TRT)(CSS-1H) (314-7004) | GAL | 2,218 | $4.00 | $15.00 | $8.50 | $1.00 | $5.00 | $8.00 | $15.00 |
| 14 | Cem stabil BKFL (400-7010) | CY | 229 | $187.00 | $185.00 | $265.00 | $285.00 | $225.00 | $180.00 | $350.00 |
| 15 | Trench excavation protection (402-7001) | LF | 26 | $1.00 | $30.00 | $20.00 | $1.00 | $10.00 | $80.00 | |
| 16 | Temporary special shoring (403-7001) | SF | 1,197 | $25.00 | $26.00 | $4.00 | $1.00 | $35.00 | $15.00 | |
| 17 | Drilled shaft (18 in) (416-7002) | LF | 104 | $300.00 | $165.00 | $88.00 | $200.00 | $150.00 | $300.00 | $145.00 |
| 18 | Drilled shaft (36 in) (416-7006) | LF | 259 | $350.00 | $186.00 | $250.00 | $300.00 | $200.00 | $300.00 | $218.00 |
| 19 | Class C concrete (abutment) (420-7012) | CY | 49.30 | $1,800.00 | $1,200.00 | $875.00 | $1,100.00 | $1,000.00 | $1,000.00 | $1,200.00 |
| 20 | Class C concrete (cap) (420-7022) | CY | 18.30 | $1,600.00 | $1,000.00 | $1,450.00 | $1,200.00 | $1,200.00 | $1,200.00 | $2,250.00 |
| 21 | Class C concrete (column) (420-7038) | CY | 6.50 | $1,120.00 | $1,300.00 | $1,880.00 | $1,900.00 | $1,800.00 | $1,200.00 | $2,500.00 |
| 22 | Reinforced concrete slab (422-7001) | SF | 2,600 | $33.00 | $23.00 | $24.75 | $35.75 | $34.00 | $25.00 | $35.00 |
| 23 | Prestressed concrete girder (TX28) (425-7001) | LF | 395.17 | $275.00 | $267.00 | $270.00 | $300.00 | $250.00 | $250.00 | $326.00 |
| 24 | Riprap (stone protection)(18 in) (432-7043) | CY | 991 | $140.00 | $150.00 | $140.00 | $110.00 | $175.00 | $150.00 | $100.00 |
| 25 | Rail (type T223) (450-7008) | LF | 388 | $175.00 | $75.00 | $112.00 | $145.00 | $150.00 | $200.00 | $250.00 |
| 26 | Type A joint (454-7001) | LF | 69 | $180.00 | $75.00 | $60.00 | $54.00 | $45.00 | $50.00 | $25.00 |
| 27 | Concrete box culvert (9 FT X 8 FT) (462-7030) | LF | 52 | $961.00 | $1,180.00 | $1,650.00 | $1,600.00 | $1,200.00 | $1,000.00 | |
| 28 | Wingwall (PW - 1) (HW=10 FT) (466-7180) | EACH | 2 | $21,000 | $24,500 | $39,500 | $50,000 | $15,000 | $40,000 | |
| 29 | Removing structure (pipe) (496-7007) | LF | 280 | $16.00 | $12.00 | $10.00 | $35.00 | $18.00 | $10.00 | $50.00 |
| 30 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $15,000 | $1,000.00 | $7,000.00 | $10,000 | $15,000 | $10,000 | $5,000.00 |
| 31 | Mobilization (500-7001) | LS | 1 | $130,000 | $136,000 | $90,000 | $110,000 | $100,000 | $100,000 | $120,000 |
| 32 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $6,400.00 | $1,100.00 | $1,600.00 | $750.00 | $1,500.00 | $5,000.00 | $1,500.00 |
| 33 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $13,000 | $8,750.00 | $5,000.00 | $14,000 | $1,000.00 | $9,000.00 |
| 34 | Rock filter dams (install) (type 2) (506-7002) | LF | 187 | $45.00 | $10.00 | $35.00 | $40.00 | $1.00 | $20.00 | $30.00 |
| 35 | Rock filter dams (install) (type 3) (506-7003) | LF | 96 | $90.00 | $10.00 | $38.00 | $79.00 | $1.00 | $20.00 | $50.00 |
| 36 | Rock filter dams (remove) (506-7011) | LF | 283 | $12.00 | $0.25 | $7.00 | $10.00 | $1.00 | $5.00 | $10.00 |
| 37 | Temporary sediment control fence (install) (506-7039) | LF | 2,200 | $5.00 | $3.00 | $3.25 | $5.25 | $1.00 | $5.00 | $2.00 |
| 38 | Temporary sediment control fence (remove) (506-7041) | LF | 2,200 | $1.00 | $0.25 | $1.50 | $1.25 | $1.00 | $1.00 | $1.00 |
| 39 | Metal W-beam guard fence (steel post) (540-7002) | LF | 522 | $38.00 | $30.50 | $34.50 | $31.00 | $30.00 | $35.00 | $29.50 |
| 40 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 8 | $1,100.00 | $1,555.00 | $1,350.00 | $1,400.00 | $1,400.00 | $1,000.00 | $1,275.00 |
| 41 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,450.00 | $1,620.00 | $1,450.00 | $1,300.00 | $1,500.00 | $1,500.00 | $1,350.00 |
| 42 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,560.00 | $3,115.00 | $3,500.00 | $3,100.00 | $3,300.00 | $3,500.00 | $3,300.00 |
| 43 | Wire fence (type C) (552-7003) | LF | 565 | $10.00 | $7.00 | $27.00 | $15.00 | $18.00 | $8.00 | $15.00 |
| 44 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 10 | $25.00 | $2.00 | $47.75 | $21.00 | $45.00 | $30.00 | $45.00 |
| 45 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 29 | $45.00 | $65.00 | $47.75 | $48.00 | $45.00 | $30.00 | $45.00 |
| 46 | Driftwood removal (735-7061) | LS | 1 | $5,000.00 | $1.00 | $4,000.00 | $2,500.00 | $1,000.00 | $5,000.00 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.