TxDOT letting results, September 7, 2023

31 contracts let by Texas DOT on September 7, 2023, $268,009,804 in low bids, a median of 3 bidders per contract. On the 31 with an engineer's estimate, the low bid came in under it 16 times; median low bid -2.0% against the estimate.

Owner
Texas DOT
Contracts
31
Low bids, total
$268,009,804
Data through
19 NOV 2026

Contracts let that day

ContractProjectDistrictBidsLow bidderLow bidSecond bidGapAgainst estimateSource
09233203US 60 Rehabilitate existing roadway from DEAF SMITH CO LINE to US 87 IN CANYONAmarillo District4Duininck, Inc.$34,924,134$38,421,699+10%-14%TxDOT
09233204IH 10 Resurface roadway from FM 473 to CIBOLO CREEKSan Antonio District6Texas Materials Group, Inc.$26,085,495$27,410,575+5.0%-13%TxDOT
09233205US 62 Surfacing/roadway restoration from FM 213 IN WELLMAN to BEG OF 4 LN DIVIDED S OF BROWNFIELDLubbock District3James Hamilton Construction Co.$22,784,907$25,535,166+12%-6.0%TxDOT
09233210SH 153 Rehabilitate existing roadway / bridge replacemen from TAYLOR COUNTY LINE / VALLEY CREEK to US 83San Angelo District3RK Hall, LLC$21,350,245$23,896,190+12%-4.0%TxDOT
09233207IH 10 Preventive maintenance from 5.346 MI W OF CULBERSON CL to HUDSPETH/CULBERSON CLEl Paso District2Dan Williams Company$18,357,209$20,489,954+12%+1.0%TxDOT
09233208SH 36 Rehab rdwy to add pass lns from COMANCHE CO LINE to US 281Waco District4Big Creek Construction, LTD.$18,187,374$19,345,672+6.0%+9.0%TxDOT
09233206FM 1255 Rehabilitate existing roadway from IH 20 to SH 110Tyler District3Reynolds & Kay, LTD.$17,084,796$17,259,655+1.0%-25%TxDOT
09233212IH 10 Fy 2024 seal coat - crumb rubber from SH 18 to 0.759 MI E OF US 67, ETC.Odessa District2Cox Paving of Texas, Inc.$14,363,578$15,581,191+8.0%+5.0%TxDOT
09233214SH 18 Fy 2024 seal coat from 0.22 MI S OF FM 1776 to PECOS COUNTY LINE, ETC.Odessa District4Ronald R. Wagner & Co., LP$13,110,325$13,305,500+1.0%+3.0%TxDOT
09233209IH 20 Preventive maintenance from NOLAN COUNTY LINE to NEAR WELLS LANEAbilene District3Foutsco Paving Company, LLC$12,105,732$13,824,449+14%-14%TxDOT
09233211FM 1015 Rehabilitate existing roadway from IH-2 to 2.584 MILES SOUTH OF IH-2Pharr District4Texas Cordia Construction, LLC$11,217,266$11,535,678+3.0%-19%TxDOT
09233215BS 71-E Bridge maintenance from AT COLORADO RIVER IN LA GRANGE to STR # 0265-14-038Yoakum District4Cekra Inc.$8,209,128$13,440,465+64%+22%TxDOT
09233216IH 2 Preventive maintenance from FM 2557 to FM 1423Pharr District3Ronald R. Wagner & Co., LP$6,490,669$6,860,930+6.0%+6.0%TxDOT
09233213IH 37 Rehabilitate existing roadway from SH 188 to 0.47 MI SOUTH OF SH 188 (CONTROL BRCorpus Christi District7Brannan Paving Co., LTD.$6,031,422$6,122,722+2.0%-30%TxDOT
09233223FM 1466 Bridge replacement from AT LITTLE DRY BRUSHY CREEK to STR# 14-246-0-1200-04-007Austin District4Joe Bland Construction, L.P.$5,546,235$6,263,294+13%+45%TxDOT
09233222FM 511 Preventive maintenance from OLD PORT ISABEL RD. to CHARMAINE LANEPharr District3Brannan Paving Co., LTD.$4,012,544$4,070,520+1.0%+16%TxDOT
09233217CR Bridge replacement from CR 451A (MARY LANE) AT DRAINAGE DITHouston District3Main Lane Industries LTD.$3,799,247$4,246,590+12%-5.0%TxDOT
09233220FM 141 Seal coat from SH 21 to FM 1697Austin District3Texas Materials Group, Inc.$3,387,874$3,618,418+7.0%+31%TxDOT
09233218US 290 Seal coat from E. OF REEH RD to US 87Austin District4Allen Keller Company$3,070,930$3,200,778+4.0%-14%TxDOT
09233225SL 108 Bridge replacement from SL 108 AT HORSESHOE LAKEHouston District2John Reed and Company, LLC$2,472,329$3,098,072+25%+39%TxDOT
09233232CR Bridge replacement from CR 3210 to AT BULLARD CREEKParis District6THK Construction LLC$2,295,795$2,536,352+10%+6.0%TxDOT
09233219US 290 Bridge maintenance from AT FM 577Bryan District6Main Lane Industries LTD.$2,162,427$2,278,767+5.0%-29%TxDOT
09233221FM 157 Intersection improvements with right and/or left from SH 121 SB FRONTAGE RD /RIO GRANDE B to FM 157/INDUSTRIAL BLVDFort Worth District3Ragle Construction, Inc.$2,090,442$2,390,908+14%+9.0%TxDOT
09233226SH 31 Resurface roadway from 2.6 MILES WEST OF SH 198Tyler District4Baker & Company Construction, LLC$2,061,802$2,322,903+13%-2.0%TxDOT
09233224PR 72 Surfacing/roadway restoration from IN BRAZOS BEND STATE PARKHouston District3Forde Construction Company, Inc.$1,866,653$2,218,460+19%-3.0%TxDOT
09233227RM 2322 Seal coat from SH 71 to PACE BEND PARK ROADAustin District3Texas Materials Group, Inc.$1,340,429$1,381,691+3.0%+16%TxDOT
09233228SH 80 Bridge maintenance from 200 FT N OF SAN MARCO RIVER BRIDGE to 200 FT S OF SAN MARCO RIVER BRIDGEAustin District7Gibson & Associates, Inc.$1,012,429$1,128,707+11%-21%TxDOT
09233229VA State park improvements from AT TPWD STATE HEADQUARTERS COMPLEXAustin District2FNH Construction, LLC$971,504$972,3420.0%+25%TxDOT
09233230US 79 Resurface roadway from 2.2 MILES EAST OF FM 645Tyler District3FNH Construction, LLC$664,721$750,490+13%+34%TxDOT
09233231VA Bridge maintenance from VARIOUS LOCATIONS DISTRICTWIDELufkin District4Garret Shields Infrastructure$644,360$670,000+4.0%-13%TxDOT
09233202BU 287P Landscape development from WJ BOAZ RD to BAILEY BOSWELL RDFort Worth District5Tight Line Construction, LLC$307,805$317,170+3.0%-15%TxDOT
TxDOT contracts let on September 7, 2023, largest low bid first

Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy