PL Russell LLC submitted 15 bids on Alabama DOT contracts in the data, from 30 AUG 2024 to 31 JUL 2026, and was the low bidder on 3 of them (20%). When it was not low, its total sat a median +19% above the low bid.
- Owner
- Alabama DOT
- Low bid volume
- $3,317,111
- Latest bid
- 31 JUL 2026
- Data through
- 28 AUG 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2024 | 4 | 0 | 0% |
| 2025 | 5 | 1 | 20% |
| 2026 | 6 | 2 | 33% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| 0902 | 6 | 2 | 33% |
| 0804 | 3 | 0 | 0% |
| 0702 | 3 | 0 | 0% |
| 0901 | 2 | 0 | 0% |
| 0802 | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Cones (36 inches high) | 740E000 | EACH | 14 | 4 (29%) | $18.38 | $20.47 |
| Temporary seeding | 665A000 | ACRE | 8 | 4 (50%) | $473.79 | $900.00 |
| Silt fence | 665J002 | LF | 14 | 3 (21%) | $5.08 | $5.00 |
| Silt fence removal | 665O001 | LF | 14 | 3 (21%) | $1.71 | $1.45 |
| Temporary mulching | 665B001 | TON | 9 | 3 (33%) | $486.21 | $545.62 |
| Minor structure concrete | 620A000 | CY | 7 | 3 (43%) | $1,617.34 | $2,279.07 |
| Topsoil | 650A000 | CY | 13 | 2 (15%) | $37.12 | $45.00 |
| Unclassified excavation | 210A000 | CY | 13 | 2 (15%) | $29.94 | $32.97 |
| Tack coat | 405A000 | GAL | 12 | 2 (17%) | $6.36 | $4.55 |
| Wattle | 665Q002 | LF | 10 | 2 (20%) | $10.91 | $10.75 |
| Filter blanket, geotextile | 610D003 | SY | 10 | 2 (20%) | $5.37 | $5.47 |
| Temporary coarse aggregate,aldot number 1 | 665N000 | TON | 10 | 2 (20%) | $106.02 | $73.12 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| McElhenney Construction Co., LLC | 12 | 6 of 12 |
| Wiregrass Construction Company, Inc. | 10 | 6 of 10 |
| Rob Middleton Construction, LLC | 6 | 1 of 6 |
| Apac-Alabama, Inc. | 4 | 2 of 4 |
| Pine City Contracting, LLC | 3 | 1 of 3 |
| C. Thornton, Inc. | 2 | 1 of 2 |
| Cornerstone Civil Contractors, LLC | 2 | 0 of 2 |
| Arrington Curb & Excavation, Inc. | 2 | 1 of 2 |
| J. Hunt Enterprises General Contractors, LLC | 2 | 2 of 2 |
| S. A. Graham Company, Inc. | 2 | 2 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 31 JUL 2026 | 20260731008 | 0802 | ROADWAY SAFETY IMPROVEMENTS (GUARDRAIL INSTALLATION AND GUARDRAIL END ANCHORS) ON VARIOUS ROUTES AT VARIOUS LOCATIONS AS INDICATED IN THE PL | 1 of 4 | $217,898 | Low, 12% under the second |
| 31 JUL 2026 | 20260731025 | 0902 | INTERSECTION IMPROVEMENTS (ADDITIONAL TURN LANES AND TRAFFIC SIGNAL UPGRADES) ON SR-42 (US-98) AT CR-87 EAST OF FOLEY | 3 of 6 | $949,026 | +10% |
| 26 JUN 2026 | 20260626035 | 0902 | ROADWAY IMPROVEMENTS (ADDITIONAL LANES, MICRO-MILLING, CURB AND GUTTER INSTALLATION, RESURFACING, AND TRAFFIC STRIPE) ON SR-59 SOUTH FROM TH | 3 of 5 | $1,951,373 | +16% |
