ALDOT contract 20250131018 bid tabulation
CONCRETE REPAIR, RESURFACING, AND ADDITIONAL LANES ON SR-38 (US-280) FROM THE JUNCTION OF ROSEDALE DRIVE IN HOMEWOOD TO THE CAHABA RIVER BRIDGE. Let by Alabama DOT on January 31, 2025, Jefferson, 0301. 3 bids received; low bid $52,693,167 by Apac-Alabama, Inc..
- Owner
- Alabama DOT
- Letting
- 31 JAN 2025
- Pay items
- 245
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Apac-Alabama, Inc. | $52,693,167 | Low |
| 2 | Dunn Construction Company, Inc. | $53,100,000 | +1.0% |
| 3 | Wiregrass Construction Company, Inc. | $67,713,631 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Apac-Alabama, Inc. | 2. Dunn Construction Company, Inc. | 3. Wiregrass Construction Company, Inc. |
|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (maximum allowable bid $ 8,000.00 per acre) (approximately 4 acres) (201A002) | LS | 1 | $32,000 | $32,000 | $32,000 |
| 0020 | Removal of old bridge, station 6+76.45 (206A000) | LS | 1 | $417,400 | $471,136 | $455,973 |
| 0030 | Removal of old bridge, partial, station 309+72.74 (206A050) | LS | 1 | $52,000 | $324,781 | $314,328 |
| 0040 | Removing concrete slope paving (206C002) | SY | 429 | $77.63 | $86.74 | $84.80 |
| 0050 | Removing concrete flumes (206C003) | SY | 742 | $90.78 | $101.44 | $99.16 |
| 0060 | Removing concrete median (206C008) | SY | 3,118 | $90.90 | $101.58 | $99.30 |
| 0070 | Removing pipe (206D000) | LF | 1,455 | $90.52 | $101.15 | $98.88 |
| 0080 | Removing guardrail (206D001) | LF | 8,034 | $3.49 | $3.90 | $3.81 |
| 0090 | Removing curb (206D002) | LF | 13,033 | $28.03 | $31.32 | $30.62 |
| 0100 | Removing curb and gutter (206D003) | LF | 3,998 | $28.08 | $31.37 | $30.67 |
| 0110 | Removing safety barrier (206D010) | LF | 1,141 | $29.99 | $33.52 | $32.77 |
| 0120 | Removing headwalls (206E000) | EACH | 5 | $1,189.89 | $1,329.63 | $1,299.85 |
| 0130 | Removing inlets (206E001) | EACH | 33 | $2,181.32 | $2,437.48 | $2,382.86 |
| 0140 | Removing junction boxes (206E002) | EACH | 1 | $2,146.12 | $2,398.15 | $2,344.42 |
| 0150 | Removing guardrail end anchor (all type) (206E008) | EACH | 25 | $465.04 | $519.65 | $508.01 |
| 0160 | Removing existing overhead sign structure (206E020) | EACH | 1 | $17,527 | $5,792.76 | $28,575 |
| 0170 | Removing impact attenuators (206E041) | EACH | 7 | $581.30 | $649.56 | $635.01 |
| 0180 | Unclassified excavation (210A000) | CY | 18,980 | $105.80 | $118.22 | $115.57 |
| 0195 | Borrow excavation (loose truckbed measurement)(A4 or better) (210D021) | CY | 23,594 | $227.60 | $198.77 | $194.31 |
| 0200 | Borrow excavation (sand fill, complete in place) (210D101) | CY | 87 | $211.96 | $236.86 | $231.55 |
| 0210 | Borrow excavation (underwater backfill) (aldot #57) (210F002) | TON | 75 | $232.52 | $259.82 | $254.00 |
| 0220 | Structure excavation (214A000) | CY | 1,892 | $190.62 | $213.00 | $208.23 |
| 0230 | Foundation backfill, commercial (214B001) | CY | 652 | $199.70 | $223.15 | $218.15 |
| 0240 | Cofferdams or sheeting and shoring, station 6+61.80 (215B000) | LS | 1 | $65,740 | $74,202 | $71,814 |
| 0260 | Crushed aggregate base course, type B, plant mixed, 6" compacted thickness (301A012) | SY | 1,056 | $60.02 | $67.07 | $65.57 |
| 0270 | Crushed aggregate, section 825, for miscellaneous use (305B077) | TON | 2,022 | $131.69 | $147.15 | $143.85 |
