TxDOT contract A00190263 bid tabulation
Highway Improvement, FM 812 (0.19 MI NW Old San Antonio/Watts Lane to 0.19 MI SE of Artesian Drive). Let by Texas DOT on June 4, 2025, Bastrop, Austin District. 7 bids received; low bid $7,601,604 by Dan Williams Company, -3.9% against the engineer's estimate of $7,909,276.
- Owner
- Texas DOT
- Letting
- 04 JUN 2025
- Pay items
- 129
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Dan Williams Company | $7,601,604 | Low | -4.0% |
| 2 | Hunter Industries, LTD. | $7,755,026 | +2.0% | -2.0% |
| 3 | Acme Bridge Company, Inc. | $8,552,546 | +13% | +8.0% |
| 4 | C. E. Barker, LTD. | $8,686,090 | +14% | +10% |
| 5 | Dean Word Company, LTD. | $9,092,000 | +20% | +15% |
| 6 | Aaron Concrete Contractors, LLC | $9,664,286 | +27% | +22% |
| 7 | Joe Bland Construction LLC | $9,735,608 | +28% | +23% |
Engineer's estimate: $7,909,276.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Dan Williams Company | 2. Hunter Industries, LTD. | 3. Acme Bridge Company, Inc. | 4. C. E. Barker, LTD. | 5. Dean Word Company, LTD. | 6. Aaron Concrete Contractors, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 156.10 | $2,000.00 | $2,500.00 | $2,697.31 | $1,370.00 | $5,500.00 | $1,150.00 | $650.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 12,219 | $20.50 | $17.00 | $24.70 | $22.40 | $26.03 | $34.35 | $31.00 |
| 3 | Embankment (final)(OC)(type B) (132-7003) | CY | 5,214 | $20.00 | $25.00 | $24.70 | $10.10 | $27.84 | $29.65 | $10.00 |
| 4 | Embankment (final)(OC)(type C) (132-7005) | CY | 1,613 | $50.00 | $48.50 | $87.01 | $58.90 | $27.84 | $133.25 | $100.00 |
| 5 | Furn & place topsoil (4") (160-7002) | SY | 52,742 | $2.00 | $1.25 | $1.62 | $1.59 | $2.17 | $2.30 | $1.90 |
| 6 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 52,742 | $0.30 | $0.17 | $0.17 | $0.12 | $0.12 | $0.30 | $0.15 |
| 7 | Drill seed (permanent_rural_clay) (164-7010) | SY | 52,742 | $0.35 | $0.20 | $0.20 | $0.16 | $0.15 | $0.30 | $0.18 |
| 8 | Vegetative watering (168-7001) | TGL | 886 | $42.50 | $8.00 | $24.50 | $39.40 | $61.39 | $163.60 | $35.00 |
| 9 | Soil ret BLKT(SL_mod_clay_long) (169-7002) | SY | 52,742 | $1.40 | $1.75 | $1.70 | $0.80 | $0.79 | $1.00 | $1.00 |
| 10 | FL BS (compacted in place)(type D GR 5)(final pos) (247-7191) | CY | 11,487 | $69.00 | $55.00 | $70.95 | $84.30 | $74.34 | $86.65 | $95.00 |
| 11 | Prime coat (multi option) (310-7015) | GAL | 8,726 | $5.25 | $3.50 | $4.82 | $3.65 | $3.61 | $5.50 | $4.30 |
| 12 | D-GR HMA type-B PG64-22 (341-7001) | TON | 4,484 | $122.50 | $130.00 | $115.90 | $127.00 | $125.78 | $116.80 | $150.00 |
| 13 | D-GR HMA type D PG76-22 (341-7056) | TON | 2,799 | $140.00 | $170.00 | $121.40 | $173.00 | $171.15 | $135.75 | $205.00 |
| 14 | D-GR HMA type D PG76-22 (level-UP) (341-7059) | TON | 2,046 | $152.50 | $150.00 | $123.80 | $148.00 | $146.40 | $152.90 | $175.00 |
| 15 | Tom-C PG76-22 sac-B (347-7002) | TON | 4,051 | $162.50 | $160.00 | $157.70 | $158.00 | $156.71 | $142.90 | $187.00 |
