TxDOT contract A00195465 bid tabulation
Bridge Replacement, IH 40 (At IH 40 to .). Let by Texas DOT on February 7, 2025, Carson, Amarillo District. 6 bids received; low bid $9,874,035 by Altus Construction LLC, -6.9% against the engineer's estimate of $10,602,018.
- Owner
- Texas DOT
- Letting
- 07 FEB 2025
- Pay items
- 82
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Altus Construction LLC | $9,874,035 | Low | -7.0% |
| 2 | Coppell Construction Co., Inc. | $10,755,504 | +9.0% | +1.0% |
| 3 | Gilvin-Terrill, LTD. | $12,135,414 | +23% | +14% |
| 4 | Earth Builders, L.P. | $15,148,853 | +53% | +43% |
| 5 | C. E. Barker, LTD. | $15,401,568 | +56% | +45% |
| 6 | Hodges and Son Construction Company, Inc. | $16,788,394 | +70% | +58% |
Engineer's estimate: $10,602,018.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Altus Construction LLC | 2. Coppell Construction Co., Inc. | 3. Gilvin-Terrill, LTD. | 4. Earth Builders, L.P. | 5. C. E. Barker, LTD. | 6. Hodges and Son Construction Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 1,591 | $30.00 | $37.29 | $16.00 | $25.00 | $10.00 | $46.13 | $15.00 |
| 2 | Removing concrete (traffic barrier) (104-7035) | LF | 92 | $47.00 | $17.71 | $42.00 | $150.00 | $50.00 | $28.04 | $50.00 |
| 3 | Remove (22") TRT/untrt base & asphalt pavement (105-7042) | SY | 2,682 | $15.00 | $35.79 | $10.00 | $25.00 | $20.00 | $11.12 | $26.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 437 | $31.00 | $31.08 | $40.00 | $50.00 | $30.00 | $53.83 | $35.00 |
| 5 | Embankment (final)(DC)(type B) (132-7004) | CY | 9,131 | $25.00 | $18.17 | $63.00 | $50.00 | $45.00 | $75.01 | $40.00 |
| 6 | Drill seed (permanent_rural_sand) (164-7009) | SY | 28,864 | $0.30 | $0.33 | $0.25 | $0.30 | $0.25 | $1.12 | $0.30 |
| 7 | Drill seed (temporary_warm_cool) (164-7015) | SY | 28,864 | $0.30 | $0.28 | $0.15 | $0.20 | $0.25 | $1.02 | $0.20 |
| 8 | Soil ret BLKT(SL_mod_sand_short_roll) (169-7011) | SY | 7,721 | $3.50 | $2.10 | $2.00 | $3.00 | $4.00 | $3.44 | $1.50 |
| 9 | FL BS(compacted in place)(type A,B or D GR4)(12") (247-7134) | SY | 3,137 | $40.00 | $41.56 | $55.00 | $40.00 | $75.00 | $95.31 | $60.00 |
| 10 | Prime coat (MC-30) (310-7004) | GAL | 786 | $8.00 | $7.46 | $12.00 | $8.00 | $20.00 | $11.77 | $20.00 |
| 11 | SP mixes SP-B PG64-22 (344-7001) | TON | 97 | $210.00 | $125.87 | $500.00 | $250.00 | $250.00 | $462.03 | $300.00 |
| 12 | SP mixes SP-D sac-A PG70-28 (344-7057) | TON | 929 | $210.00 | $188.95 | $250.00 | $225.00 | $300.00 | $264.47 | $300.00 |
| 13 | Tack coat (344-7077) | GAL | 829 | $8.00 | $4.18 | $10.00 | $6.00 | $20.00 | $11.77 | $10.00 |
| 14 | Plane & text asphalt concrete pavement(2") (354-7019) | SY | 1,858 | $6.00 | $2.38 | $4.50 | $10.00 | $6.00 | $12.94 | $20.00 |
| 15 | Cem stabil BKFL (400-7010) | CY | 427 | $255.00 | $251.50 | $225.00 | $250.00 | $300.00 | $300.93 | $350.00 |
