ALDOT contract 20260626035 bid tabulation
ROADWAY IMPROVEMENTS (ADDITIONAL LANES, MICRO-MILLING, CURB AND GUTTER INSTALLATION, RESURFACING, AND TRAFFIC STRIPE) ON SR-59 SOUTH FROM THE JUNCTION OF CYPRESS BEND DRIVE TO THE JUNCTION OF CR-6 (OAK ROAD WEST) IN GULF SHORES. Let by Alabama DOT on June 26, 2026, Baldwin, 0902. 5 bids received; low bid $1,677,018 by Wiregrass Construction Company, Inc..
- Owner
- Alabama DOT
- Letting
- 26 JUN 2026
- Pay items
- 102
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Wiregrass Construction Company, Inc. | $1,677,018 | Low |
| 2 | McElhenney Construction Co., LLC | $1,951,292 | +16% |
| 3 | PL Russell LLC | $1,951,373 | +16% |
| 4 | Apac-Alabama, Inc. | $2,140,107 | +28% |
| 5 | Rob Middleton Construction, LLC | $2,681,377 | +60% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Wiregrass Construction Company, Inc. | 2. McElhenney Construction Co., LLC | 3. PL Russell LLC | 4. Apac-Alabama, Inc. | 5. Rob Middleton Construction, LLC |
|---|---|---|---|---|---|---|---|---|
| 0010 | Selective clearing (201B001) | ACRE | 1 | $11,668 | $8,098.57 | $2,813.85 | $9,925.80 | $13,059 |
| 0020 | Removing concrete slope paving (206C002) | SY | 65 | $12.90 | $30.91 | $42.21 | $35.31 | $32.97 |
| 0030 | Removing concrete driveway (206C010) | SY | 200 | $15.46 | $15.45 | $51.76 | $43.94 | $22.60 |
| 0040 | Removing pipe (206D000) | LF | 469 | $15.46 | $20.61 | $31.05 | $48.60 | $24.49 |
| 0050 | Removing curb (206D002) | LF | 517 | $9.67 | $13.91 | $19.41 | $17.00 | $20.28 |
| 0060 | Removing gutter (206D005) | LF | 458 | $9.66 | $13.91 | $19.41 | $19.19 | $20.44 |
| 0070 | Removing headwalls (206E000) | EACH | 19 | $128.81 | $556.30 | $316.62 | $285.00 | $481.25 |
| 0080 | Removing trees (206E006) | EACH | 3 | $644.31 | $1,030.19 | $586.70 | $1,654.30 | $634.85 |
| 0090 | Mailbox reset, single (209A000) | EACH | 3 | $150.70 | $248.02 | $314.45 | $461.87 | $823.77 |
| 0100 | Mailbox reset, multiple (209A002) | EACH | 2 | $680.30 | $744.06 | $566.61 | $952.43 | $1,208.21 |
| 0110 | Unclassified excavation (210A000) | CY | 1,684 | $35.56 | $31.15 | $32.31 | $35.98 | $32.98 |
| 0120 | Borrow excavation (loose truckbed measurement)(A-2-4(0) or A-4(0) ) (210D022) | CY | 500 | $33.46 | $32.58 | $40.53 | $26.17 | $40.33 |
| 0130 | Structure excavation (214A000) | CY | 44 | $25.21 | $24.22 | $28.95 | $34.34 | $18.80 |
| 0140 | Foundation backfill, local (214B000) | CY | 66 | $45.44 | $36.26 | $34.68 | $42.93 | $32.23 |
| 0150 | Roadbed processing (230A000) | RBST | 28 | $963.84 | $869.13 | $0.01 | $681.34 | $324.83 |
| 0160 | Crushed aggregate base course, type B, plant mixed, 6" compacted thickness (301A012) | SY | 5,431 | $33.94 | $35.04 | $36.13 | $27.58 | $54.71 |
| 0170 | Bituminous treatment A (401A000) | SY | 3,951 | $1.12 | $2.08 | $2.05 | $1.46 | $2.24 |
| 0180 | Tack coat (405A000) | GAL | 638 | $3.96 | $8.33 | $8.21 | $4.91 | $8.96 |
| 0190 | Micro-milling existing pavement (approximately 1.10" thru 2.00" thick) (408B001) | SY | 10,795 | $1.06 | $3.44 | $3.39 | $8.45 | $3.70 |
| 0200 | Material remixing device (410H000) | EACH | 1 | $41,055 | $19,643 | $19,361 | $9,076.69 | $21,109 |
| 0210 | Superpave bituminous concrete wearing surface layer, 1/2" maximum aggregate size mix, esal range C/D (424A360) | TON | 1,487 | $134.15 | $164.29 | $161.93 | $186.71 | $176.55 |