| 16 | Struct excavation (box) (400-7002) | CY | 428 | $27.00 | $1.00 | $100.40 | $15.50 | $56.71 | $54.00 | $165.00 |
| 17 | Flowable backfill (401-7001) | CY | 83 | $375.00 | $250.00 | $334.67 | $439.00 | $219.86 | $261.40 | $268.00 |
| 18 | Trench excavation protection (402-7001) | LF | 146 | $85.00 | $1.00 | $18.96 | $10.30 | $56.96 | $179.55 | $6.00 |
| 19 | Temporary special shoring (403-7001) | SF | 6,762 | $37.50 | $7.00 | $7.00 | $35.20 | $5.16 | $4.70 | $31.00 |
| 20 | Temporary special shoring (cofferdam) (403-7002) | SF | 600 | $100.00 | $15.00 | $100.00 | $24.80 | $36.09 | $222.85 | $61.00 |
| 21 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 22 | $375.00 | $350.00 | $496.80 | $501.00 | $465.72 | $533.55 | $403.00 |
| 22 | Riprap (concrete)(4 in) (432-7001) | CY | 2.37 | $1,700.00 | $1,500.00 | $1,673.70 | $776.00 | $881.51 | $1,589.95 | $932.00 |
| 23 | Riprap (concrete)(5 in) (432-7002) | CY | 920 | $500.00 | $450.00 | $585.79 | $569.00 | $701.08 | $616.90 | $854.00 |
| 24 | Riprap (mow strip)(4 in) (432-7013) | CY | 224 | $550.00 | $700.00 | $613.69 | $776.00 | $520.66 | $795.95 | $936.00 |
| 25 | Riprap (stone protection)(15 in) (432-7042) | CY | 28 | $350.00 | $270.00 | $250.00 | $569.00 | $283.53 | $246.50 | $357.00 |
| 26 | Concrete box culvert (9 FT X 8 FT) (462-7030) | LF | 116 | $1,400.00 | $1,500.00 | $1,697.94 | $1,760.00 | $1,331.77 | $2,178.70 | $1,460.00 |
| 27 | Concrete box culvert (10 FT X 9 FT) (462-7037) | LF | 30 | $2,500.00 | $2,500.00 | $2,570.25 | $2,120.00 | $1,577.31 | $3,156.90 | $1,820.00 |
| 28 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,838 | $90.00 | $70.00 | $109.32 | $93.10 | $184.23 | $81.95 | $120.00 |
| 29 | RC pipe (CL IV)(24 in) (464-7021) | LF | 27 | $300.00 | $370.00 | $139.45 | $136.00 | $194.42 | $885.00 | $654.00 |
| 30 | RC pipe (CL IV)(30 in) (464-7023) | LF | 13 | $400.00 | $435.00 | $390.45 | $204.00 | $211.04 | $1,024.00 | $752.00 |
| 31 | RC pipe (arch)(CL III)(des 1) (464-7040) | LF | 138 | $250.00 | $160.00 | $273.31 | $295.00 | $283.41 | $220.60 | $310.00 |
| 32 | Wingwall (PW - 1) (HW=10 FT) (466-7180) | EACH | 1 | $70,000 | $50,000 | $52,097 | $44,100 | $36,085 | $81,626 | $94,000 |
| 33 | Wingwall (PW - 1) (HW=12 FT) (466-7182) | EACH | 1 | $99,000 | $68,000 | $66,376 | $51,100 | $36,085 | $115,511 | $118,000 |
| 34 | Headwall (CH - PW - 0)(diameter= 24 in)(mod) (466-7217) | EACH | 3 | $8,500.00 | $19,000 | $35,140 | $14,000 | $21,651 | $57,615 | $10,800 |
| 35 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 94 | $1,450.00 | $2,600.00 | $1,840.68 | $1,430.00 | $3,260.02 | $1,925.80 | $2,000.00 |
| 36 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 1 | $3,250.00 | $2,500.00 | $3,625.57 | $1,790.00 | $3,371.37 | $2,607.50 | $1,625.00 |
| 37 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $3,250.00 | $2,600.00 | $3,904.46 | $2,010.00 | $3,468.28 | $2,578.35 | $2,560.00 |
| 38 | Set (type II) (30 in) (RCP) (3: 1) (C) (467-7345) | EACH | 2 | $3,250.00 | $3,500.00 | $3,569.80 | $2,530.00 | $3,781.71 | $3,318.50 | $3,300.00 |
