ALDOT contract 20250530001 bid tabulation
ROADWAY IMPROVEMENTS (ADD LANES AND BRIDGE RAISING) ON I-65 FROM A POINT 0.200 MILE SOUTH OF THE CR-87 INTERCHANGE IN CALERA TO A POINT 0.560 MILE SOUTH OF BUCK CREEK. Let by Alabama DOT on May 30, 2025, Shelby, 0305. 4 bids received; low bid $31,782,578 by Chilton Contractors, Inc..
- Owner
- Alabama DOT
- Letting
- 30 MAY 2025
- Pay items
- 225
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Chilton Contractors, Inc. | $31,782,578 | Low |
| 2 | Dunn Construction Company, Inc. | $33,423,384 | +5.0% |
| 3 | Wiregrass Construction Company, Inc. | $33,469,155 | +5.0% |
| 4 | GFC Construction Inc & Dominion | $36,781,455 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Chilton Contractors, Inc. | 2. Dunn Construction Company, Inc. | 3. Wiregrass Construction Company, Inc. | 4. GFC Construction Inc & Dominion |
|---|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (maximum allowable bid $ $8,000.00 per acre) (approximately 48 acres) (201A002) | LS | 1 | $300,000 | $358,650 | $316,500 | $384,000 |
| 0020 | Removing concrete slope paving (206C002) | SY | 8 | $68.12 | $60.29 | $54.28 | $556.20 |
| 0030 | Removing concrete flumes (206C003) | SY | 1,122 | $10.79 | $9.55 | $8.59 | $27.27 |
| 0040 | Removing pipe (206D000) | LF | 111 | $59.77 | $56.79 | $51.12 | $37.80 |
| 0050 | Removing guardrail (206D001) | LF | 13,654 | $4.03 | $4.73 | $4.31 | $4.03 |
| 0060 | Removing curb (206D002) | LF | 510 | $12.56 | $11.12 | $10.00 | $27.00 |
| 0070 | Removing headwalls (206E000) | EACH | 20 | $569.25 | $503.77 | $453.54 | $1,350.00 |
| 0080 | Removing inlets (206E001) | EACH | 15 | $1,345.39 | $1,406.30 | $1,266.09 | $1,350.00 |
| 0090 | Removing guardrail end anchor (all type) (206E008) | EACH | 14 | $252.14 | $295.89 | $269.19 | $172.50 |
| 0100 | Removing guardrail end anchor (type 2A) (206E014) | EACH | 4 | $1,008.57 | $1,183.55 | $1,076.77 | $172.50 |
| 0110 | Unclassified excavation (210A000) | CY | 68,407 | $29.23 | $26.90 | $24.23 | $35.01 |
| 0120 | Borrow excavation (210D000) | CY | 1,596 | $23.03 | $20.80 | $18.35 | $56.61 |
| 0130 | Borrow excavation (sand fill, complete in place) (210D101) | CY | 2,536 | $74.14 | $65.61 | $59.07 | $72.81 |
| 0140 | Borrow excavation (underwater backfill) (aldot #57) (210F002) | TON | 863 | $72.65 | $59.61 | $57.89 | $62.45 |
| 0150 | Structure excavation (214A000) | CY | 7,823 | $17.01 | $15.05 | $13.55 | $16.78 |
| 0160 | Foundation backfill, commercial (214B001) | CY | 2,135 | $107.61 | $84.37 | $77.44 | $63.88 |
| 0170 | Cement mortar flowable backfill, mix 4 (260A003) | CY | 7 | $984.11 | $994.16 | $895.03 | $999.00 |
| 0180 | Crushed aggregate base course, type B, plant mixed, 6" compacted thickness (301A012) | SY | 101,734 | $17.97 | $17.96 | $14.79 | $15.47 |
| 0190 | Crushed aggregate, section 825, for miscellaneous use (305B077) | TON | 267 | $63.39 | $56.45 | $50.51 | $53.86 |
| 0200 | Bituminous treatment AE (401A043) | SY | 101,734 | $4.03 | $3.57 | $2.91 | $3.11 |
| 0210 | Tack coat (405A000) | GAL | 35,072 | $3.52 | $3.59 | $3.00 | $4.15 |
| 0220 | Micro-milling existing pavement (approximately 0.00" thru 1.00" thick) (408B000) | SY | 13,730 | $1.11 | $1.80 | $2.92 | $1.30 |