| 0220 | Superpave bituminous concrete wearing surface layer, widening, 1/2" maximum aggregate size mix, esal range C/D (424A369) | TON | 81 | $237.80 | $165.53 | $322.69 | $300.68 | $351.82 |
| 0230 | Superpave bituminous concrete upper binder layer, 3/4" maximum aggregate size mix, esal range C/D (424B650) | TON | 426 | $140.36 | $165.53 | $179.53 | $183.37 | $181.67 |
| 0240 | Superpave bituminous concrete upper binder layer, leveling, 3/4" maximum aggregate size mix, esal range C/D (424B658) | TON | 318 | $125.23 | $165.53 | $166.62 | $205.03 | $230.28 |
| 0250 | Superpave bituminous concrete upper binder layer, widening, 3/4" maximum aggregate size mix, esal range C/D (424B661) | TON | 99 | $202.16 | $165.52 | $201.83 | $254.45 | $351.82 |
| 0260 | Superpave bituminous concrete lower binder layer, 3/4" maximum aggregate size mix, esal range C/D (424B680) | TON | 418 | $141.24 | $165.53 | $179.53 | $182.12 | $230.28 |
| 0270 | Scoring bituminous pavement surface (428A001) | MI | 1 | $1,586.46 | $357.15 | $352.02 | $367.97 | $4,861.53 |
| 0280 | Aggregate surfacing (crushed aggregate base, type B) (430B040) | TON | 200 | $86.31 | $84.05 | $107.04 | $92.38 | $92.89 |
| 0290 | 22" span, 14" rise roadway pipe (class 3 R.C.) (530B001) | LF | 274 | $86.10 | $126.79 | $80.89 | $125.50 | $87.76 |
| 0300 | 18" side drain pipe (class 3 R.C.) (535A080) | LF | 246 | $78.25 | $114.86 | $66.18 | $110.62 | $65.70 |
| 0310 | 22" span, 14" rise side drain pipe (class 3 R.C.) (535B088) | LF | 478 | $82.12 | $128.55 | $80.89 | $124.74 | $86.77 |
| 0320 | Mobilization (600A000) | LS | 1 | $157,218 | $176,515 | $204,135 | $195,519 | $493,575 |
| 0330 | 6" underdrain pipe (606A000) | LF | 1,000 | $40.30 | $19.97 | $37.05 | $37.06 | $62.56 |
| 0340 | Filter blanket, geotextile (610D003) | SY | 900 | $7.83 | $5.21 | $5.24 | $4.65 | $8.17 |
| 0350 | Slope paving (614A000) | CY | 6 | $893.00 | $1,063.09 | $1,211.89 | $1,150.06 | $1,215.38 |
| 0360 | 18" side drain pipe end treatment, class 1 (619A101) | EACH | 4 | $1,092.73 | $1,238.95 | $1,481.96 | $1,340.32 | $3,198.38 |
| 0370 | 18" side drain pipe end treatment, class 1 (double line) (619A271) | EACH | 2 | $1,458.04 | $1,653.16 | $2,221.05 | $1,788.40 | $4,477.73 |
| 0380 | 22" span, 14" rise roadway pipe end treatment, class 1 (619B016) | EACH | 1 | $1,115.61 | $1,264.90 | $1,694.93 | $1,368.38 | $2,558.70 |
| 0390 | 22" span, 14" rise side drain pipe end treatment, class 1 (619B116) | EACH | 4 | $1,224.43 | $1,388.28 | $1,316.10 | $1,501.86 | $3,838.05 |
| 0400 | 22" span, 14" rise side drain pipe end treatment, class 1 (double line) (619B396) | EACH | 10 | $1,458.04 | $1,653.15 | $2,279.73 | $1,788.40 | $6,396.75 |
| 0410 | Junction boxes, type 1 or 1P (621A011) | EACH | 1 | $4,306.41 | $5,625.67 | $3,675.93 | $4,201.65 | $3,160.34 |
| 0420 | Concrete curb, type N (623B000) | LF | 332 | $42.27 | $47.93 | $51.72 | $51.85 | $51.17 |
| 0430 | Concrete curb, type N special (623B001) | LF | 86 | $72.00 | $85.59 | $97.63 | $92.59 | $153.52 |
| 0440 | Concrete curb, type A (623B002) | LF | 61 | $33.98 | $38.52 | $59.04 | $41.68 | $95.95 |
| 0450 | Combination curb & gutter, type M-4 (623C015) | LF | 422 | $45.19 | $51.24 | $45.25 | $55.43 | $51.17 |
| 0460 | Topsoil (650A000) | CY | 894 | $39.38 | $42.00 | $43.94 | $40.67 | $38.28 |
