TxDOT letting results, September 7, 2023
31 contracts let by Texas DOT on September 7, 2023, $268,009,804 in low bids, a median of 3 bidders per contract. On the 31 with an engineer's estimate, the low bid came in under it 16 times; median low bid -2.0% against the estimate.
- Owner
- Texas DOT
- Contracts
- 31
- Low bids, total
- $268,009,804
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 09233203 | US 60 Rehabilitate existing roadway from DEAF SMITH CO LINE to US 87 IN CANYON | Amarillo District | 4 | Duininck, Inc. | $34,924,134 | $38,421,699 | +10% | -14% | TxDOT |
| 09233204 | IH 10 Resurface roadway from FM 473 to CIBOLO CREEK | San Antonio District | 6 | Texas Materials Group, Inc. | $26,085,495 | $27,410,575 | +5.0% | -13% | TxDOT |
| 09233205 | US 62 Surfacing/roadway restoration from FM 213 IN WELLMAN to BEG OF 4 LN DIVIDED S OF BROWNFIELD | Lubbock District | 3 | James Hamilton Construction Co. | $22,784,907 | $25,535,166 | +12% | -6.0% | TxDOT |
| 09233210 | SH 153 Rehabilitate existing roadway / bridge replacemen from TAYLOR COUNTY LINE / VALLEY CREEK to US 83 | San Angelo District | 3 | RK Hall, LLC | $21,350,245 | $23,896,190 | +12% | -4.0% | TxDOT |
| 09233207 | IH 10 Preventive maintenance from 5.346 MI W OF CULBERSON CL to HUDSPETH/CULBERSON CL | El Paso District | 2 | Dan Williams Company | $18,357,209 | $20,489,954 | +12% | +1.0% | TxDOT |
| 09233208 | SH 36 Rehab rdwy to add pass lns from COMANCHE CO LINE to US 281 | Waco District | 4 | Big Creek Construction, LTD. | $18,187,374 | $19,345,672 | +6.0% | +9.0% | TxDOT |
| 09233206 | FM 1255 Rehabilitate existing roadway from IH 20 to SH 110 | Tyler District | 3 | Reynolds & Kay, LTD. | $17,084,796 | $17,259,655 | +1.0% | -25% | TxDOT |
| 09233212 | IH 10 Fy 2024 seal coat - crumb rubber from SH 18 to 0.759 MI E OF US 67, ETC. | Odessa District | 2 | Cox Paving of Texas, Inc. | $14,363,578 | $15,581,191 | +8.0% | +5.0% | TxDOT |
| 09233214 | SH 18 Fy 2024 seal coat from 0.22 MI S OF FM 1776 to PECOS COUNTY LINE, ETC. | Odessa District | 4 | Ronald R. Wagner & Co., LP | $13,110,325 | $13,305,500 | +1.0% | +3.0% | TxDOT |
| 09233209 | IH 20 Preventive maintenance from NOLAN COUNTY LINE to NEAR WELLS LANE | Abilene District | 3 | Foutsco Paving Company, LLC | $12,105,732 | $13,824,449 | +14% | -14% | TxDOT |
| 09233211 | FM 1015 Rehabilitate existing roadway from IH-2 to 2.584 MILES SOUTH OF IH-2 | Pharr District | 4 | Texas Cordia Construction, LLC | $11,217,266 | $11,535,678 | +3.0% | -19% | TxDOT |
| 09233215 | BS 71-E Bridge maintenance from AT COLORADO RIVER IN LA GRANGE to STR # 0265-14-038 | Yoakum District | 4 | Cekra Inc. | $8,209,128 | $13,440,465 | +64% | +22% | TxDOT |
| 09233216 | IH 2 Preventive maintenance from FM 2557 to FM 1423 | Pharr District | 3 | Ronald R. Wagner & Co., LP | $6,490,669 | $6,860,930 | +6.0% | +6.0% | TxDOT |
| 09233213 | IH 37 Rehabilitate existing roadway from SH 188 to 0.47 MI SOUTH OF SH 188 (CONTROL BR | Corpus Christi District | 7 | Brannan Paving Co., LTD. | $6,031,422 | $6,122,722 | +2.0% | -30% | TxDOT |