| 0230 | Micro-milling existing pavement (approximately 1.10" thru 2.00" thick) (408B001) | SY | 41,639 | $1.11 | $1.12 | $2.35 | $1.30 |
| 0240 | Material remixing device (410H000) | EACH | 1 | $82,412 | $88,908 | $250,500 | $97,129 |
| 0250 | Smoothness testing, certified inertial profiler (410I000) | EACH | 1 | $2,211.06 | $2,293.81 | $6,000.00 | $2,605.90 |
| 0260 | Stone matrix asphalt wearing layer, 1/2" maximum aggregate size (423A003) | TON | 10,508 | $118.59 | $127.28 | $132.27 | $139.77 |
| 0270 | Stone matrix asphalt binder layer, 3/4" maximum aggregate size (423B002) | TON | 11,279 | $110.55 | $118.12 | $121.44 | $130.30 |
| 0280 | Superpave bituminous concrete wearing surface layer, 1/2" maximum aggregate size mix, esal range C/D (424A360) | TON | 4,128 | $92.46 | $99.30 | $122.77 | $108.97 |
| 0290 | Superpave bituminous concrete upper binder layer, patching, 3/4" maximum aggregate size mix, esal range E (424B284) | TON | 500 | $122.61 | $132.30 | $154.36 | $144.51 |
| 0300 | Superpave bituminous concrete upper binder layer, leveling, 3/4" maximum aggregate size mix, esal range E (424B288) | TON | 1,594 | $99.50 | $106.60 | $228.27 | $117.27 |
| 0310 | Superpave bituminous concrete lower binder layer, 1" maximum aggregate size mix, esal range E (424B581) | TON | 46,554 | $70.45 | $75.78 | $94.41 | $83.03 |
| 0320 | Superpave bituminous concrete lower binder layer, leveling, 1" maximum aggregate size mix, esal range E (424B589) | TON | 500 | $97.49 | $105.04 | $110.03 | $114.90 |
| 0330 | Superpave bituminous concrete upper binder layer, 3/4" maximum aggregate size mix, esal range C/D (424B650) | TON | 996 | $97.49 | $104.27 | $128.03 | $114.90 |
| 0340 | Superpave bituminous concrete lower binder layer, 1" maximum aggregate size mix, esal range C/D (424B681) | TON | 3,479 | $81.41 | $87.73 | $97.60 | $95.94 |
| 0350 | Scoring bituminous pavement surface (428A001) | MI | 11 | $957.79 | $1,863.93 | $281.31 | $908.50 |
| 0360 | Aggregate surfacing (1" down, crusher run) (430B043) | TON | 85,547 | $43.91 | $41.46 | $34.98 | $39.32 |
| 0370 | Patching (460A000) | LB | 4,410 | $4.00 | $4.73 | $6.50 | $6.90 |
| 0380 | Steel reinforcement (502A000) | LB | 1,089 | $2.42 | $2.84 | $2.58 | $2.76 |
| 0390 | Raising existing bridge, station 700+44.35 (520B000) | LS | 1 | $287,879 | $313,640 | $306,879 | $346,902 |
| 0400 | Retaining wall, number 1 (gravity wall) (529A020) | SF | 1,751 | $236.00 | $260.64 | $233.76 | $287.91 |
| 0410 | Retaining wall, number 2 (gravity wall) (529A021) | SF | 1,062 | $298.57 | $277.46 | $248.90 | $287.91 |
| 0420 | Retaining wall, number 3 (MSE wall) (529A022) | SF | 1,237 | $108.78 | $127.04 | $113.85 | $176.90 |
| 0430 | Retaining wall, number 4 (MSE wall) (529A023) | SF | 812 | $127.42 | $139.85 | $125.40 | $176.90 |
| 0440 | 18" roadway pipe (class 3 R.C.) (530A001) | LF | 27 | $102.96 | $93.92 | $84.56 | $265.64 |
| 0450 | 24" roadway pipe (class 3 R.C.) (530A002) | LF | 5,816 | $118.56 | $105.30 | $94.80 | $101.07 |
| 0460 | 30" roadway pipe (class 3 R.C.) (530A003) | LF | 116 | $149.75 | $138.46 | $124.66 | $166.12 |
| 0470 | 36" roadway pipe (class 3 R.C.) (530A004) | LF | 67 | $184.66 | $171.20 | $154.13 | $180.98 |