| 39 | Adjusting manholes (479-7001) | EACH | 1 | $6,500.00 | $3,200.00 | $6,900.00 | $9,980.00 | $541.28 | $13,688 | $6,340.00 |
| 40 | Removing structure (set) (496-7004) | EACH | 74 | $525.00 | $400.00 | $669.34 | $569.00 | $360.85 | $826.80 | $760.00 |
| 41 | Removing structure (headwall) (496-7006) | EACH | 3 | $2,250.00 | $2,250.00 | $2,454.23 | $1,600.00 | $5,412.75 | $4,378.85 | $3,500.00 |
| 42 | Removing structure (pipe) (496-7007) | LF | 1,322 | $22.50 | $18.00 | $27.89 | $23.80 | $21.65 | $16.95 | $36.00 |
| 43 | Mobilization (500-7001) | LS | 1 | $639,300 | $750,000 | $647,077 | $800,000 | $765,000 | $650,000 | $975,000 |
| 44 | Barricades, signs and traffic handling (502-7001) | MO | 19 | $7,500.00 | $15,000 | $8,129.72 | $36,110 | $1,773.32 | $9,867.00 | $2,300.00 |
| 45 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $12,500 | $7,876.99 | $15,000 | $20,620 | $21,974 | $10,500 |
| 46 | TMA (stationary) (505-7001) | DAY | 25 | $300.00 | $450.00 | $210.05 | $260.00 | $1,031.00 | $534.25 | $640.00 |
| 47 | TMA (mobile operation) (505-7002) | HR | 20 | $150.00 | $75.00 | $105.03 | $119.00 | $154.65 | $144.90 | $100.00 |
| 48 | Rock filter dams (install) (type 2) (506-7002) | LF | 191 | $42.50 | $47.50 | $47.50 | $61.10 | $60.93 | $68.45 | $72.00 |
| 49 | Rock filter dams (install) (type 4) (506-7004) | LF | 100 | $80.00 | $90.00 | $90.00 | $72.50 | $72.26 | $81.45 | $86.00 |
| 50 | Rock filter dams (remove) (506-7011) | LF | 291 | $12.50 | $22.50 | $22.50 | $21.50 | $21.46 | $24.15 | $25.00 |
| 51 | Temporary sediment control fence (install) (506-7039) | LF | 6,213 | $5.52 | $4.00 | $3.65 | $3.75 | $3.74 | $4.20 | $4.50 |
| 52 | Temporary sediment control fence (remove) (506-7041) | LF | 6,213 | $1.25 | $1.00 | $0.50 | $1.10 | $1.10 | $1.30 | $1.30 |
| 53 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 100 | $7.88 | $8.00 | $7.50 | $12.80 | $12.73 | $14.45 | $15.00 |
| 54 | Biodegradable erosion control logs (remove) (506-7046) | LF | 100 | $2.69 | $1.00 | $1.00 | $1.55 | $1.54 | $1.80 | $1.80 |
| 55 | Constructing detours (508-7001) | SY | 929 | $150.00 | $150.00 | $76.70 | $139.00 | $118.57 | $183.25 | $152.00 |
| 56 | One-way traffic control (port traffic signal) (510-7003) | MO | 4 | $8,500.00 | $5,000.00 | $4,588.38 | $4,200.00 | $6,186.00 | $10,890 | $19,600 |
| 57 | PTB (fur&inst)(SSCB or CSB)(type 1)or(steel) (512-7085) | LF | 1,410 | $55.00 | $20.00 | $30.00 | $15.20 | $80.93 | $30.15 | $89.00 |
| 58 | PTB (move)(SSCB or CSB)(type 1)or(steel) (512-7086) | LF | 1,500 | $30.00 | $7.00 | $15.00 | $17.30 | $10.83 | $9.70 | $29.00 |
| 59 | PTB (remove)(SSCB or CSB)(type 1)or(steel) (512-7088) | LF | 1,410 | $25.00 | $12.00 | $13.00 | $15.00 | $21.14 | $17.95 | $33.00 |
| 60 | Intersections (ACP) (530-7002) | SY | 2,095 | $70.00 | $80.00 | $74.99 | $94.70 | $52.58 | $83.95 | $94.00 |
| 61 | Driveways (concrete) (530-7006) | SY | 122 | $150.00 | $125.00 | $102.65 | $109.00 | $53.61 | $176.25 | $31.00 |