| 0280 | Tack coat (405A000) | GAL | 41,344 | $5.55 | $3.65 | $8.89 |
| 0290 | Micro-milling existing pavement (approximately 0.00" thru 1.00" thick) (408B000) | SY | 456,652 | $2.03 | $1.75 | $2.43 |
| 0300 | Micro-milling existing pavement (approximately 1.10" thru 2.00" thick) (408B001) | SY | 453,137 | $2.49 | $2.00 | $3.44 |
| 0310 | Material remixing device (410H000) | EACH | 1 | $350,000 | $153,459 | $50,000 |
| 0320 | Polymer modified open graded friction course (420A015) | TON | 15,975 | $191.08 | $168.83 | $198.63 |
| 0330 | Open graded friction course tack coat (420B000) | GAL | 65,960 | $8.50 | $5.48 | $7.70 |
| 0340 | Stone matrix asphalt wearing layer, 1/2" maximum aggregate size (423A003) | TON | 33,018 | $156.79 | $147.52 | $175.27 |
| 0350 | Superpave bituminous concrete wearing surface layer, 1/2" maximum aggregate size mix, esal range C/D (424A360) | TON | 324 | $159.95 | $198.57 | $248.34 |
| 0360 | Superpave bituminous concrete wearing surface layer, widening, 1/2" maximum aggregate size mix, esal range C/D (424A369) | TON | 196 | $238.03 | $565.04 | $312.54 |
| 0370 | Superpave bituminous concrete upper binder layer, 3/4" maximum aggregate size mix, esal range E (424B280) | TON | 3,340 | $180.92 | $150.46 | $166.17 |
| 0380 | Superpave bituminous concrete upper binder layer, patching, 1" maximum aggregate size mix, esal range E (424B285) | TON | 38 | $743.16 | $656.02 | $304.93 |
| 0390 | Superpave bituminous concrete upper binder layer, leveling, 3/4" maximum aggregate size mix, esal range E (424B288) | TON | 50 | $308.93 | $338.98 | $581.06 |
| 0400 | Superpave bituminous concrete upper binder layer, widening, 3/4" maximum aggregate size mix, esal range E (424B291) | TON | 297 | $212.94 | $188.82 | $341.73 |
| 0420 | Superpave bituminous concrete lower binder layer, 1" maximum aggregate size mix, esal range E (424B581) | TON | 9,625 | $167.43 | $151.39 | $176.09 |
| 0430 | Superpave bituminous concrete lower binder layer, widening, 1" maximum aggregate size mix, esal range E (424B592) | TON | 1,018 | $180.95 | $146.99 | $223.56 |
| 0440 | Scoring bituminous pavement surface (428A001) | MI | 3 | $2,253.26 | $3,774.40 | $7,234.33 |
| 0450 | Aggregate surfacing (aldot #57) (430B003) | TON | 966 | $137.94 | $226.05 | $96.73 |
| 0460 | Plain cement concrete pavement,10 inches thick (450A019) | SY | 134 | $232.52 | $298.80 | $254.00 |
| 0470 | Reinforced cement concrete bridge end slab (450B000) | SY | 229 | $213.53 | $241.01 | $233.26 |
| 0480 | Removal of concrete pavement (453A001) | SY | 2,366 | $92.98 | $103.89 | $101.56 |
| 0490 | Removal of concrete pavement slab (453C000) | SY | 167 | $98.82 | $428.68 | $107.95 |
| 0500 | Concrete pavement replacement slab (453D000) | CY | 48 | $2,034.54 | $1,818.77 | $2,222.52 |
| 0510 | Cleaning and sealing concrete pavement, type II, joints (454A002) | LF | 490 | $3.49 | $3.90 | $3.81 |
| 0520 | Cleaning and sealing concrete pavement, type II, cracks (454A003) | LF | 15,948 | $3.49 | $3.90 | $3.81 |
| 0530 | Cleaning and sealing concrete pavement, type II, joints (longitudinal shoulder joints) (454A007) | LF | 32,121 | $2.33 | $2.60 | $2.54 |
| 0540 | Cleaning and sealing concrete pavement, type II, joints (longitudinal joints) (454A009) | LF | 23,210 | $2.33 | $2.60 | $2.54 |