| 0480 | 18" roadway pipe (class 3 R.C.) (extension) (530A101) | LF | 8 | $391.43 | $349.91 | $315.02 | $563.58 |
| 0490 | 24" roadway pipe (class 3 R.C.) (extension) (530A102) | LF | 319 | $200.74 | $178.12 | $160.36 | $152.94 |
| 0500 | 30" roadway pipe (class 3 R.C.) (extension) (530A103) | LF | 98 | $259.02 | $236.65 | $213.05 | $168.11 |
| 0510 | 36" roadway pipe (class 3 R.C.) (extension) (530A104) | LF | 39 | $320.50 | $293.36 | $264.11 | $308.42 |
| 0520 | 24" roadway pipe (14 gauge C.C.S.) (stack pipe)(no bedding required) (530A802) | LF | 5 | $986.32 | $872.87 | $785.84 | $1,305.00 |
| 0530 | 36" span, 23" rise roadway pipe (class 3 R.C.) (530B003) | LF | 111 | $184.10 | $163.82 | $147.48 | $168.04 |
| 0540 | 24" roadway pipe, jacked installation (smooth steel) (530C002) | LF | 271 | $1,015.62 | $1,244.55 | $1,085.38 | $791.99 |
| 0550 | 30" roadway pipe, jacked installation (smooth steel) (530C003) | LF | 108 | $1,204.03 | $1,970.54 | $1,286.74 | $1,055.91 |
| 0560 | 36" roadway pipe, jacked installation (smooth steel) (530C004) | LF | 83 | $1,221.16 | $2,306.08 | $1,305.04 | $1,224.67 |
| 0570 | 12" storm sewer pipe (class 3 R.C.) (533A096) | LF | 113 | $98.45 | $86.88 | $78.22 | $91.52 |
| 0580 | 15" storm sewer pipe (class 3 R.C.) (533A097) | LF | 55 | $98.45 | $88.19 | $79.40 | $116.83 |
| 0590 | 18" storm sewer pipe (class 3 R.C.) (533A098) | LF | 110 | $102.96 | $93.92 | $84.56 | $120.07 |
| 0600 | 24" storm sewer pipe (class 3 R.C.) (533A099) | LF | 173 | $128.56 | $114.15 | $102.77 | $129.85 |
| 0610 | 36" storm sewer pipe (class 3 R.C.) (533A101) | LF | 18 | $184.69 | $171.23 | $154.16 | $330.60 |
| 0620 | 36" span, 23" rise storm sewer pipe (class 3 R.C.) (533B100) | LF | 70 | $197.39 | $175.57 | $158.07 | $192.99 |
| 0630 | Cleaning pipe underdrain outlets (534A000) | EACH | 10 | $463.92 | $549.07 | $484.55 | $517.50 |
| 0640 | 66" roadway pipe rehabilitation (538A011) | LF | 205 | $2,770.26 | $3,141.89 | $2,772.68 | $2,961.25 |
| 0650 | Mobilization (600A000) | LS | 1 | $1,130,566 | $854,537 | $2,446,000 | $4,003,129 |
| 0660 | 6" underdrain pipe (606A000) | LF | 200 | $45.69 | $42.91 | $38.65 | $27.16 |
| 0670 | Separation geotextile (608A000) | SY | 1,856 | $4.40 | $3.89 | $3.50 | $3.40 |
| 0680 | Loose riprap, class 1 (610C000) | TON | 731 | $105.99 | $88.53 | $84.45 | $69.50 |
| 0690 | Loose riprap, class 2 (610C001) | TON | 464 | $107.79 | $88.53 | $85.88 | $69.50 |
| 0700 | Loose riprap, class 3 (610C002) | TON | 84 | $161.04 | $134.39 | $128.31 | $79.70 |
| 0710 | Filter blanket, geotextile (610D003) | SY | 12,067 | $4.17 | $3.69 | $3.32 | $3.40 |
| 0720 | Slope paving (614A000) | CY | 28 | $896.73 | $1,053.36 | $958.32 | $1,023.50 |
| 0730 | 18" roadway pipe end treatment, class 1 (619A002) | EACH | 1 | $2,176.32 | $2,556.46 | $2,325.82 | $2,484.00 |
| 0740 | 24" roadway pipe end treatment, class 1 (619A003) | EACH | 19 | $2,508.82 | $2,947.03 | $2,681.15 | $2,863.50 |
| 0750 | 30" roadway pipe end treatment, class 1 (619A004) | EACH | 4 | $2,670.03 | $3,136.40 | $2,853.44 | $3,047.50 |
| 0760 | 30" roadway pipe end treatment, class 2 (619A054) | EACH | 2 | $4,065.49 | $4,775.61 | $4,344.76 | $4,640.25 |
| 0770 | 36" roadway pipe end treatment, class 2 (619A055) | EACH | 2 | $5,561.72 | $6,533.18 | $5,943.76 | $6,348.00 |