| 09233223 | FM 1466 Bridge replacement from AT LITTLE DRY BRUSHY CREEK to STR# 14-246-0-1200-04-007 | Austin District | 4 | Joe Bland Construction, L.P. | $5,546,235 | $6,263,294 | +13% | +45% | TxDOT |
| 09233222 | FM 511 Preventive maintenance from OLD PORT ISABEL RD. to CHARMAINE LANE | Pharr District | 3 | Brannan Paving Co., LTD. | $4,012,544 | $4,070,520 | +1.0% | +16% | TxDOT |
| 09233217 | CR Bridge replacement from CR 451A (MARY LANE) AT DRAINAGE DIT | Houston District | 3 | Main Lane Industries LTD. | $3,799,247 | $4,246,590 | +12% | -5.0% | TxDOT |
| 09233220 | FM 141 Seal coat from SH 21 to FM 1697 | Austin District | 3 | Texas Materials Group, Inc. | $3,387,874 | $3,618,418 | +7.0% | +31% | TxDOT |
| 09233218 | US 290 Seal coat from E. OF REEH RD to US 87 | Austin District | 4 | Allen Keller Company | $3,070,930 | $3,200,778 | +4.0% | -14% | TxDOT |
| 09233225 | SL 108 Bridge replacement from SL 108 AT HORSESHOE LAKE | Houston District | 2 | John Reed and Company, LLC | $2,472,329 | $3,098,072 | +25% | +39% | TxDOT |
| 09233232 | CR Bridge replacement from CR 3210 to AT BULLARD CREEK | Paris District | 6 | THK Construction LLC | $2,295,795 | $2,536,352 | +10% | +6.0% | TxDOT |
| 09233219 | US 290 Bridge maintenance from AT FM 577 | Bryan District | 6 | Main Lane Industries LTD. | $2,162,427 | $2,278,767 | +5.0% | -29% | TxDOT |
| 09233221 | FM 157 Intersection improvements with right and/or left from SH 121 SB FRONTAGE RD /RIO GRANDE B to FM 157/INDUSTRIAL BLVD | Fort Worth District | 3 | Ragle Construction, Inc. | $2,090,442 | $2,390,908 | +14% | +9.0% | TxDOT |
| 09233226 | SH 31 Resurface roadway from 2.6 MILES WEST OF SH 198 | Tyler District | 4 | Baker & Company Construction, LLC | $2,061,802 | $2,322,903 | +13% | -2.0% | TxDOT |
| 09233224 | PR 72 Surfacing/roadway restoration from IN BRAZOS BEND STATE PARK | Houston District | 3 | Forde Construction Company, Inc. | $1,866,653 | $2,218,460 | +19% | -3.0% | TxDOT |
| 09233227 | RM 2322 Seal coat from SH 71 to PACE BEND PARK ROAD | Austin District | 3 | Texas Materials Group, Inc. | $1,340,429 | $1,381,691 | +3.0% | +16% | TxDOT |
| 09233228 | SH 80 Bridge maintenance from 200 FT N OF SAN MARCO RIVER BRIDGE to 200 FT S OF SAN MARCO RIVER BRIDGE | Austin District | 7 | Gibson & Associates, Inc. | $1,012,429 | $1,128,707 | +11% | -21% | TxDOT |
| 09233229 | VA State park improvements from AT TPWD STATE HEADQUARTERS COMPLEX | Austin District | 2 | FNH Construction, LLC | $971,504 | $972,342 | 0.0% | +25% | TxDOT |
| 09233230 | US 79 Resurface roadway from 2.2 MILES EAST OF FM 645 | Tyler District | 3 | FNH Construction, LLC | $664,721 | $750,490 | +13% | +34% | TxDOT |
| 09233231 | VA Bridge maintenance from VARIOUS LOCATIONS DISTRICTWIDE | Lufkin District | 4 | Garret Shields Infrastructure | $644,360 | $670,000 | +4.0% | -13% | TxDOT |
| 09233202 | BU 287P Landscape development from WJ BOAZ RD to BAILEY BOSWELL RD | Fort Worth District | 5 | Tight Line Construction, LLC | $307,805 | $317,170 | +3.0% | -15% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.