| 0550 | Grinding concrete pavement (455A000) | SY | 41,663 | $6.55 | $5.97 | $7.15 |
| 0560 | Patching (460A000) | LB | 80,000 | $3.78 | $4.22 | $4.13 |
| 0570 | Bridge deck spall repair (490D000) | SF | 2,190 | $63.94 | $71.45 | $69.85 |
| 0580 | Steel reinforcement (502A000) | LB | 50,801 | $1.53 | $1.73 | $1.68 |
| 0590 | Steel reinforcement for bridge superstructure, station 6+61.80, approximately 102,000 pounds (502B000) | LS | 1 | $114,400 | $129,126 | $124,970 |
| 0600 | Drilled shaft excavation, 3'-6" diameter (506A005) | LF | 81 | $591.03 | $667.11 | $645.64 |
| 0610 | Special drilled shaft excavation, 3'-6" diameter (506B002) | LF | 42 | $2,774.13 | $3,131.21 | $3,030.44 |
| 0620 | Drilled shaft construction, 3'-6" diameter, class DS1 concrete (506C041) | LF | 123 | $149.63 | $168.89 | $163.45 |
| 0630 | Crosshole sonic logging, 3'-6" diameter (506G001) | EACH | 6 | $374.08 | $422.23 | $408.64 |
| 0640 | Structural steel (508A000) | LB | 10,860 | $11.04 | $12.46 | $12.06 |
| 0650 | Structural steel superstructure, 230'- 0" approximately 888,500 pounds (508B000) | EACH | 1 | $3,383,159 | $3,486,701 | $3,695,743 |
| 0660 | Bridge substructure concrete (510A007) | CY | 158 | $1,465.39 | $1,654.02 | $1,600.79 |
| 0670 | Bridge concrete, class B (510B001) | CY | 45 | $4,603.88 | $9,743.42 | $7,500.00 |
| 0680 | Bridge concrete superstructure, station 6+61.80 approximately 285 cubic yards (510C051) | LS | 1 | $687,299 | $775,768 | $750,801 |
| 0690 | Bridge concrete superstructure, high early strength, station 6+61.80, approximately 16 cubic yards (510C052) | LS | 1 | $30,352 | $2,141.15 | $33,156 |
| 0700 | Grooving concrete bridge decks (510E000) | SY | 1,058 | $11.36 | $12.82 | $12.41 |
| 0710 | Bridge barrier rail, type 36” single slope (510J000) | LF | 456 | $290.29 | $327.65 | $317.11 |
| 0720 | Elastomeric bearing type 4 (511A004) | EACH | 10 | $8,888.19 | $10,032 | $9,709.41 |
| 0730 | Application of bridge deck sealant (515D000) | SY | 17,930 | $22.09 | $24.68 | $24.13 |
| 0740 | Culvert concrete extension (cast in place) (524B011) | CY | 14 | $6,016.43 | $6,722.96 | $6,572.32 |
| 0750 | 18" roadway pipe (class 3 R.C.) (530A001) | LF | 1,014 | $180.20 | $201.36 | $196.85 |
| 0760 | 30" roadway pipe (class 3 R.C.) (530A003) | LF | 3 | $930.08 | $1,039.30 | $1,016.01 |
| 0770 | 60" roadway pipe (class 4 R.C.) (530A019) | LF | 12 | $1,395.12 | $1,558.95 | $1,524.02 |
| 0775 | 18" roadway pipe (class 3 R.C.) (extension) (530A101) | LF | 5 | $1,000.00 | $1,558.95 | $1,524.02 |
| 0780 | 24" roadway pipe (class 3 R.C.) (extension) (530A102) | LF | 37 | $465.04 | $519.65 | $508.00 |
| 0790 | 36" roadway pipe (class 3 R.C.) (extension) (530A104) | LF | 15 | $697.56 | $779.47 | $762.01 |
| 0800 | 22" span, 14" rise roadway pipe (class 3 R.C.) (530B001) | LF | 12 | $639.43 | $714.52 | $698.51 |
| 0810 | 18" span, 11" rise roadway pipe (class 3 R.C.) (extension) (530B011) | LF | 9 | $728.36 | $813.89 | $795.65 |
| 0820 | 18" slotted drain pipe (532A032) | LF | 1,288 | $589.42 | $658.64 | $53.33 |
| 0830 | 30" storm sewer pipe (class 3 R.C.) (533A100) | LF | 600 | $523.17 | $584.61 | $571.51 |
| 0840 | Cleaning existing culvert (less than or equal to 48" horizontal opening) (534E000) | LF | 224 | $40.11 | $32.97 | $32.07 |