| 0780 | 36" span, 23" rise roadway pipe end treatment, class 2 (619B068) | EACH | 1 | $5,138.54 | $6,036.09 | $5,491.52 | $5,865.00 |
| 0790 | Minor structure concrete (620A000) | CY | 21 | $3,284.63 | $3,858.36 | $3,510.27 | $3,749.00 |
| 0800 | Junction boxes, type 1 or 1P (621A011) | EACH | 6 | $5,662.47 | $6,651.53 | $6,051.44 | $6,069.60 |
| 0810 | Junction boxes, type 1 or 2P (621A019) | EACH | 1 | $5,843.83 | $6,864.57 | $6,245.26 | $6,264.00 |
| 0820 | Junction box units, type 1 or 1P (621B011) | EACH | 2 | $1,148.62 | $1,349.25 | $1,227.52 | $1,231.20 |
| 0830 | Junction box units, type 1 or 2P (621B014) | EACH | 1 | $1,163.73 | $1,367.00 | $1,243.67 | $1,247.20 |
| 0840 | Inlets, type Y (621C020) | EACH | 3 | $3,335.01 | $3,917.54 | $3,564.10 | $3,806.50 |
| 0850 | Inlets, type E2 (621C054) | EACH | 14 | $12,594 | $14,794 | $13,460 | $14,375 |
| 0860 | Inlets, type E3 (621C069) | EACH | 5 | $10,579 | $12,427 | $11,306 | $12,075 |
| 0870 | Inlets, type E4 (621C070) | EACH | 29 | $13,602 | $15,978 | $14,536 | $15,525 |
| 0880 | Inlet units, type Y (621D019) | EACH | 5 | $1,108.31 | $1,301.90 | $1,184.45 | $1,265.00 |
| 0890 | Inlet units, type E2 (621D041) | EACH | 15 | $1,239.29 | $1,455.76 | $1,324.43 | $1,414.50 |
| 0900 | Inlet units, type E3 (621D046) | EACH | 5 | $962.22 | $1,130.29 | $1,028.31 | $1,098.25 |
| 0910 | Inlet units, type E4 (621D047) | EACH | 35 | $1,239.29 | $1,455.76 | $1,324.43 | $1,414.50 |
| 0920 | Concrete curb, type N (623B000) | LF | 32 | $97.73 | $114.80 | $104.45 | $111.55 |
| 0930 | Concrete curb, type N special (623B001) | LF | 24 | $190.43 | $223.69 | $203.51 | $217.35 |
| 0940 | Concrete median or safety barrier, type tes (629A012) | LF | 60 | $422.24 | $487.62 | $443.63 | $473.80 |
| 0950 | Concrete median or safety barrier, type 4A (reinforced) (retaining wall mounted) (629A086) | LF | 515 | $252.27 | $320.32 | $137.29 | $446.96 |
| 0960 | Concrete median or safety barrier, type CSF-42 (SE) (629A096) | LF | 3,125 | $166.84 | $189.37 | $172.28 | $184.00 |
| 0970 | Concrete median or safety barrier, type CSF-42 (FO) (629A097) | LF | 69 | $605.11 | $704.21 | $640.68 | $684.25 |
| 0980 | Concrete median or safety barrier, type CSF-54 (629A103) | LF | 2,828 | $136.02 | $159.78 | $145.36 | $155.25 |
| 0990 | Concrete median or safety barrier, type CSF-54 (SE) (629A104) | LF | 7,269 | $207.15 | $236.71 | $215.35 | $230.00 |
| 1000 | Concrete median or safety barrier, type CSF-54 (FO) (629A105) | LF | 301 | $532.59 | $618.99 | $563.15 | $601.45 |
| 1010 | Concrete median or safety barrier, type CSF-4A (629A107) | LF | 438 | $172.29 | $202.39 | $184.13 | $196.65 |
| 1020 | Steel beam guardrail, class A, type 2 (630A001) | LF | 2,900 | $22.19 | $26.04 | $23.69 | $28.75 |
| 1030 | Guardrail end anchor, type 8 (MASH) (630C077) | EACH | 11 | $1,210.29 | $1,420.26 | $1,292.12 | $1,265.00 |
| 1040 | Guardrail end anchor, type 13 (MASH) (630C079) | EACH | 7 | $3,530.01 | $4,142.41 | $3,768.69 | $3,565.00 |
| 1050 | Guardrail end anchor, type 20 series (MASH) (630C080) | EACH | 14 | $3,025.72 | $3,550.64 | $3,230.31 | $4,082.50 |
| 1060 | Topsoil from stockpiles (650B000) | CY | 19,109 | $23.39 | $20.69 | $18.63 | $15.67 |