| 16 | Temporary special shoring (403-7001) | SF | 4,684 | $60.00 | $40.27 | $72.00 | $50.00 | $30.00 | $67.95 | $10.00 |
| 17 | Drilled shaft (18 in) (416-7002) | LF | 528 | $165.00 | $56.16 | $75.00 | $150.00 | $200.00 | $550.00 | $105.00 |
| 18 | Drilled shaft (42 in) (416-7007) | LF | 924 | $350.00 | $273.05 | $280.00 | $300.00 | $500.00 | $1,100.00 | $300.00 |
| 19 | Drilled shaft (48 in) (416-7008) | LF | 408 | $420.00 | $469.24 | $365.00 | $400.00 | $900.00 | $1,550.00 | $380.00 |
| 20 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 16 | $300.00 | $303.01 | $325.00 | $346.00 | $600.00 | $323.58 | $300.00 |
| 21 | Class C concrete (abutment) (420-7012) | CY | 157.50 | $1,500.00 | $1,057.92 | $1,100.00 | $2,000.00 | $2,400.00 | $2,781.00 | $2,500.00 |
| 22 | Class C concrete (cap) (420-7022) | CY | 77.20 | $2,000.00 | $2,262.44 | $1,100.00 | $2,000.00 | $2,400.00 | $2,681.00 | $3,000.00 |
| 23 | Class C concrete (column) (420-7038) | CY | 76.50 | $2,000.00 | $1,055.50 | $1,300.00 | $2,000.00 | $2,400.00 | $2,800.00 | $3,500.00 |
| 24 | Reinforced concrete slab (422-7001) | SF | 17,296 | $42.25 | $36.73 | $45.00 | $40.00 | $50.00 | $45.00 | $50.00 |
| 25 | Approach slab (422-7013) | CY | 208 | $750.00 | $645.90 | $700.00 | $2,000.00 | $1,500.00 | $946.38 | $1,800.00 |
| 26 | Retaining wall (MSE) (423-7001) | SF | 6,473 | $110.00 | $129.21 | $99.00 | $135.00 | $150.00 | $107.02 | $120.00 |
| 27 | Epoxy waterproof finish (type X) (427-7005) | SF | 2,239 | $13.00 | $17.81 | $18.00 | $8.00 | $25.00 | $9.41 | $10.00 |
| 28 | Riprap (concrete)(4 in) (432-7001) | CY | 1,012 | $620.00 | $343.00 | $550.00 | $675.00 | $1,000.00 | $549.34 | $750.00 |
| 29 | Riprap (concrete)(flume) (432-7012) | CY | 14 | $650.00 | $652.63 | $650.00 | $850.00 | $1,000.00 | $1,001.33 | $800.00 |
| 30 | Riprap (mow strip)(4 in) (432-7013) | CY | 24 | $650.00 | $652.63 | $1,500.00 | $850.00 | $600.00 | $2,766.30 | $800.00 |
| 31 | Elastomeric bearing (EE5) (434-7007) | EACH | 10 | $3,000.00 | $2,695.07 | $2,500.00 | $4,000.00 | $7,500.00 | $2,550.98 | $4,000.00 |
| 32 | Elastomeric bearing (EE6) (434-7008) | EACH | 2 | $3,000.00 | $3,095.35 | $3,000.00 | $4,000.00 | $8,000.00 | $2,929.86 | $4,000.00 |
| 33 | Elastomeric bearing (F7) (434-7037) | EACH | 6 | $5,000.00 | $5,594.01 | $5,500.00 | $4,000.00 | $10,000 | $4,558.34 | $4,000.00 |
| 34 | STR steel (plate girder) (442-7001) | LB | 1,292,142 | $2.80 | $2.49 | $2.20 | $2.25 | $3.15 | $3.11 | $5.60 |
| 35 | Rail (type SSTR) (450-7024) | LF | 832 | $120.00 | $95.07 | $175.00 | $250.00 | $400.00 | $419.63 | $220.00 |
| 36 | Rail (type T80PP) (450-7051) | LF | 420 | $180.00 | $242.26 | $490.00 | $350.00 | $700.00 | $851.60 | $300.00 |
| 37 | Sealed expansion joint (5 in) (SEJ - M) (454-7005) | LF | 176 | $275.00 | $279.70 | $280.00 | $300.00 | $400.00 | $293.97 | $250.00 |
| 38 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $300,000 | $271,309 | $200,000 | $850,000 | $1,000,000 | $550,000 | $900,000 |