| 0850 | Cleaning existing pipe (greater than 48" horizontal opening) (534F001) | LF | 420 | $48.13 | $39.57 | $38.49 |
| 0860 | 12" side drain pipe (PVC) (535A240) | LF | 23 | $174.39 | $194.87 | $190.50 |
| 0870 | 12" roadway pipe rehabilitation (538A000) | LF | 260 | $360.99 | $296.75 | $288.67 |
| 0880 | 15" roadway pipe rehabilitation (538A002) | LF | 47 | $914.50 | $751.78 | $731.29 |
| 0890 | 18" roadway pipe rehabilitation (538A003) | LF | 415 | $320.88 | $263.78 | $256.59 |
| 0900 | 24" roadway pipe rehabilitation (538A004) | LF | 264 | $641.75 | $527.56 | $513.19 |
| 0910 | 30" roadway pipe rehabilitation (538A005) | LF | 412 | $561.53 | $461.62 | $449.04 |
| 0920 | 18" span X 11" rise roadway pipe rehabilitation (538B000) | LF | 206 | $481.31 | $395.67 | $384.89 |
| 0930 | 18 inch trench drain (539A007) | LF | 27 | $965.71 | $1,503.06 | $1,428.76 |
| 0940 | Hydroblasting (544A000) | SY | 546 | $375.22 | $1,047.15 | $409.88 |
| 0950 | Placing and finishing concrete overlay (544C000) | SY | 459 | $124.30 | $359.96 | $135.79 |
| 0960 | Concrete for overlay (544D000) | CY | 23 | $2,689.82 | $30.11 | $2,938.34 |
| 0970 | Mobilization (600A000) | LS | 1 | $5,485,000 | $4,820,500 | $18,111,090 |
| 0980 | Right of way markers (602A000) | EACH | 9 | $4,650.38 | $1,299.12 | $5,080.05 |
| 0985 | Furnishing type 3 field office (603A002) | EACH | 1 | $168,944 | $195,527 | $437,796 |
| 0990 | Pavement edge drain (aggregate filled underdrain) (605A002) | LF | 700 | $24.72 | $27.62 | $27.00 |
| 1000 | Special underdrain outlet, type B (605B001) | EACH | 2 | $2,148.60 | $2,400.91 | $2,347.11 |
| 1010 | Filter blanket, geotextile (610D003) | SY | 1,800 | $7.05 | $7.87 | $7.70 |
| 1020 | Slope paving (614A000) | CY | 1,293 | $965.71 | $1,493.99 | $1,460.51 |
| 1030 | 12" roadway pipe end treatment, class 1 (619A000) | EACH | 1 | $2,446.47 | $3,117.89 | $3,048.03 |
| 1040 | 18" roadway pipe end treatment, class 1 (619A002) | EACH | 3 | $3,734.08 | $3,897.37 | $3,810.04 |
| 1050 | 24" roadway pipe end treatment, class 1 (619A003) | EACH | 1 | $3,991.60 | $4,222.15 | $4,127.55 |
| 1060 | 30" roadway pipe end treatment, class 1 (619A004) | EACH | 1 | $4,635.41 | $4,546.93 | $4,445.04 |
| 1070 | 60" roadway pipe end treatment, class 1 (619A009) | EACH | 1 | $9,013.29 | $12,082 | $11,811 |
| 1080 | Minor structure concrete (620A000) | CY | 61 | $1,743.83 | $1,948.68 | $1,905.02 |
| 1090 | Junction boxes, type 1 or 1P (621A011) | EACH | 15 | $5,279.21 | $10,783 | $10,541 |
| 1100 | Junction boxes, type special (621A013) | EACH | 1 | $7,725.68 | $12,342 | $24,765 |
| 1110 | Junction boxes, type partial (621A057) | EACH | 5 | $7,081.87 | $7,145.18 | $6,985.07 |
| 1120 | Inlets, type E (621C008) | EACH | 6 | $11,589 | $19,487 | $17,145 |
| 1125 | Inlets, type E1 (621C009) | EACH | 7 | $15,694 | $17,538 | $17,145 |
| 1130 | Inlets, type S1 or S3 (1 wing) (621C015) | EACH | 19 | $9,979.00 | $11,302 | $11,049 |
| 1140 | Inlets, type S2 or S4 (1 wing) (621C016) | EACH | 1 | $9,979.00 | $11,302 | $11,049 |
| 1150 | Inlets, type C (621C027) | EACH | 6 | $10,945 | $11,952 | $11,684 |
| 1170 | Inlets, type E (modified) (621C076) | EACH | 2 | $18,027 | $19,487 | $19,050 |
| 1180 | Inlets, type PB (621C111) | EACH | 8 | $10,945 | $12,342 | $12,065 |
| 1190 | Inlets, type E1 (modified) (621C130) | EACH | 1 | $19,314 | $19,487 | $19,050 |