| 1070 | Seeding (652A100) | ACRE | 48 | $1,500.00 | $1,775.32 | $1,655.53 | $1,620.00 |
| 1080 | Seeding(wetland mix) (652A110) | ACRE | 3 | $2,500.00 | $2,958.87 | $2,759.22 | $3,240.00 |
| 1090 | Mowing (652C000) | ACRE | 191 | $120.00 | $142.03 | $132.44 | $162.00 |
| 1100 | Solid sodding (bermuda) (654A001) | SY | 19,237 | $9.00 | $10.65 | $9.93 | $10.35 |
| 1110 | Mulching (656A010) | ACRE | 48 | $1,500.00 | $1,775.32 | $1,655.53 | $1,620.00 |
| 1120 | Erosion control product, type S3 (659C001) | SY | 788 | $1.90 | $2.25 | $2.10 | $2.16 |
| 1130 | Erosion control product, type S2 (659C002) | SY | 745 | $1.90 | $2.25 | $2.10 | $2.16 |
| 1140 | Erosion control product, type C2 (659C004) | SY | 2,778 | $1.90 | $2.25 | $2.10 | $2.16 |
| 1150 | Erosion control product, type C4 (659C005) | SY | 380 | $4.00 | $4.73 | $4.41 | $5.40 |
| 1160 | Erosion control product, type C8 (659C007) | SY | 2,694 | $4.00 | $4.73 | $4.41 | $5.40 |
| 1170 | Temporary seeding (665A000) | ACRE | 12 | $400.00 | $473.42 | $441.48 | $4,320.00 |
| 1180 | Temporary mulching (665B001) | TON | 107 | $800.00 | $946.84 | $882.95 | $10.80 |
| 1190 | Temporary pipe (665C010) | LF | 360 | $38.22 | $33.82 | $30.45 | $26.19 |
| 1200 | Temporary pipe end treatment (665D001) | EACH | 30 | $467.06 | $413.34 | $372.12 | $1,620.00 |
| 1210 | Polyethylene (665E000) | SY | 1,000 | $1.00 | $1.18 | $1.10 | $2.70 |
| 1220 | Hay bales (665F000) | EACH | 1,000 | $10.00 | $11.84 | $11.04 | $8.64 |
| 1230 | Sand bags (665G000) | EACH | 2,196 | $5.75 | $6.81 | $6.35 | $8.10 |
| 1240 | Flow baffle (665H005) | LF | 1,027 | $8.00 | $9.47 | $8.83 | $8.64 |
| 1250 | Temporary riprap, class 2 (665I000) | TON | 540 | $159.23 | $126.50 | $126.86 | $77.60 |
| 1260 | Silt fence (665J002) | LF | 23,361 | $4.25 | $5.03 | $4.69 | $3.91 |
| 1270 | Drainage sump excavation (665K000) | CY | 972 | $54.80 | $48.50 | $43.66 | $70.20 |
| 1280 | Temporary coarse aggregate,aldot number 1 (665N000) | TON | 2,000 | $76.63 | $54.59 | $61.05 | $61.55 |
| 1290 | Temporary coarse aggregate,aldot number 4 (665N001) | TON | 108 | $130.43 | $102.14 | $103.92 | $61.55 |
| 1300 | Silt fence removal (665O001) | LF | 23,361 | $0.50 | $0.59 | $0.55 | $1.40 |
| 1310 | Inlet protection, stage 3 or 4 (665P005) | EACH | 48 | $500.00 | $591.77 | $551.84 | $459.00 |
| 1320 | Wattle (665Q002) | LF | 4,380 | $7.00 | $8.28 | $7.73 | $8.64 |
| 1330 | Basin dewatering device (665X000) | EACH | 8 | $2,351.86 | $1,893.67 | $1,765.90 | $2,160.00 |
| 1340 | Pest control treatment (666A001) | ACRE | 48 | $175.00 | $207.12 | $193.15 | $16.20 |
| 1350 | Flocculant application, ditch check (672C100) | EACH | 192 | $10.00 | $11.84 | $11.04 | $21.60 |
| 1360 | Flocculant application, sedimentation basin (672C102) | EACH | 384 | $195.00 | $230.79 | $215.22 | $243.00 |
| 1370 | Construction safety fence (674A000) | LF | 1,000 | $2.00 | $2.37 | $2.21 | $6.48 |
| 1380 | Geometric controls (680A001) | LS | 1 | $345,480 | $379,350 | $350,000 | $432,000 |
| 1390 | Construction fuel (maximum bid limited to $ 1,509,300.00) (698A000) | LS | 1 | $217,000 | $259,424 | $233,659 | $0.00 |
| 1400 | Solid white, class 2, type A traffic stripe (5" wide) (701A227) | MI | 8 | $4,570.71 | $5,355.55 | $4,872.38 | $5,203.75 |