| 62 | Driveways (ACP) (530-7010) | SY | 2,059 | $67.50 | $80.00 | $61.70 | $91.00 | $56.71 | $189.75 | $95.00 |
| 63 | Metal W-beam guard fence (timber post) (540-7001) | LF | 4,037.50 | $25.50 | $23.00 | $28.36 | $24.80 | $25.03 | $27.85 | $38.00 |
| 64 | Downstream anchor terminal section (540-7015) | EACH | 10 | $1,700.00 | $1,500.00 | $1,325.44 | $1,400.00 | $1,486.57 | $1,566.00 | $2,150.00 |
| 65 | Remove metal beam guard fence (542-7001) | LF | 925 | $6.00 | $4.00 | $3.18 | $2.60 | $8.25 | $3.00 | $7.00 |
| 66 | Remove downstream anchor terminal (542-7003) | EACH | 6 | $150.00 | $300.00 | $249.18 | $259.00 | $154.91 | $290.05 | $182.00 |
| 67 | Guardrail end treatment (install) (544-7001) | EACH | 10 | $3,500.00 | $4,500.00 | $3,234.06 | $3,100.00 | $3,734.73 | $3,479.90 | $4,900.00 |
| 68 | Guardrail end treatment (remove) (544-7003) | EACH | 6 | $500.00 | $300.00 | $360.52 | $259.00 | $428.40 | $290.05 | $370.00 |
| 69 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 8 | $1,250.00 | $1,000.00 | $1,776.08 | $853.00 | $1,704.00 | $992.70 | $1,280.00 |
| 70 | Crash cushion attenuator (remove) (545-7004) | EACH | 6 | $800.00 | $850.00 | $858.88 | $1,280.00 | $1,224.23 | $641.35 | $875.00 |
| 71 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 6 | $9,000.00 | $6,500.00 | $8,562.32 | $7,190.00 | $9,498.16 | $8,153.50 | $12,700 |
| 72 | Wire fence (type A) (552-7001) | LF | 100 | $35.00 | $45.00 | $36.53 | $35.60 | $51.55 | $39.80 | $42.00 |
| 73 | Wire fence (type C) (552-7003) | LF | 100 | $35.00 | $45.00 | $38.97 | $38.00 | $51.55 | $42.60 | $45.00 |
| 74 | Gate (type 1) (552-7006) | EACH | 2 | $1,000.00 | $1,250.00 | $980.82 | $956.00 | $515.50 | $1,073.05 | $1,130.00 |
| 75 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 14 | $310.00 | $325.00 | $339.31 | $233.00 | $231.98 | $365.50 | $275.00 |
| 76 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 2 | $400.00 | $325.00 | $381.73 | $269.00 | $268.06 | $365.50 | $320.00 |
| 77 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 16 | $900.00 | $775.00 | $954.31 | $620.00 | $618.60 | $887.30 | $735.00 |
| 78 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 200 | $25.00 | $40.00 | $32.00 | $34.80 | $16.74 | $37.15 | $54.00 |
| 79 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 115 | $25.00 | $41.00 | $45.00 | $49.00 | $16.74 | $52.30 | $55.00 |
| 80 | Electrical conductor (no.8) bare (620-7007) | LF | 750 | $1.90 | $3.00 | $2.70 | $2.95 | $2.30 | $3.20 | $4.00 |
| 81 | Electrical conductor (no.8) insulated (620-7008) | LF | 1,260 | $2.00 | $4.00 | $2.70 | $2.95 | $2.61 | $3.20 | $5.40 |
| 82 | Electrical conductor (no.6) bare (620-7009) | LF | 60 | $2.75 | $4.00 | $3.35 | $3.65 | $2.74 | $4.00 | $5.40 |
| 83 | Electrical conductor (no.6) insulated (620-7010) | LF | 120 | $2.75 | $5.00 | $3.35 | $3.65 | $5.16 | $4.00 | $6.70 |
| 84 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 29 | $685.00 | $525.00 | $726.34 | $672.00 | $670.15 | $602.05 | $800.00 |