| 1200 | Inlet units, type C (621D002) | EACH | 4 | $1,287.62 | $3,767.46 | $3,683.04 |
| 1210 | Inlet units, type E (621D008) | EACH | 6 | $1,287.61 | $3,767.46 | $3,683.04 |
| 1220 | Inlet units, type S1 or S3 (621D015) | EACH | 9 | $1,287.61 | $3,767.46 | $3,683.04 |
| 1230 | Inlet units, type S2 or S4 (621D016) | EACH | 2 | $1,287.61 | $3,767.46 | $3,683.04 |
| 1240 | Manholes, type L or M (storm) (621E004) | EACH | 3 | $18,602 | $20,786 | $20,320 |
| 1250 | Manhole units, type L or M (storm) (621F005) | EACH | 9 | $5,812.98 | $6,495.62 | $6,350.06 |
| 1260 | Concrete gutter (2' 6" wide) (623A002) | LF | 3,166 | $57.94 | $102.09 | $99.70 |
| 1270 | Concrete curb, type N (623B000) | LF | 6,423 | $45.07 | $90.94 | $88.90 |
| 1280 | Combination curb & gutter, type C (623C000) | LF | 7,213 | $57.94 | $110.43 | $107.95 |
| 1290 | Combination curb & gutter, type C (modified) (623C003) | LF | 359 | $77.26 | $146.15 | $142.88 |
| 1302 | Concrete median or safety barrier, type CSF-42 (629A095) | LF | 4,386 | $255.76 | $285.81 | $279.40 |
| 1303 | Concrete median or safety barrier, type CSF-42 (SE) (629A096) | LF | 1,200 | $267.39 | $298.80 | $292.10 |
| 1304 | Concrete median or safety barrier, type CSF-42 (FO) (629A097) | LF | 1,090 | $424.33 | $474.18 | $463.55 |
| 1330 | Concrete median or safety barrier end section (type tes) (629C002) | EACH | 5 | $6,975.57 | $7,794.74 | $7,620.08 |
| 1340 | Steel beam guardrail, class A, type 2 (8'-0" post) (630A034) | LF | 5,738 | $27.90 | $31.18 | $30.48 |
| 1350 | Guardrail end anchor, type 8 (MASH) (630C077) | EACH | 10 | $1,743.89 | $1,948.69 | $1,905.02 |
| 1360 | Guardrail end anchor, type 13 (MASH) (630C079) | EACH | 6 | $4,185.35 | $4,676.84 | $4,572.05 |
| 1370 | Guardrail end anchor, type 20 series (MASH) (630C080) | EACH | 12 | $4,069.09 | $4,546.93 | $4,445.05 |
| 1380 | Topsoil (650A000) | CY | 1,329 | $116.26 | $129.91 | $127.00 |
| 1390 | Seeding (652A100) | ACRE | 2 | $2,284.36 | $2,078.60 | $2,628.93 |
| 1400 | Solid sodding (bermuda) (654A001) | SY | 10,343 | $12.06 | $12.34 | $13.88 |
| 1410 | Mulching (656A010) | ACRE | 2 | $1,649.82 | $1,688.86 | $1,898.67 |
| 1420 | Erosion control product, type C8 (659C007) | SY | 284 | $9.02 | $9.22 | $10.38 |
| 1430 | Temporary seeding (665A000) | ACRE | 2 | $1,319.85 | $1,351.09 | $1,518.94 |
| 1440 | Temporary mulching (665B001) | TON | 18 | $1,078.73 | $1,104.26 | $1,241.44 |
| 1450 | Polyethylene (665E000) | SY | 1,000 | $6.02 | $5.85 | $6.58 |
| 1460 | Sand bags (665G000) | EACH | 2,400 | $8.02 | $7.79 | $8.76 |
| 1470 | Silt fence (665J002) | LF | 12,500 | $6.53 | $6.69 | $7.52 |
| 1480 | Temporary coarse aggregate,aldot number 1 (665N000) | TON | 600 | $98.33 | $109.88 | $107.42 |
| 1490 | Silt fence removal (665O001) | LF | 12,500 | $1.59 | $1.62 | $1.83 |
| 1500 | Inlet protection, stage 3 or 4 (665P005) | EACH | 97 | $729.73 | $747.00 | $839.80 |
| 1510 | Wattle (665Q002) | LF | 2,340 | $9.52 | $9.74 | $10.96 |
| 1520 | Temporary earth berms (665T000) | LF | 55 | $2.96 | $3.31 | $3.24 |
| 1530 | Pest control treatment (666A001) | ACRE | 2 | $279.20 | $285.81 | $321.31 |
| 1540 | Flocculant application, ditch check (672C100) | EACH | 50 | $38.07 | $38.97 | $43.82 |
| 1550 | Construction safety fence (674A000) | LF | 600 | $4.21 | $4.70 | $4.60 |