| 1410 | Solid yellow, class 2, type A traffic stripe (5" wide) (701A230) | MI | 8 | $4,570.71 | $5,355.55 | $4,872.38 | $5,203.75 |
| 1420 | Broken white, class 2, type A traffic stripe (5" wide) (701A239) | MI | 13 | $2,752.53 | $3,225.16 | $2,934.19 | $3,133.75 |
| 1430 | Solid white, class 2 type A traffic stripe (10" wide) (701A270) | MI | 2 | $21,333 | $24,997 | $22,741 | $24,288 |
| 1440 | Dotted, class 2, type A traffic stripe (5" wide) (701B207) | LF | 5,665 | $2.02 | $2.37 | $2.15 | $2.30 |
| 1450 | Broken temporary traffic stripe (701C000) | MI | 21 | $1,035.35 | $1,213.13 | $1,103.69 | $1,178.75 |
| 1460 | Solid temporary traffic stripe (701C001) | MI | 42 | $1,060.61 | $1,242.72 | $1,130.61 | $1,207.50 |
| 1470 | Solid traffic stripe removed (paint) (701D007) | MI | 40 | $2,525.25 | $2,958.87 | $2,691.92 | $2,875.00 |
| 1480 | Broken traffic stripe removed (paint) (701D014) | MI | 14 | $2,525.25 | $2,958.87 | $2,691.92 | $2,875.00 |
| 1490 | Dotted temporary traffic stripe (701F000) | LF | 8,601 | $0.20 | $0.24 | $0.22 | $0.23 |
| 1500 | Solid white, class W, type A traffic stripe (5"wide) (701G146) | LF | 496 | $5.05 | $5.92 | $5.38 | $5.75 |
| 1510 | Solid yellow, class W, type A traffic stripe (5" wide) (701G154) | LF | 496 | $5.05 | $5.92 | $5.38 | $5.75 |
| 1520 | Dotted traffic stripe removed (paint) (701H010) | LF | 6,098 | $0.51 | $0.59 | $0.54 | $0.58 |
| 1530 | Traffic control markings, class 2, type A (703A002) | SF | 4,558 | $5.81 | $6.81 | $6.19 | $6.61 |
| 1540 | Traffic control legends, class 2, type A (703B002) | SF | 127 | $6.06 | $7.10 | $6.46 | $6.90 |
| 1550 | Removal of existing traffic control markings or legends (paint) (703C000) | SF | 302 | $3.28 | $3.85 | $3.50 | $3.74 |
| 1560 | Temporary traffic control markings (703D001) | SF | 2,360 | $3.03 | $3.55 | $3.23 | $3.45 |
| 1570 | Pavement markers, class C, type 1- A (705A011) | EACH | 13,871 | $5.56 | $6.51 | $5.92 | $6.33 |
| 1580 | Pavement markers, class C, type 1- B (705A012) | EACH | 4,367 | $5.56 | $6.51 | $5.92 | $6.33 |
| 1590 | Pavement markers, class A-H, type 2-C (705A030) | EACH | 2,593 | $5.56 | $6.51 | $5.92 | $6.33 |
| 1600 | Pavement markers, class A-H, type 1-A (705A031) | EACH | 639 | $5.56 | $6.51 | $5.92 | $6.33 |
| 1610 | Pavement markers, class A-H, type 1-B (705A032) | EACH | 148 | $5.56 | $6.51 | $5.92 | $6.33 |
| 1620 | Pavement markers, class A-H, type 2-D (705A037) | EACH | 12 | $5.56 | $6.51 | $5.92 | $6.33 |
| 1630 | Pavement markers, class A-H, type 2-E (705A038) | EACH | 134 | $5.56 | $6.51 | $5.92 | $6.33 |
| 1640 | Barrier rail mounted delineator (mono-directional) (707G000) | EACH | 1,425 | $16.24 | $18.94 | $17.23 | $18.40 |
| 1650 | Class 9, aluminum flat sign panels (type XI background) (710A153) | SF | 8 | $22.34 | $26.04 | $23.69 | $25.30 |
| 1660 | Class 9, aluminum flat sign panels (type XI background, fluorescent) (710A154) | SF | 61 | $22.34 | $26.04 | $23.69 | $25.30 |
| 1670 | Class 4, aluminum flat sign panels (type IV background) (710A171) | SF | 75 | $23.86 | $27.81 | $25.30 | $27.03 |
| 1680 | Class 6 aluminum flat sign panels (type IV or XI background) (710A186) | SF | 138 | $38.58 | $45.66 | $40.92 | $43.70 |