| 27 MAR 2026 | 20260327047 | 0702 | MAINTENANCE STRUCTURAL REMOVAL ON SR-52 FROM A POINT WEST OF THE INTERSECTION OF 2ND AVENUE TO A POINT EAST OF THE JUNCTION OF COX STREET | 7 of 9 | $443,682 | +68% |
| 27 FEB 2026 | 20260227007 | 0902 | ROADWAY AND SAFETY IMPROVEMENTS (PEDESTRIAN AND BICYCLE UPGRADES/TRAFFIC SIGNALS AND TRAFFIC STRIPE) ON SR-182 FROM MP 13.750 IN GULF SHORES | 1 of 2 | $623,215 | Low, 17% under the second |
| 27 FEB 2026 | 20260227028 | 0702 | ROADWAY SAFETY IMPROVEMENTS (DRAINAGE IMPROVEMENTS) ON SR-12 (US-84) AT THE JUNCTION OF CR-502 EAST OF ELBA | 4 of 5 | $850,735 | +47% |
| 05 DEC 2025 | 20251205015 | 0702 | ROADWAY/INTERSECTION SAFETY IMPROVEMENTS ON SR-12- (US-84) AT SR-141 SOUTHWEST OF ELBA | 4 of 4 | $1,493,891 | +26% |
| 07 NOV 2025 | 20251107057 | 0804 | INTERSECTION IMPROVEMENTS TO INCLUDE LEFT TURN LANE ADDITION ON SR-57 (US-45) AT CR-1 TO INCLUDE LEFT TURN LANES ON SR-57 (US-45) IN FRUITDA | 6 of 8 | $1,515,000 | +26% |
| 25 JUL 2025 | 20250725027 | 0902 | WIDEN, RESURFACE, TURN LANE ADDITION, AND STRIPE ON SR-16 (US-90) FROM A POINT NEAR MT AID BAPTIST CHURCH TO THE INTERSECTION OF SR-181 | 1 of 5 | $2,475,998 | Low, 1.0% under the second |
| 25 APR 2025 | 20250425045 | 0902 | ROADWAY IMPROVEMENTS AND WIDENING ON SR-225 FROM THE JUNCTION OF OAKRIDGE DRIVE IN SPANISH FORT TO THE JUNCTION OF GENERAL CANBY BOULEVARD | 4 of 5 | $1,580,354 | +22% |
| 28 MAR 2025 | 20250328037 | 0804 | INTERSECTION IMPROVEMENTS AND ACCESS MANAGEMENT ON SR-13 (US-43) AT SR-69 IN JACKSON | 2 of 6 | $1,259,196 | +10% |
| 06 DEC 2024 | 20241206012 | 0804 | ROADWAY IMPROVEMENTS (DRAINAGE STRUCTURE AND ROADWAY REPAIR) ON SR-17 FROM A POINT SOUTH OF THE JUNCTION OF SPARKS ROAD NORTHEAST OF TOXEY | 2 of 2 | $1,795,004 | +49% |
| 08 NOV 2024 | 20241108061 | 0901 | ROADWAY IMPROVEMENTS (LANE ADDITION) ON SR-158 FROM THE EXISTING 4 LANE SECTION TO A POINT EASTERLY FOR 1500 FEET IN SARALAND | 2 of 5 | $1,671,734 | +7.0% |
| 27 SEP 2024 | 20240927042 | 0902 | INTERSECTION IMPROVEMENTS TO INCLUDE ADDING TURN LANES ON SR-59 AT CR-12 IN FOLEY | 3 of 5 | $1,944,028 | +6.0% |
| 30 AUG 2024 | 20240830011 | 0901 | ROADWAY IMPROVEMENTS (LEFT TURN BYPASS LANE ADDITION) ON SR-17 (US-45) AND SR-57 (US-45) AT VARIOUS LOCATIONS IN THE SOUTHWEST REGION (MOBIL | 3 of 5 | $514,063 | +9.0% |
How this record was read
ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
- Every bid counted here matched its published total to within one dollar; ALDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.