| 1560 | Geometric controls (680A001) | LS | 1 | $1,300,000 | $1,804,470 | $1,904,107 |
| 1570 | Construction fuel (maximum bid limited to $ 2,134,150.00) (698A000) | LS | 1 | $0.00 | $0.00 | $0.00 |
| 1580 | Solid white, class 2, type A traffic stripe (5" wide) (701A227) | MI | 22 | $5,260.75 | $5,878.53 | $5,689.34 |
| 1590 | Solid yellow, class 2, type A traffic stripe (5" wide) (701A230) | MI | 15 | $5,260.75 | $5,878.53 | $5,689.34 |
| 1600 | Broken white, class 2, type A traffic stripe (5" wide) (701A239) | MI | 32 | $3,197.14 | $3,572.59 | $3,457.61 |
| 1610 | Dotted, class W, type A traffic stripe (5" wide) (701B027) | LF | 121 | $4.07 | $4.55 | $4.40 |
| 1620 | Dotted, class 2, type A traffic stripe(lane drop 10" wide) (701B063) | LF | 6,675 | $4.36 | $4.87 | $4.71 |
| 1630 | Dotted, class 2, type A traffic stripe (5" wide) (701B207) | LF | 21,195 | $2.33 | $2.60 | $2.51 |
| 1640 | Broken temporary traffic stripe (701C000) | MI | 25 | $1,453.24 | $1,623.90 | $1,571.64 |
| 1650 | Solid temporary traffic stripe (701C001) | MI | 40 | $1,482.31 | $1,656.38 | $1,603.07 |
| 1660 | Dotted temporary traffic stripe (701F000) | LF | 2,260 | $0.28 | $0.31 | $0.30 |
| 1670 | Solid white, class W, type A traffic stripe (701G144) | LF | 570 | $6.39 | $7.15 | $6.92 |
| 1680 | Solid yellow, class W, type A traffic stripe (5" wide) (701G154) | LF | 589 | $6.39 | $7.15 | $6.92 |
| 1690 | Traffic control markings, class 2, type A (703A002) | SF | 23,268 | $6.39 | $7.15 | $6.92 |
| 1700 | Traffic control markings, class W, type A (703A011) | SF | 68 | $17.44 | $19.49 | $18.86 |
| 1710 | Traffic control legends, class 2, type A (703B002) | SF | 3,526 | $7.27 | $8.12 | $7.86 |
| 1720 | Traffic control legends, class W, type A (703B011) | SF | 23 | $20.35 | $22.73 | $22.00 |
| 1730 | Temporary traffic control markings (paint) (703D002) | SF | 8,849 | $3.49 | $3.90 | $3.77 |
| 1740 | Pavement markers, class C, type 2- C (705A022) | EACH | 4,680 | $8.14 | $9.09 | $8.80 |
| 1750 | Pavement markers, class A-H, type 2-C (705A030) | EACH | 5,933 | $6.39 | $7.15 | $6.92 |
| 1760 | Pavement markers, class A-H, type 1-B (705A032) | EACH | 55 | $6.39 | $7.15 | $6.92 |
| 1770 | Pavement markers, class A-H, type 2-D (705A037) | EACH | 18 | $6.39 | $7.15 | $6.92 |
| 1780 | Pavement markers, class A-H, type 2-E (705A038) | EACH | 190 | $6.39 | $7.15 | $6.92 |
| 1790 | Class 10 aluminum flat sign panels (type XI background) (710A163) | SF | 27 | $26.88 | $29.88 | $45.72 |
| 1800 | Class 4, aluminum flat sign panels (type IV background) (710A171) | SF | 159 | $24.54 | $27.28 | $38.10 |
| 1810 | Class 6 aluminum flat sign panels (type IV or XI background) (710A186) | SF | 167 | $40.90 | $45.47 | $62.23 |
| 1820 | Class 6 aluminum multiple flat sign panels (type IV or XI background) (710A188) | SF | 1,405 | $40.90 | $45.47 | $62.23 |
| 1830 | Roadway sign post (S4 X 7.7 steel beam) (710B006) | LF | 32 | $251.23 | $279.31 | $400.05 |
| 1840 | Roadway sign post (W10 X 22 steel beam) (710B013) | LF | 104 | $227.86 | $253.33 | $444.50 |
| 1850 | Roadway sign post (#3 U channel, galvanized steel or 2 ", 14 GA square tubular steel) (710B021) | LF | 658 | $25.71 | $28.58 | $26.67 |
| 1860 | Removal of existing roadway signs (710C000) | LS | 1 | $17,527 | $19,487 | $44,450 |