| 1690 | Class 6 aluminum multiple flat sign panels (type IV or XI background) (710A188) | SF | 1,820 | $38.58 | $45.66 | $40.92 | $43.70 |
| 1700 | Roadway sign post (3" O.D. steel uniform diameter) (710B004) | LF | 36 | $101.52 | $118.35 | $107.68 | $115.00 |
| 1710 | Roadway sign post (#3 U channel, galvanized steel or 2 ", 14 GA square tubular steel) (710B021) | LF | 177 | $20.30 | $23.67 | $21.54 | $23.00 |
| 1720 | Removal of existing roadway signs (710C000) | LS | 1 | $22,843 | $1,183.55 | $1,076.77 | $1,150.00 |
| 1730 | Roadway sign relocation (711A000) | LS | 1 | $10,152 | $26,630 | $10,768 | $11,500 |
| 1740 | Overhead roadway sign structure number 1 (715A000) | LS | 1 | $82,441 | $97,573 | $87,439 | $93,385 |
| 1750 | Overhead roadway sign structure number 2 (715A001) | LS | 1 | $165,332 | $195,678 | $175,354 | $187,280 |
| 1760 | Overhead roadway sign structure number 3 (715A002) | LS | 1 | $166,156 | $196,653 | $176,228 | $188,213 |
| 1770 | Overhead roadway sign structure number 4 (715A003) | LS | 1 | $82,441 | $97,573 | $87,439 | $93,385 |
| 1780 | Overhead roadway sign structure number 5 (715A004) | LS | 1 | $82,441 | $97,573 | $87,439 | $93,385 |
| 1790 | Vehicular impact attenuator assembly (BI-directional,TL-3) (720A026) | EACH | 2 | $41,030 | $47,561 | $43,808 | $45,920 |
| 1800 | Portable concrete safety barriers, type 6 (726A000) | LF | 34,623 | $60.71 | $75.45 | $64.53 | $73.31 |
| 1810 | Portable concrete safety barriers, type 6-A (726A001) | LF | 90 | $47.62 | $59.18 | $50.61 | $57.50 |
| 1820 | Portable impact attenuator assembly (unidirectional,TL-3) (726D025) | EACH | 9 | $11,905 | $14,794 | $12,652 | $14,375 |
| 1830 | Truck mounted impact attenuator unit (728A000) | EACH | 2 | $75,000 | $12,701 | $26,919 | $41,475 |
| 1840 | Fiber optic trunk cable, 144F (729A006) | LF | 3,925 | $4.69 | $5.55 | $4.96 | $5.30 |
| 1850 | Fiber optic drop cable, 12F (729A101) | LF | 1,240 | $2.91 | $3.45 | $3.08 | $3.29 |
| 1860 | Fiber distribution unit, secondary (729B010) | EACH | 1 | $795.38 | $941.37 | $841.45 | $898.68 |
| 1870 | Fan-out kit (729B020) | EACH | 3 | $137.61 | $162.86 | $145.58 | $155.48 |
| 1880 | FO patch cable, duplex, SC-SC, 2 meter (729B201) | EACH | 6 | $40.48 | $47.91 | $42.82 | $45.74 |
| 1890 | FO patch cable, duplex, SC-LC, 2 meter (729B211) | EACH | 6 | $40.48 | $47.91 | $42.82 | $45.74 |
| 1900 | Network device, type C (fmes) (729C020) | EACH | 1 | $3,780.83 | $4,474.79 | $3,999.84 | $4,271.84 |
| 1910 | Vehicle detection system, radar (type B) (729E111) | EACH | 1 | $20,428 | $24,178 | $21,612 | $23,081 |
| 1920 | Conduit, underground, non-metallic, 2 X 2 inch (729I108) | LF | 2,155 | $23.78 | $28.14 | $25.15 | $26.86 |
| 1930 | Conductor, 6 AWG (729I701) | LF | 14,245 | $3.38 | $4.00 | $3.57 | $3.82 |
| 1940 | Locate tone wire (729I800) | LF | 3,605 | $0.97 | $1.14 | $1.02 | $1.09 |
| 1950 | ITS cabinet, pole mount, type 336S (729J024) | EACH | 1 | $7,775.53 | $9,202.70 | $8,225.93 | $8,785.38 |
| 1960 | Electrical power service ( existing to BE modified) (729K053) | EACH | 1 | $2,336.25 | $2,765.06 | $2,471.58 | $2,639.68 |
| 1970 | Transformer ( 1 kva ) (729K104) | EACH | 1 | $2,759.33 | $3,265.79 | $2,919.16 | $3,117.70 |