| 39 | Mobilization (500-7001) | LS | 1 | $900,000 | $977,288 | $960,000 | $1,200,000 | $1,400,000 | $1,383,824 | $1,500,000 |
| 40 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $29,000 | $35,739 | $25,000 | $50,000 | $25,000 | $19,768 | $8,000.00 |
| 41 | Portable changeable message sign (503-7002) | EACH | 4 | $15,000 | $8,961.72 | $15,000 | $18,500 | $18,000 | $29,416 | $30,000 |
| 42 | TMA (stationary) (505-7001) | DAY | 50 | $300.00 | $310.78 | $330.00 | $550.00 | $300.00 | $924.85 | $300.00 |
| 43 | TMA (mobile operation) (505-7002) | HR | 40 | $100.00 | $124.31 | $250.00 | $70.00 | $150.00 | $386.82 | $50.00 |
| 44 | Construction exits (install) (type 1) (506-7020) | SY | 480 | $50.00 | $31.70 | $50.00 | $45.00 | $30.00 | $35.30 | $1.00 |
| 45 | Construction exits (remove) (506-7024) | SY | 480 | $20.00 | $11.80 | $10.00 | $15.00 | $15.00 | $17.65 | $1.00 |
| 46 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 3,000 | $7.00 | $7.04 | $3.50 | $4.00 | $6.00 | $29.42 | $1.00 |
| 47 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,000 | $2.00 | $1.86 | $1.00 | $1.00 | $3.00 | $11.77 | $1.00 |
| 48 | Constructing detours (508-7001) | SY | 1,179 | $115.00 | $186.91 | $515.00 | $250.00 | $180.00 | $269.39 | $185.00 |
| 49 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 2,040 | $25.00 | $13.05 | $18.00 | $5.00 | $40.00 | $34.48 | $50.00 |
| 50 | Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041) | LF | 2,040 | $25.00 | $17.71 | $14.00 | $5.00 | $20.00 | $34.48 | $50.00 |
| 51 | Portable concrete traffic barrier (connection hardware) (512-7070) | EACH | 70 | $100.00 | $93.23 | $55.00 | $55.00 | $100.00 | $58.83 | $85.00 |
| 52 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 1,362 | $25.00 | $125.98 | $250.00 | $125.00 | $250.00 | $176.50 | $200.00 |
| 53 | Metal W-beam guard fence (steel post) (540-7002) | LF | 50 | $40.00 | $32.63 | $45.00 | $40.00 | $200.00 | $52.95 | $35.00 |
| 54 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $3,500.00 | $2,330.84 | $3,350.00 | $2,700.00 | $6,000.00 | $3,941.78 | $2,500.00 |
| 55 | Remove metal beam guard fence (542-7001) | LF | 3,025 | $5.00 | $3.00 | $2.00 | $4.00 | $15.00 | $2.35 | $2.00 |
| 56 | Cable barrier system (install)(TL-3) (543-7001) | LF | 500 | $30.00 | $30.77 | $55.00 | $55.00 | $30.00 | $64.72 | $80.00 |
| 57 | Cable barrier terminal sec (install)(TL-3) (543-7017) | EACH | 2 | $2,500.00 | $6,686.99 | $5,750.00 | $5,750.00 | $7,000.00 | $6,765.74 | $12,000 |
| 58 | Cable barrier (remove) (543-7037) | LF | 500 | $5.00 | $4.66 | $5.00 | $5.00 | $20.00 | $5.88 | $10.00 |
| 59 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $4,900.00 | $3,106.11 | $3,400.00 | $3,500.00 | $7,000.00 | $3,941.78 | $4,000.00 |
| 60 | Guardrail end treatment (remove) (544-7003) | EACH | 2 | $400.00 | $298.35 | $300.00 | $400.00 | $500.00 | $353.00 | $500.00 |