| 1870 | Overhead roadway sign structure no. ohs-1 ohs-2 & ohs-3 (717A000) | LS | 1 | $213,896 | $237,807 | $234,952 |
| 1880 | Vehicular impact attenuator assembly (MASH) (unidirectional,TL- 3) (720A074) | EACH | 5 | $39,528 | $53,264 | $52,071 |
| 1890 | Portable concrete safety barriers, type 6 (726A000) | LF | 6,200 | $63.37 | $75.35 | $69.28 |
| 1900 | Portable concrete safety barriers, type 6-A (726A001) | LF | 150 | $54.63 | $64.96 | $59.72 |
| 1910 | Portable impact attenuator assembly (unidirectional,TL-2) (726D020) | EACH | 13 | $13,657 | $16,239 | $14,931 |
| 1920 | Fiber optic trunk cable, 96F (729A005) | LF | 5,625 | $6.81 | $3.78 | $5.85 |
| 1930 | Fiber optic drop cable, 12F (729A101) | LF | 1,550 | $5.30 | $2.19 | $3.38 |
| 1940 | Fan-out kit (729B020) | EACH | 1 | $1,900.94 | $112.67 | $180.98 |
| 1950 | Conduit, underground, non-metallic, 2 inch (729I101) | LF | 25 | $376.54 | $35.79 | $30.16 |
| 1960 | Conduit, underground, non-metallic, 2 X 2 inch (729I108) | LF | 4,420 | $376.54 | $172.33 | $36.20 |
| 1970 | Messenger (729I600) | LF | 25 | $105.66 | $331.41 | $12.07 |
| 1980 | Locate tone wire (729I800) | LF | 4,580 | $0.54 | $0.93 | $1.21 |
| 1990 | Warning tape (729I810) | LF | 3,925 | $4.09 | $0.46 | $1.81 |
| 2000 | Miscellaneous infrastructure, fusion splicing (729N000) | EACH | 684 | $54.29 | $53.03 | $82.04 |
| 2010 | Miscellaneous infrastructure, splice closure, underground, 96 fiber (729N117) | EACH | 7 | $1,959.91 | $1,164.04 | $1,809.77 |
| 2020 | Miscellaneous infrastructure, commbox, type F1 (729N301) | EACH | 9 | $4,596.68 | $3,579.22 | $3,619.54 |
| 2030 | Miscellaneous infrastructure, commbox, type F2 (729N302) | EACH | 5 | $4,459.75 | $4,175.75 | $4,222.79 |
| 2040 | Miscellaneous infrastructure, fiber marker post (729N500) | EACH | 13 | $173.05 | $191.02 | $301.63 |
| 2050 | Removal of existing traffic control unit (partial) ( SR-38 (US-280) at overton road) (730A012) | LS | 1 | $1,610.20 | $1,799.28 | $6,032.56 |
| 2060 | Removal of existing traffic control unit (partial) ( SR-38 (US-280) at dolly ridge road/cahaba river road) (730A013) | LS | 1 | $4,993.35 | $5,579.73 | $6,032.56 |
| 2070 | Removal of existing traffic control unit (partial) ( SR-38 (US-280) at summit boulevard) (730A014) | LS | 1 | $8,731.09 | $9,756.41 | $6,032.56 |
| 2080 | Furnishing and installing traffic control unit ( SR-38 (US-280) at cherokee road) (730C000) | LS | 1 | $4,691.07 | $5,241.96 | $21,717 |
| 2090 | Furnishing and installing traffic control unit ( SR-38 (US-280) at overton road) (730C001) | LS | 1 | $22,107 | $24,703 | $21,717 |
| 2100 | Furnishing and installing traffic control unit ( SR-38 (US-280) at rocky ridge road) (730C002) | LS | 1 | $19,782 | $22,105 | $21,717 |
| 2110 | Furnishing and installing traffic control unit ( SR-38 (US-280) at green valley road) (730C003) | LS | 1 | $32,907 | $36,772 | $21,717 |
| 2120 | Furnishing and installing traffic control unit ( SR-38 (US-280) at dolly ridge road/cahaba river road) (730C004) | LS | 1 | $15,061 | $16,830 | $21,717 |
| 2130 | Furnishing and installing traffic control unit ( SR-38 (US-280) at summit boulevard) (730C005) | LS | 1 | $45,832 | $51,215 | $21,717 |
| 2140 | Furnishing and installing traffic control unit ( SR-38 (US-280) at I- 459 southbound ramps) (730C006) | LS | 1 | $5,574.65 | $6,229.29 | $33,782 |