| 1980 | Pole, steel (50 FT agl) (729L150) | EACH | 1 | $20,221 | $23,933 | $21,393 | $22,847 |
| 1990 | Miscellaneous infrastructure, fusion splicing (729N000) | EACH | 312 | $68.00 | $80.48 | $71.94 | $76.83 |
| 2000 | Miscellaneous infrastructure, splice closure, underground, 12 fiber (729N111) | EACH | 3 | $1,066.82 | $1,262.63 | $1,128.61 | $1,205.37 |
| 2010 | Miscellaneous infrastructure, splice closure, underground, 144 fiber (729N118) | EACH | 2 | $1,586.40 | $1,877.58 | $1,678.30 | $1,792.44 |
| 2020 | Miscellaneous infrastructure, commbox, type F1 (729N301) | EACH | 5 | $1,835.60 | $2,172.52 | $1,941.93 | $2,074.00 |
| 2030 | Miscellaneous infrastructure, commbox, type F2 (729N302) | EACH | 4 | $2,821.15 | $3,338.96 | $2,984.57 | $3,187.55 |
| 2040 | Miscellaneous infrastructure, commbox, type E1 (729N311) | EACH | 10 | $959.47 | $1,135.58 | $1,015.05 | $1,084.08 |
| 2050 | Miscellaneous infrastructure, fiber marker post (729N500) | EACH | 10 | $74.65 | $88.35 | $78.97 | $84.34 |
| 2060 | Relocation of ITS infrastructure ( site 1) (734W000) | LS | 1 | $6,735.63 | $7,971.93 | $7,125.80 | $7,610.42 |
| 2070 | Relocation of ITS infrastructure ( site 2) (734W001) | LS | 1 | $24,924 | $29,498 | $26,367 | $28,161 |
| 2080 | Relocation of ITS infrastructure ( site 3) (734W002) | LS | 1 | $20,424 | $24,173 | $21,607 | $23,077 |
| 2090 | Removal of fiber optic cable ( and conductors (I-65) (734X000) | LS | 1 | $18,967 | $22,448 | $20,066 | $21,430 |
| 2100 | Construction signs (740B000) | SF | 2,778 | $6.09 | $7.10 | $6.46 | $6.90 |
| 2110 | Special construction signs (740C000) | SF | 132 | $6.60 | $7.69 | $7.00 | $7.48 |
| 2120 | Channelizing drums (740D000) | EACH | 1,000 | $28.43 | $33.14 | $30.15 | $32.20 |
| 2130 | Cones (36 inches high) (740E000) | EACH | 100 | $21.32 | $24.85 | $23.66 | $24.15 |
| 2140 | Barricades, type III (740F002) | EACH | 10 | $228.43 | $266.30 | $242.27 | $258.75 |
| 2150 | Portable sequential arrow and chevron sign unit (741C010) | EACH | 4 | $3,375.64 | $3,935.29 | $3,580.26 | $3,823.75 |
| 2160 | Portable changeable message sign, type 2 (742A001) | EACH | 6 | $10,584 | $12,338 | $11,225 | $11,989 |
| 2170 | Roadway luminaire assembly with one, LED, 250 watt equivalent luminaire (750B601) | EACH | 55 | $5,960.90 | $7,055.00 | $5,488.02 | $6,169.75 |
| 2180 | Pole foundation,roadway (750C010) | EACH | 55 | $2,945.39 | $3,486.00 | $2,864.20 | $3,220.00 |
| 2190 | Electrical junction box,type 1 (750D200) | EACH | 15 | $1,936.56 | $2,292.01 | $869.49 | $977.50 |
| 2200 | Combined duct and cable,2 #6 AWG/ 1 #6 AWG GND (750G010) | LF | 4,300 | $8.53 | $10.10 | $12.28 | $13.80 |
| 2210 | Combined duct and cable, 4 #6 AWG/ 1 #6 AWG GND (750G012) | LF | 5,815 | $11.16 | $13.21 | $12.28 | $13.80 |
| 2220 | Service pole (750H005) | EACH | 3 | $3,677.01 | $4,351.91 | $2,864.20 | $3,220.00 |
| 2230 | Lighting control center (750I015) | EACH | 3 | $20,974 | $24,824 | $34,575 | $38,870 |
| 2240 | 6" electrical conduit, 1 line, type 5 installation (756A028) | LF | 2,135 | $59.54 | $70.47 | $62.99 | $86.25 |
| 2250 | Trainee hours at 80 cents per hour (999 000) | HR | 5,600 | $0.80 | $0.80 | $0.80 | $0.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of May 30, 2025. Compiled by Mirage Metrics.