Dunn Construction Company, Inc.: ALDOT bid record
Dunn Construction Company, Inc. submitted 57 bids on Alabama DOT contracts in the data, from 28 JAN 2022 to 28 AUG 2026, and was the low bidder on 16 of them (28%). When it was not low, its total sat a median +7.0% above the low bid.
- Owner
- Alabama DOT
- Low bid volume
- $123,058,983
- Latest bid
- 28 AUG 2026
- Data through
- 28 AUG 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 9 | 3 | 33% |
| 2023 | 16 | 5 | 31% |
| 2024 | 10 | 3 | 30% |
| 2025 | 14 | 2 | 14% |
| 2026 | 8 | 3 | 38% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| 0301 | 23 | 7 | 30% |
| 0504 | 9 | 3 | 33% |
| 1008 | 8 | 3 | 38% |
| 0305 | 8 | 2 | 25% |
| 0302 | 5 | 1 | 20% |
| 0405 | 3 | 0 | 0% |
| 0505 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Tack coat | 405A000 | GAL | 52 | 40 (77%) | $3.71 | $4.55 |
| Micro-milling existing pavement (approximately 1.10" thru 2.00" thick) | 408B001 | SY | 29 | 16 (55%) | $2.04 | $2.07 |
| Open graded friction course tack coat | 420B000 | GAL | 17 | 16 (94%) | $5.33 | $7.41 |
| Micro-milling existing pavement (approximately 0.00" thru 1.00" thick) | 408B000 | SY | 19 | 14 (74%) | $1.33 | $1.75 |
| Portable sequential arrow and chevron sign unit | 741C010 | EACH | 46 | 12 (26%) | $1,572.73 | $1,597.10 |
| Channelizing drums | 740D000 | EACH | 50 | 11 (22%) | $30.35 | $33.00 |
| Superpave bituminous concrete wearing surface layer, 1/2" maximum aggregate size mix, esal range C/D | 424A360 | TON | 28 | 11 (39%) | $111.87 | $120.00 |
| Smoothness testing, certified inertial profiler | 410I000 | EACH | 17 | 11 (65%) | $3,547.35 | $6,155.57 |
| Material remixing device | 410H000 | EACH | 53 | 10 (19%) | $41,100 | $34,670 |
| Portable changeable message sign, type 2 | 742A001 | EACH | 34 | 9 (26%) | $3,264.28 | $4,210.53 |
| Topsoil | 650A000 | CY | 17 | 9 (53%) | $44.04 | $45.00 |
| Crushed aggregate, section 825, for miscellaneous use | 305B077 | TON | 29 | 7 (24%) | $80.55 | $70.30 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Wiregrass Construction Company, Inc. | 54 | 27 of 54 |
| Apac-Alabama, Inc. | 26 | 11 of 26 |
| Midsouth Paving, Inc. | 14 | 7 of 14 |
| Vulcan Materials Asphalt and Construction, | 7 | 5 of 7 |
| Whitaker Contracting Corporation | 4 | 4 of 4 |
| Alabama Grading & Excavation, LLC. | 3 | 3 of 3 |
| Gary Ingram Grading & Paving, Inc. | 2 | 2 of 2 |
| Gillespie Construction, LLC | 2 | 2 of 2 |
| James Paving Company, LLC | 1 | 0 of 1 |
| McInnis Construction, LLC & Chilton | 1 | 0 of 1 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 28 AUG 2026 | 20260828021 | 1008 | RESURFACING, GUARDRAIL INSTALL (GUARDRAIL, GUARDRAIL END ANCHORS, AND GUARDRAIL STEEL BLOCKOUT REPLACEMENT), AND STRIPE ON I-22 FROM A POINT | 1 of 3 | $8,271,788 | Low, 2.0% under the second |