| 2150 | Furnishing and installing traffic control unit ( (SR-38 (US-280) at I- 459 northbound ramps) (730C007) | LS | 1 | $3,388.96 | $3,786.95 | $33,782 |
| 2160 | Furnishing and installing traffic control unit ( (SR-38 (US-280) at cahaba river road/fire station) (730C008) | LS | 1 | $3,075.06 | $3,436.18 | $33,782 |
| 2170 | Metal traffic signal pole foundation (730E000) | EACH | 2 | $8,888.05 | $9,931.80 | $21,717 |
| 2180 | Metal traffic signal pole with 35' mast arm assembly (730F000) | EACH | 1 | $26,240 | $29,321 | $27,750 |
| 2190 | Metal traffic signal strain pole (730G001) | EACH | 1 | $22,456 | $25,093 | $26,543 |
| 2200 | Traffic signal junction box type S1 (730K001) | EACH | 1 | $1,133.53 | $1,266.64 | $784.24 |
| 2210 | Traffic signal junction box type S3 (730K003) | EACH | 1 | $4,795.70 | $5,358.88 | $3,016.28 |
| 2220 | 1", non-metallic, conduit (730L003) | LF | 25 | $14.30 | $15.98 | $14.48 |
| 2230 | 2", non-metallic, conduit (730L005) | LF | 180 | $14.24 | $15.91 | $18.10 |
| 2240 | Luminaire extension assembly, 12' (730N000) | EACH | 2 | $3,127.38 | $3,494.64 | $4,222.79 |
| 2250 | Vehicular signal head, 12 inch, 1 (730P020) | EACH | 2 | $1,360.24 | $1,519.98 | $1,809.77 |
| 2260 | Vehicular signal head, 12 inch, 3 (730P022) | EACH | 21 | $1,761.33 | $1,968.17 | $2,171.72 |
| 2270 | Vehicular signal head, 12 inch, 4 (730P023) | EACH | 3 | $2,017.11 | $2,253.98 | $2,533.68 |
| 2280 | Electrical power service assembly with wood pole (730T010) | EACH | 1 | $4,778.27 | $5,339.39 | $4,584.74 |
| 2290 | Video detection system ( SR-38 (US- 280) at overton road) (730U015) | LS | 1 | $81,841 | $91,452 | $78,423 |
| 2300 | Video detection system ( SR-38 (US- 280) at summit boulevard) (730U016) | LS | 1 | $81,841 | $91,452 | $78,423 |
| 2310 | Radar detection system ( SR-38 (US-280 at rocky ridge road) (730U400) | LS | 1 | $34,965 | $39,071 | $47,054 |
| 2320 | Wood pole (734U090) | EACH | 2 | $3,193.94 | $4,507.96 | $3,378.24 |
| 2330 | Construction signs (740B000) | SF | 1,913 | $8.76 | $9.74 | $10.37 |
| 2340 | Channelizing drums (740D000) | EACH | 1,645 | $33.89 | $37.67 | $67.40 |
| 2350 | Cones (36 inches high) (740E000) | EACH | 150 | $25.71 | $28.58 | $32.41 |
| 2360 | Barricades, type III (740F002) | EACH | 34 | $262.91 | $292.30 | $317.57 |
| 2370 | Portable sequential arrow and chevron sign unit (741C010) | EACH | 4 | $4,615.57 | $5,131.54 | $3,694.17 |
| 2380 | Portable changeable message sign, type 2 (742A001) | EACH | 10 | $12,850 | $14,286 | $16,332 |
| 2390 | Uniformed police officer (745A000) | HR | 4,000 | $87.43 | $77.95 | $138.30 |
| 2400 | 6" electrical conduit, 1 line, type 1 installation (756A027) | LF | 885 | $695.52 | $320.80 | $150.81 |
| 2410 | 6" electrical conduit, 1 line, type 5 installation (756A028) | LF | 710 | $671.15 | $320.80 | $150.81 |
| 2430 | Video detection zone adjustment (760A000) | EACH | 32 | $488.29 | $545.63 | $844.56 |
| 2440 | Radar detection zone adjustment (760A002) | EACH | 33 | $488.29 | $545.63 | $904.88 |
| 2450 | Roadway closure rental fee (766A000) | LS | 1 | $82,360 | $90,939 | $88,012 |
| 2460 | Trainee hours at 80 cents per hour (999 000) | HR | 1,760 | $0.80 | $0.80 | $0.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of January 31, 2025. Compiled by Mirage Metrics.