Ditch excavation including haul, WSDOT

Low bidders on WSDOT contracts carried a median of $14.45 per CY for this item, over the 24 months to 07 OCT 2026, across 1 low bids. Half of all 8 bids fell between $32.50 and $49.25.

Owner
Washington State DOT
Item
No code published
Unit
CY
Data through
07 OCT 2026

WSDOT prints this item as “DITCH EXCAVATION INCL. HAUL”.

$14.45Low bidder's median, per CY
$40.50Median of all bids, per CY
1Contracts in the window

By year of letting

Ditch excavation including haul, WSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200022$10.0015$11.00
200122$8.507$20.00
200266$27.5024$24.50
200311$10.008$17.25
200455$19.0027$25.00
200588$11.5042$14.11
200655$13.2526$18.00
200788$17.0066$17.00
200822$7.089$10.95
200933$11.0017$12.00
201066$13.6065$18.00
201155$27.0029$26.00
201244$24.6233$15.00
201311$15.508$11.00
201422$9.9019$13.25
201633$17.5023$25.00
201744$37.5025$34.00
201833$43.1512$41.58
201911$100.004$41.00
202022$24.5012$25.50
202122$28.009$20.00
202222$97.005$75.00
202322$18.009$30.00
202611$14.458$40.50

Bid prices as published, not adjusted for inflation.

By region

RegionLow bidsLow-bid medianAll bidsMedian, all bids
NWR region42$15.60290$20.00
SWR region8$14.7864$14.75
SCR region8$30.5053$16.00
OR region10$25.0041$22.00
ER region8$14.0034$20.00
NCR region4$9.7520$11.50
Ditch excavation including haul, WSDOT: unit prices by region, all lettings

Regions with at least three low bids, over all lettings.

By quantity

Quantity (CY)Low bidsLow-bid median
2 to 6420$37.25
80 to 20020$17.50
219 to 95920$12.62
1,037 to 16,05020$11.00
Ditch excavation including haul, WSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Imco General Construction, Inc96 (67%)
Tri-State Construction, Inc.195 (26%)
Mowat Construction Company105 (50%)
Scarsella Bros., Inc.274 (15%)
Max J. Kuney Company124 (33%)
Interwest Construction, Inc.153 (20%)
Ditch excavation including haul, WSDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
23 SEP 2026XE3772SCR region6,420$14.45$40.50n/a8Scarsella Bros., Inc.WSDOT
23 FEB 2023009925ER region870$16.00$35.50$13.002Max J. Kuney CompanyWSDOT
19 JAN 2023009891OR region2,080$20.00$30.00$54.007Ceccanti, Inc.WSDOT
09 MAR 2022009774OR region24$125.00$129.00$50.002Kraemer North America, LLC.WSDOT
20 JAN 2022009754NWR region33$69.00$69.00$30.003Granite Construction CompanyWSDOT
21 APR 2021009662NWR region110$50.00$62.50$50.004Scarsella Bros., Inc.WSDOT
13 JAN 2021009623ER region4,440$6.00$13.50$20.005Max J. Kuney CompanyWSDOT
01 APR 2020009530SCR region140$34.00$37.00$50.004Apollo, Inc.WSDOT
20 FEB 2020009516OR region480$15.00$21.50$29.008Interwest Construction, Inc.WSDOT
24 APR 2019009426ER region3$100.00$41.00$150.004N.A. Degerstrom, Inc.WSDOT
11 APR 2018009250SCR region300$67.00$66.00$40.004Interstate Concrete & AsphaltWSDOT
04 APR 2018009238SWR region382$20.00$25.00$18.503Rognlin'S, Inc.WSDOT
28 FEB 2018009218NWR region180$43.15$35.00$40.005Tiger Construction, LTD.WSDOT
13 DEC 2017009177NWR region959$35.00$35.00$17.003Tapani, Inc.WSDOT
13 DEC 2017009172NWR region219$24.00$30.25$30.008Colacurcio Brothers, Inc.WSDOT
Latest WSDOT contracts carrying Ditch excavation including haul

Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.

How these prices were read

WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the WSDOT letting of 07 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.