| 29 MAY 2026 | 20260529023 | 0301 | MICRO-MILLING, RESURFACING (SCRUB SEAL), BRIDGE GUARDRAIL RETROFIT, GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-3 (US-31) FROM THE INTE | 4 of 4 | $7,167,150 | +18% |
| 29 MAY 2026 | 20260529024 | 0301 | SAFETY WIDENING, RESURFACING (SCRUB SEAL), BRIDGE GUARDRAIL RETROFIT, GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-79 FROM WINEWOOD ROAD | 2 of 3 | $4,904,590 | +2.0% |
| 24 APR 2026 | 20260424013 | 0301 | SAFETY WIDENING, MICRO-MILLING, RESURFACING (SCRUB SEAL), GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-79 FROM A POINT SOUTH OF THE FIVE | 1 of 3 | $2,437,529 | Low, 5.0% under the second |
| 24 APR 2026 | 20260424023 | 0302 | RESURFACING (SCRUB SEAL), GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-25 (US-411) FROM THE JUNCTION OF MADDOX FARM ROAD IN ODENVILLE TO | 5 of 5 | $3,526,766 | +34% |
| 24 APR 2026 | 20260424027 | 0302 | SAFETY WIDENING, MICRO-MILLING, RESURFACING (SCRUB SEAL), AND TRAFFIC STRIPE ON SR-25 (US-231) FROM THE JUNCTION OF THE US-231/US-431 ROUNDA | 4 of 4 | $2,410,646 | +36% |
| 24 APR 2026 | 20260424032 | 0301 | MICRO-MILLING, RESURFACING, AMERICAN WITH DISABILITIES ACT (ADA) UPGRADES, TRAFFIC SIGNS, AND TRAFFIC STRIPE ON VARIOUS ROUTES AT VARIOUS LO | 2 of 3 | $4,216,651 | +2.0% |
| 27 FEB 2026 | 20260227038 | 0504 | PLANING, RESURFACING (SCRUB SEAL), GUARDRAIL INSTALLATION, TRAFFIC SIGNAL UPGRADES (BACKPLATE REPLACEMENT), AND STRIPE ON SR-25 FROM THE INT | 1 of 3 | $1,980,602 | Low, 7.0% under the second |
| 07 NOV 2025 | 20251107026 | 1008 | MICRO-FINE MILL, RESURFACING, GUARDRAIL INSTALL, AND STRIPE ON I-22 FROM A POINT 0.800 MILE EAST OF THE CR-61 OVERPASS SOUTHEAST OF CORDOVA | 2 of 3 | $5,290,978 | +9.0% |
| 26 SEP 2025 | 20250926017 | 0301 | RESURFACING, GUARDRAIL INSTALLATION, AND STRIPE ON I-20/I-59 FROM A POINT SOUTH OF THE FAIRFIELD BOULEVARD BRIDGE TO A POINT SOUTH OF THE VA | 1 of 3 | $1,503,936 | Low, 14% under the second |
| 26 SEP 2025 | 20250926018 | 0301 | MICRO-MILL, RESURFACE, GUARDRAIL, CONCRETE CLEAN, & STRIPE ON I-459 FROM THE SOUTH END OF THE BRIDGE OVER SR-150 TO THE NORTH END OF THE RAM | 2 of 3 | $5,734,293 | +4.0% |
| 29 AUG 2025 | 20250829007 | 0302 | MICRO-FINE MILLING, RESURFACING, AND TRAFFIC STRIPE ON I-20 FROM A POINT 0.500 MILE EAST OF THE KELLY CREEK ROAD INTERCHANGE TO WEST OF THE | 1 of 4 | $12,549,275 | Low, 2.0% under the second |
| 25 JUL 2025 | 20250725001 | 0301 | INTERCHANGE MODIFICATIONS ON SR-149 (LAKESHORE PARKWAY) AT THE I-65 INTERCHANGE IN HOMEWOOD | 5 of 7 | $25,373,630 | +9.0% |