| 85 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 19 | $950.00 | $625.00 | $842.98 | $724.00 | $721.70 | $695.85 | $860.00 |
| 86 | Install small roadside sign support and assembly type 10BWG(1)SA(T-2EXT) (644-7005) | EACH | 4 | $850.00 | $675.00 | $922.50 | $801.00 | $799.03 | $770.30 | $850.00 |
| 87 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 2 | $1,000.00 | $825.00 | $1,187.59 | $905.00 | $902.13 | $946.55 | $1,070.00 |
| 88 | Install small roadside sign support and assembly TYS80(1)SA(T-2EXT) (644-7029) | EACH | 2 | $1,100.00 | $850.00 | $1,214.10 | $977.00 | $974.30 | $981.40 | $1,160.00 |
| 89 | Remove SM RD SN sup&AM (644-7073) | EACH | 122 | $160.00 | $100.00 | $106.03 | $103.00 | $103.10 | $86.95 | $123.00 |
| 90 | Install delineator assembly (D-SW)SZ 2(WC)GND(BI) (658-7010) | EACH | 4 | $100.00 | $35.00 | $77.41 | $56.90 | $56.71 | $40.60 | $67.00 |
| 91 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 59 | $65.00 | $35.00 | $48.78 | $46.50 | $46.40 | $28.85 | $55.00 |
| 92 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 10,134 | $0.50 | $0.35 | $0.35 | $0.36 | $1.55 | $0.50 | $0.45 |
| 93 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 300 | $1.50 | $0.55 | $0.55 | $0.41 | $2.06 | $0.50 | $0.50 |
| 94 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 87 | $4.00 | $12.00 | $12.00 | $5.20 | $6.70 | $5.70 | $6.10 |
| 95 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 2 | $100.00 | $275.00 | $275.00 | $103.00 | $139.19 | $115.95 | $122.00 |
| 96 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 2 | $100.00 | $350.00 | $350.00 | $103.00 | $170.12 | $115.95 | $122.00 |
| 97 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 210 | $2.00 | $0.42 | $0.42 | $0.57 | $2.06 | $0.80 | $0.70 |
| 98 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 10,716 | $0.50 | $0.35 | $0.35 | $0.36 | $1.55 | $0.50 | $0.40 |
| 99 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 15 | $3.00 | $2.50 | $1.63 | $17.10 | $0.93 | $3.70 | $0.90 |
| 100 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 2,064 | $1.75 | $2.50 | $1.63 | $1.75 | $0.93 | $3.70 | $1.90 |
| 101 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 300 | $1.50 | $1.30 | $1.30 | $1.40 | $2.06 | $1.50 | $1.70 |
| 102 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 118 | $12.00 | $13.50 | $13.50 | $6.70 | $6.70 | $7.50 | $8.00 |
| 103 | Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041) | EACH | 6 | $225.00 | $325.00 | $325.00 | $181.00 | $139.19 | $202.90 | $215.00 |
| 104 | Reflectorized pavement marking type I (W)(word)(090MIL) (666-7065) | EACH | 2 | $275.00 | $395.00 | $395.00 | $207.00 | $170.12 | $232.05 | $245.00 |
| 105 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 30,084 | $0.40 | $0.23 | $0.23 | $0.31 | $0.67 | $0.30 | $0.40 |
| 106 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 300 | $1.00 | $0.32 | $0.32 | $0.41 | $1.03 | $0.50 | $0.50 |
| 107 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 118 | $4.00 | $2.58 | $2.50 | $4.15 | $3.09 | $4.70 | $5.00 |
