TxDOT letting results, December 2, 2022
24 contracts let by Texas DOT on December 2, 2022, $254,416,757 in low bids, a median of 3 bidders per contract. On the 24 with an engineer's estimate, the low bid came in under it 12 times; median low bid -1.0% against the estimate.
- Owner
- Texas DOT
- Contracts
- 24
- Low bids, total
- $254,416,757
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 12223201 | SH 5 Reconstruct & widen 2 ln rural hwy to 4 ln urban from SH 121 to NORTH OF COLLIN COUNTY OUTER LOOP | Dallas District | 9 | Harper Brothers Construction LLC | $42,771,527 | $43,597,680 | +2.0% | -2.0% | TxDOT |
| 12223202 | SH 302 Roadway widening to a super 2 from EAST OF PURPLE CATTLE GUARD RD to WINKLER COUNTY LINE | Loving | 3 | FNF Construction, Inc. | $31,270,743 | $32,395,444 | +4.0% | +20% | TxDOT |
| 12223204 | SH 121 Highway improvement from GILVIN ST to MIDWAY | Fort Worth District | 4 | Austin Bridge & Road Services, LP | $25,141,983 | $26,428,325 | +5.0% | +6.0% | TxDOT |
| 12223203 | SH 11 Seal coat from FRANKLIN C/L to CAMP C/L | Tyler District | 2 | Clark Construction of Texas, Inc. | $24,618,622 | $30,524,365 | +24% | +7.0% | TxDOT |
| 12223211 | BS 349C Rehabilitate existing roadway from SL 250 to IH 20 | Odessa District | 3 | Jones Bros. Dirt & Paving Contractors, Inc. | $17,997,658 | $19,338,274 | +7.0% | +30% | TxDOT |
| 12223205 | IH 45 Surfacing/roadway restoration from MADISON COUNTY LINE to SH 7 | Bryan District | 1 | Big Creek Construction, LTD. | $17,287,258 | -11% | TxDOT | ||
| 12223206 | US 83 Seal coat from 11.429 MI S OF RUNNELS COUNTY LINE to US 87 IN EDEN | San Angelo District | 3 | Ronald R. Wagner & Co., LP | $16,983,573 | $18,562,598 | +9.0% | -11% | TxDOT |
| 12223208 | SH 114 Preventive maintenance from YOUNG CO LN to US 281 | Fort Worth District | 2 | Northeastern Pavers, LLC | $12,812,480 | $12,937,806 | +1.0% | +7.0% | TxDOT |
| 12223209 | US 83 Super 2 from CR 15, SOUTH to COLLINGSWORTH C/L | Childress District | 4 | Duininck, Inc. | $12,191,889 | $12,542,620 | +3.0% | +2.0% | TxDOT |
| 12223210 | BS 288B Widen road - add shoulders from FM 523 to FM 521 | Houston District | 5 | Durwood Greene Construction Co. | $10,948,342 | $12,163,999 | +11% | -3.0% | TxDOT |
| 12223207 | SH 21 Resurface roadway from SH 147 N to FM 1, ETC. | Lufkin District | 1 | Moore Brothers Construction Company | $10,737,999 | +7.0% | TxDOT | ||
| 12223214 | FM 316 Rehabilitate existing roadway from VAN ZANDT C/L (FM 1861) to US 175 | Tyler District | 5 | Baker & Company Construction, LLC | $7,938,414 | $8,648,465 | +9.0% | +22% | TxDOT |
| 12223212 | IH 20 Rehabilitate bridge from IH 20 to AT SPUR 408 | Dallas District | 3 | Gibson & Associates, Inc. | $4,350,740 | $4,483,874 | +3.0% | -10% | TxDOT |
| 12223213 | IH 27 Hazard elimination & safety from SWISHER CO LINE to US 60/US 87 INTERCHANGE | Amarillo District | 4 | 3LW Civil LLC | $4,296,749 | $4,418,949 | +3.0% | -3.0% | TxDOT |
| 12223215 | FM 2304 Resurface roadway from MATTHEWS LANE to KAISER DR. | Austin District | 3 | Lone Star Paving Company | $2,730,040 | $3,246,481 | +19% | -17% | TxDOT |
| 12223217 | FM 339 Rehabilitate existing roadway from SH 31 to LIMESTONE CO LINE | Waco District | 3 | Big Creek Construction, LTD. | $2,487,780 | $2,971,791 | +19% | -6.0% | TxDOT |
| 12223218 | US 82 Hazard elimination & safety from AT 1502 | Paris District | 3 | H. H. Howard & Sons, Inc. | $1,751,101 | $2,304,752 | +32% | -21% | TxDOT |
| 12223220 | IH 27 Rehabilitate bridge from NORTH AVE Q to BROADWAY | Lubbock District | 3 | Ti-Zack Concrete, LLC | $1,738,710 | $1,981,731 | +14% | 0.0% | TxDOT |
| 12223219 | CR Bridge replacement from AT WERTZNER CREEK to STR#AA01-79-001(HALSTEDT RD) | Yoakum District | 9 | Acme Bridge Company, Inc. | $1,728,304 | $1,752,866 | +1.0% | +3.0% | TxDOT |
| 12223226 | US 87 Bridge replacement from BIRDS CREEK to STR # 0143-08-017) | Yoakum District | 8 | Dunn Services, Inc. | $1,282,152 | $1,577,763 | +23% | +15% | TxDOT |
| 12223223 | VA Bridge maintenance from VARIOUS | Abilene District | 5 | Cross Plus Construction, LLC | $1,087,689 | $1,505,194 | +38% | 0.0% | TxDOT |
| 12223224 | FM 3247 Surfacing/roadway restoration from BU 90Y, SOUTH to EOM | Beaumont District | 2 | Cornerstone Paving and Construction, L.L.C. | $1,011,891 | $1,191,054 | +18% | -8.0% | TxDOT |
| 12223222 | US 83 Traffic signal improvements from LOMAS DEL SUR INTERSECTION to 0.2 MI SOUTH OF SORIA DR | Laredo District | 3 | Triple H Field Services, LLC | $812,477 | $923,321 | +14% | -5.0% | TxDOT |
| 12223225 | SS 580 Construct pedestrian infrastructure from ALTA MERE DR. to LACKLAND ROAD | Fort Worth District | 5 | Garret Shields Infrastructure | $438,635 | $451,872 | +3.0% | -5.0% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.