| 27 JUN 2025 | 20250627010 | 0301 | MICRO-MILLING, RESURFACING, AND TRAFFIC SIGNAL UPGRADES ON SR-5 (US-11) FROM THE SOUTHWEST CITY LIMITS OF BIRMINGHAM TO THE JUNCTION OF ARKA | 2 of 3 | $2,606,753 | +2.0% |
| 27 JUN 2025 | 20250627014 | 0301 | SAFETY WIDEN, MICRO-MILL, RESURFACE, TRAFFIC SIGNALS, STRIPE ON SR-79 FROM THE INTERSECTION OF ALABAMA STREET TO A POINT SOUTH OF THE BRIDGE | 2 of 3 | $2,730,999 | +2.0% |
| 30 MAY 2025 | 20250530001 | 0305 | ROADWAY IMPROVEMENTS (ADD LANES AND BRIDGE RAISING) ON I-65 FROM A POINT 0.200 MILE SOUTH OF THE CR-87 INTERCHANGE IN CALERA TO A POINT 0.56 | 2 of 4 | $33,423,384 | +5.0% |
| 28 MAR 2025 | 20250328017 | 0504 | SAFETY WIDEN, PLANING, RESURFACE, GUARDRAIL, AND STRIPE ON SR-6 (US-82) FROM THE JUNCTION OF WILSON ROAD SOUTHEAST OF EOLINE TO THE JUNCTION | 2 of 3 | $3,143,079 | +7.0% |
| 28 MAR 2025 | 20250328018 | 0405 | RESURFACE (SCRUB SEAL), BRIDGE GUARDRAIL RETROFIT, & STRIPE ON SR-38 (US-280) FROM THE JUNCTION OF CR-25 TO A POINT 0.211 MILE EAST OF THE I | 3 of 4 | $7,708,644 | +21% |
| 31 JAN 2025 | 20250131018 | 0301 | CONCRETE REPAIR, RESURFACING, AND ADDITIONAL LANES ON SR-38 (US-280) FROM THE JUNCTION OF ROSEDALE DRIVE IN HOMEWOOD TO THE CAHABA RIVER BRI | 2 of 3 | $53,100,000 | +1.0% |
| 31 JAN 2025 | 20250131019 | 0305 | MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON SR-38 (US-280) FROM THE INTERSECTION OF CR-55 TO THE JUNCTION OF CR-62 | 2 of 3 | $3,447,859 | +3.0% |
| 31 JAN 2025 | 20250131032 | 1008 | RESURFACE, TRAFFIC SIGNALS, WIM STATION, AND TRAFFIC STRIPE ON SR-5 FROM THE JEFFERSON COUNTY LINE TO A POINT 0.250 MILE WEST OF THE JUNCTIO | 3 of 3 | $7,521,819 | +21% |
| 31 JAN 2025 | 20250131048 | 0504 | RESURFACING, TRAFFIC SIGNAL UPGRADES, AND TRAFFIC STRIPE ON SR-3 (US-31) FROM NEWPORT AVENUE TO INVERNESS DRIVE AND ON SR-145 FROM SR-3 (US- | 2 of 2 | $2,272,749 | +11% |
| 06 DEC 2024 | 20241206002 | 0305 | GRADE, DRAIN, PAVE, BRIDGE REMOVAL, AND BRIDGE REPLACEMENT ON I-65 FROM THE SR-3 (US-31) INTERCHANGE NORTH OF CALERA TO A POINT 0.200 MILE S | 1 of 3 | $44,058,580 | Low, 1.0% under the second |
| 08 NOV 2024 | 20241108019 | 1008 | MICRO-MILLING, RESURFACING, GUARDRAIL INSTALL, AND STRIPE ON I-22 FROM THE SR-118 INTERCHANGE (MP 51.788) TO THE SR- 118 INTERCHANGE (MP 57. | 1 of 2 | $5,956,682 | Low, 7.0% under the second |
| 08 NOV 2024 | 20241108051 | 0504 | RESURFACE, BRIDGE GUARDRAIL RETROFIT, GUARDRAIL, AND STRIPE ON SR-25 FROM 0.280 MILE NORTH OF THE JUNCTION OF SR-6 (US-82) IN CENTREVILLE TO | 2 of 3 | $3,289,046 | +4.0% |
How this record was read
ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
- Every bid counted here matched its published total to within one dollar; ALDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.