| 0470 | Solid sodding (bermuda) (654A001) | SY | 8,030 | $5.36 | $6.07 | $5.98 | $7.36 | $7.68 |
| 0480 | Temporary seeding (665A000) | ACRE | 4 | $498.75 | $565.49 | $557.37 | $1,226.58 | $1,574.61 |
| 0490 | Temporary mulching (665B001) | TON | 12 | $840.00 | $952.41 | $938.73 | $613.29 | $394.65 |
| 0500 | Polyethylene (665E000) | SY | 500 | $2.63 | $2.86 | $2.93 | $6.13 | $2.42 |
| 0510 | Hay bales (665F000) | EACH | 100 | $10.50 | $11.91 | $11.73 | $53.16 | $20.80 |
| 0520 | Sand bags (665G000) | EACH | 50 | $10.48 | $11.88 | $11.71 | $24.56 | $8.14 |
| 0530 | Silt fence (665J002) | LF | 1,503 | $5.51 | $6.25 | $6.16 | $6.75 | $4.25 |
| 0540 | Drainage sump excavation (665K000) | CY | 500 | $25.77 | $19.47 | $12.00 | $38.81 | $18.84 |
| 0550 | Temporary coarse aggregate,aldot number 1 (665N000) | TON | 200 | $88.00 | $85.83 | $74.13 | $89.96 | $88.92 |
| 0560 | Silt fence removal (665O001) | LF | 1,503 | $1.31 | $1.49 | $1.47 | $1.84 | $2.87 |
| 0570 | Inlet protection, stage 3 or 4 (665P005) | EACH | 2 | $577.50 | $654.78 | $645.38 | $404.77 | $407.60 |
| 0580 | Wattle, 20 inch (665Q020) | LF | 1,208 | $11.29 | $12.80 | $12.61 | $14.72 | $13.10 |
| 0590 | Pest control treatment (666A001) | ACRE | 2 | $210.00 | $238.10 | $234.68 | $613.29 | $1,279.35 |
| 0600 | Flocculant application, ditch check (672C100) | EACH | 8 | $52.50 | $59.53 | $58.67 | $850.04 | $959.51 |
| 0610 | Geometric controls (680A001) | LS | 1 | $17,457 | $26,881 | $35,556 | $10,590 | $17,851 |
| 0620 | Construction fuel (maximum bid limited to $ 79,000.00) (698A000) | LS | 1 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 0630 | Solid white, class 2, type A traffic stripe (5" wide) (701A227) | MI | 1 | $5,092.50 | $4,047.73 | $3,989.59 | $4,378.89 | $4,797.56 |
| 0640 | Solid yellow, class 2, type A traffic stripe (5" wide) (701A230) | MI | 1 | $5,092.50 | $4,047.73 | $3,989.59 | $4,378.89 | $4,797.56 |
| 0650 | Broken white, class 2, type A traffic stripe (5" wide) (701A239) | MI | 1 | $2,189.25 | $1,190.51 | $1,173.41 | $1,287.91 | $2,526.72 |
| 0660 | Dotted, class 2, type A traffic stripe (5" wide) (701B207) | LF | 1,810 | $1.05 | $0.30 | $0.29 | $0.32 | $1.60 |
| 0670 | Broken temporary traffic stripe (701C000) | MI | 1 | $420.00 | $1,130.98 | $1,114.74 | $1,223.52 | $1,215.38 |
| 0680 | Solid temporary traffic stripe (701C001) | MI | 2 | $735.00 | $1,904.81 | $1,877.46 | $2,060.66 | $1,247.37 |
| 0690 | Broken traffic stripe removed (plastic) (701D015) | MI | 2 | $840.00 | $2,142.92 | $2,112.14 | $2,318.24 | $3,198.38 |
| 0700 | Dotted temporary traffic stripe (701F000) | LF | 1,810 | $0.01 | $0.18 | $0.18 | $0.19 | $0.23 |
| 0710 | Traffic control markings, class 2, type A (703A002) | SF | 724 | $5.25 | $5.06 | $4.99 | $5.47 | $6.40 |
| 0720 | Traffic control legends, class 2, type A (703B002) | SF | 202 | $5.25 | $7.14 | $7.04 | $7.73 | $7.68 |
| 0730 | Removal of existing traffic control markings or legends (plastic) (703C001) | SF | 85 | $5.25 | $2.68 | $2.64 | $2.90 | $3.84 |
| 0740 | Temporary traffic control markings (703D001) | SF | 724 | $2.10 | $1.79 | $1.76 | $1.93 | $1.92 |
| 0750 | Pavement markers, class C, type 2- C (705A022) | EACH | 30 | $5.25 | $8.33 | $8.21 | $9.02 | $12.79 |
| 0760 | Pavement markers, class A-H, type 2-C (705A030) | EACH | 109 | $5.25 | $8.33 | $8.21 | $9.02 | $12.79 |