| 61 | Crash cushion attenuator (remove) (545-7004) | EACH | 6 | $2,000.00 | $932.33 | $15.00 | $3,000.00 | $1,500.00 | $17.65 | $2,000.00 |
| 62 | Crash cushion attenuator (install)(R)(N)(TL3) (545-7010) | EACH | 2 | $15,000 | $38,536 | $34,250 | $29,750 | $32,500 | $40,300 | $25,000 |
| 63 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 4 | $15,000 | $7,738.37 | $8,500.00 | $10,000 | $12,000 | $10,002 | $10,000 |
| 64 | Aluminum signs (type A) (636-7001) | SF | 24 | $50.00 | $36.36 | $47.00 | $50.00 | $100.00 | $55.30 | $1,800.00 |
| 65 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 4 | $1,200.00 | $792.48 | $1,475.00 | $1,200.00 | $2,500.00 | $1,735.56 | $2,500.00 |
| 66 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 1 | $500.00 | $559.40 | $1,000.00 | $900.00 | $2,000.00 | $1,176.65 | $1,800.00 |
| 67 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $160.00 | $107.22 | $125.00 | $100.00 | $200.00 | $147.08 | $50.00 |
| 68 | Install LRSS (struct steel) (647-7001) | LB | 516 | $10.00 | $7.51 | $13.50 | $10.00 | $20.00 | $15.88 | $40.00 |
| 69 | Remove lrsa (647-7003) | EACH | 1 | $1,000.00 | $913.69 | $2,500.00 | $2,100.00 | $3,000.00 | $2,941.63 | $5,000.00 |
| 70 | Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003) | EACH | 7 | $175.00 | $93.23 | $45.00 | $140.00 | $200.00 | $205.91 | $500.00 |
| 71 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 12 | $50.00 | $22.88 | $45.00 | $55.00 | $200.00 | $52.95 | $50.00 |
| 72 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 3 | $55.00 | $35.89 | $50.00 | $55.00 | $200.00 | $58.83 | $50.00 |
| 73 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 12 | $50.00 | $22.88 | $45.00 | $55.00 | $200.00 | $52.95 | $50.00 |
| 74 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 3 | $55.00 | $27.97 | $50.00 | $55.00 | $150.00 | $58.83 | $50.00 |
| 75 | Remove delin & object marker assms (658-7078) | EACH | 3 | $38.00 | $18.65 | $50.00 | $10.00 | $200.00 | $17.65 | $50.00 |
| 76 | Pavement sler 6" (666-7347) | LF | 1,096 | $0.20 | $0.42 | $1.00 | $1.00 | $3.00 | $1.09 | $2.00 |
| 77 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 700 | $0.85 | $0.79 | $2.75 | $2.50 | $6.00 | $2.94 | $3.00 |
| 78 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 2,793 | $0.85 | $0.75 | $2.50 | $2.50 | $6.00 | $2.94 | $3.00 |
| 79 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 3,000 | $0.85 | $0.72 | $2.50 | $2.50 | $6.00 | $2.94 | $3.00 |
| 80 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 39 | $9.00 | $5.13 | $8.00 | $20.00 | $50.00 | $9.41 | $25.00 |
| 81 | Pavement surface preparation for marking (6") (678-7002) | LF | 1,096 | $1.00 | $0.19 | $0.80 | $1.00 | $2.00 | $0.88 | $1.00 |
| 82 | Anti-graffiti coating (permnent-type II) (740-7005) | SF | 6,473 | $0.30 | $2.68 | $5.00 | $1.50 | $8.00 | $1.76 | $2.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.