| 108 | Reflectorized pavement marking type II (W) (arrow) (666-7186) | EACH | 6 | $85.00 | $25.00 | $25.00 | $85.30 | $103.10 | $95.60 | $100.00 |
| 109 | Reflectorized pavement marking type II (W) (word) (666-7194) | EACH | 2 | $100.00 | $35.00 | $35.00 | $95.70 | $103.10 | $107.30 | $113.00 |
| 110 | Reflectorized pavement marking type II (Y) 6" (broken) (666-7211) | LF | 6,860 | $1.00 | $0.25 | $0.25 | $0.41 | $0.67 | $0.50 | $0.50 |
| 111 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 31,037 | $0.65 | $0.23 | $0.23 | $0.31 | $0.67 | $0.30 | $0.40 |
| 112 | Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265) | LF | 30,084 | $1.25 | $1.20 | $1.20 | $1.05 | $1.55 | $1.30 | $1.20 |
| 113 | Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269) | LF | 31,037 | $1.30 | $1.20 | $1.20 | $1.05 | $1.55 | $1.30 | $1.20 |
| 114 | Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273) | LF | 6,860 | $1.40 | $1.30 | $1.30 | $1.05 | $2.06 | $1.30 | $1.20 |
| 115 | Reflectorized pavement marker type I-C (672-7002) | EACH | 16 | $10.00 | $8.00 | $8.00 | $6.20 | $8.25 | $7.00 | $7.40 |
| 116 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 606 | $10.00 | $7.25 | $7.25 | $6.20 | $5.67 | $7.00 | $7.40 |
| 117 | Eliminating existing PM & markers (4") (677-7001) | LF | 8,400 | $1.50 | $0.95 | $0.95 | $0.57 | $0.52 | $0.80 | $0.80 |
| 118 | Install highway traffic signal (system) (680-7003) | EACH | 1 | $27,500 | $20,000 | $13,000 | $14,100 | $37,547 | $15,079 | $18,800 |
| 119 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 8 | $375.00 | $475.00 | $420.00 | $457.00 | $341.33 | $487.25 | $638.00 |
| 120 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 8 | $375.00 | $475.00 | $420.00 | $457.00 | $341.33 | $487.25 | $638.00 |
| 121 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 8 | $375.00 | $475.00 | $420.00 | $457.00 | $341.33 | $487.25 | $638.00 |
| 122 | Backplate W/reflectorized border(3 sec) (682-7054) | EACH | 8 | $200.00 | $243.00 | $190.00 | $207.00 | $232.66 | $220.35 | $326.00 |
| 123 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 1,006 | $2.50 | $5.00 | $3.00 | $3.25 | $2.56 | $3.50 | $6.70 |
| 124 | Install RDSD FLSH BCN assembly (solar PWRD) (685-7004) | EACH | 2 | $12,000 | $9,000.00 | $9,900.00 | $10,800 | $7,294.48 | $11,484 | $10,500 |
| 125 | Ins traffic signal PL AM(S)1 arm(24')lum (686-7027) | EACH | 2 | $12,000 | $21,500 | $13,200 | $14,400 | $15,435 | $15,311 | $24,400 |
| 126 | Bonding course (3007-7001) | GAL | 13,363 | $4.50 | $3.50 | $3.66 | $3.65 | $3.61 | $13.00 | $4.30 |
| 127 | Geogrid reinforce embankments (type A) (5000-7001) | SY | 8,959 | $10.00 | $3.00 | $2.02 | $5.50 | $3.53 | $4.00 | $8.15 |
| 128 | RVDS (presence detection only) (6008-7001) | EACH | 4 | $8,000.00 | $8,500.00 | $8,800.00 | $9,580.00 | $8,043.13 | $10,208 | $9,500.00 |
| 129 | RVDS (advance detection only) (6008-7002) | EACH | 2 | $8,000.00 | $8,500.00 | $13,800 | $15,000 | $13,150 | $16,008 | $9,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.