| 0770 | Pavement markers, class A-H, type 1-B (705A032) | EACH | 29 | $5.25 | $8.33 | $8.21 | $9.02 | $12.79 |
| 0780 | Pavement markers, class A-H, type 2-D (705A037) | EACH | 3 | $5.25 | $8.33 | $8.21 | $9.02 | $12.79 |
| 0790 | Pavement markers, class A-H, type 2-E (705A038) | EACH | 15 | $5.25 | $8.33 | $8.21 | $9.02 | $12.79 |
| 0800 | Class 4, aluminum flat sign panels (type IV background) (710A171) | SF | 16 | $25.20 | $28.57 | $26.99 | $29.62 | $29.43 |
| 0810 | Roadway sign post (#3 U channel, galvanized steel or 2 ", 14 GA square tubular steel) (710B021) | LF | 15 | $19.43 | $22.02 | $25.81 | $28.33 | $28.15 |
| 0820 | Roadway sign relocation (711A000) | LS | 1 | $525.00 | $595.25 | $176.01 | $193.19 | $191.90 |
| 0830 | Portable concrete safety barriers, type 6 (726A000) | LF | 1,572 | $18.37 | $77.37 | $66.57 | $65.69 | $64.29 |
| 0840 | Portable concrete safety barriers, type 6-A (726A001) | LF | 80 | $88.73 | $105.17 | $90.88 | $43.12 | $112.51 |
| 0850 | Portable impact attenuator assembly (unidirectional,TL-3) (726D025) | EACH | 8 | $11,129 | $9,921.95 | $4,532.33 | $12,143 | $9,595.13 |
| 0860 | Removal of existing traffic control unit (partial) ( SR-59 at cypress bend drive) (730A012) | LS | 1 | $21,649 | $24,524 | $20,591 | $15,455 | $14,884 |
| 0870 | Furnishing and installing traffic control unit ( SR-59 at cypress bend drive) (730C000) | LS | 1 | $24,897 | $28,203 | $34,795 | $41,213 | $12,140 |
| 0880 | Furnishing and installing traffic control unit (temporary)( SR-59 at cypress bend drive) (730C030) | LS | 1 | $22,732 | $25,751 | $29,460 | $33,486 | $74,167 |
| 0890 | Metal traffic signal pole foundation (730E000) | EACH | 2 | $9,201.03 | $10,423 | $14,803 | $11,591 | $36,582 |
| 0900 | Traffic signal junction box type S2 (730K002) | EACH | 2 | $2,273.20 | $2,575.07 | $772.69 | $772.75 | $907.38 |
| 0910 | 2", non-metallic, conduit (730L005) | LF | 187 | $27.06 | $30.66 | $18.93 | $12.88 | $11.32 |
| 0920 | Vehicular signal head, 12 inch, 3 (730P022) | EACH | 12 | $1,407.22 | $1,594.09 | $1,671.52 | $1,931.86 | $1,761.96 |
| 0930 | Controller assembly, type atc, 16 channels (730R046) | EACH | 1 | $30,309 | $34,334 | $46,361 | $43,789 | $54,585 |
| 0940 | Uninterruptable power supply system, managed (730T022) | EACH | 1 | $14,072 | $15,941 | $16,359 | $19,319 | $17,105 |
| 0950 | Construction signs (740B000) | SF | 954 | $5.51 | $6.25 | $9.39 | $10.30 | $10.23 |
| 0960 | Channelizing drums (740D000) | EACH | 130 | $0.01 | $19.64 | $44.59 | $48.94 | $48.62 |
| 0970 | Cones (36 inches high) (740E000) | EACH | 130 | $0.01 | $42.86 | $18.77 | $0.01 | $20.47 |
| 0980 | Barricades, type III (740F002) | EACH | 14 | $84.00 | $95.24 | $252.28 | $276.90 | $275.06 |
| 0990 | Portable sequential arrow and chevron sign unit (741C010) | EACH | 2 | $997.50 | $1,130.98 | $1,584.10 | $1,738.68 | $1,727.13 |
| 1000 | Portable changeable message sign, type 2 (742A001) | EACH | 2 | $1,680.00 | $1,904.81 | $3,696.24 | $4,056.91 | $4,029.96 |
| 1010 | Uniformed police officer (745A000) | HR | 72 | $78.75 | $59.53 | $88.01 | $55.20 | $95.95 |
| 1020 | 6" electrical conduit, 1 line, type 5 installation (756A028) | LF | 100 | $102.84 | $116.49 | $72.43 | $103.03 | $116.98 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of June 26, 2026. Compiled by Mirage Metrics.