S. A. Graham Company, Inc.: ALDOT bid record

S. A. Graham Company, Inc. submitted 10 bids on Alabama DOT contracts in the data, from 25 MAR 2022 to 28 AUG 2026, and was the low bidder on 6 of them (60%). When it was not low, its total sat a median +4.0% above the low bid.

Owner
Alabama DOT
Low bid volume
$32,936,726
Latest bid
28 AUG 2026
Data through
28 AUG 2026
10Bids
6Low bids
60Win rate, percent
+4.0%Median gap to the low bid when not low, 4 bids

By year

YearBidsLow bidsWin rate
20223267%
2024100%
202522100%
20264250%
S. A. Graham Company, Inc., ALDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
07025240%
07053267%
070411100%
060411100%
S. A. Graham Company, Inc., ALDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Removing pipe206D000LF76 (86%)$10.00$31.83
Crushed aggregate base course, type B, road mixed, 6" compacted thickness301A025SY66 (100%)$20.12$30.00
Silt fence665J002LF105 (50%)$3.66$5.00
Silt fence removal665O001LF95 (56%)$0.80$1.45
Unclassified excavation210A000CY95 (56%)$12.75$32.97
Topsoil650A000CY75 (71%)$23.50$45.00
Structure excavation214A000CY84 (50%)$10.00$25.00
Roadbed processing230A000RBST64 (67%)$900.00$900.38
Mulching656A010ACRE93 (33%)$842.00$1,307.18
Wattle665Q002LF83 (38%)$6.62$10.75
Foundation backfill, commercial214B001CY73 (43%)$85.00$86.75
Inlet protection, stage 3 or 4665P005EACH73 (43%)$250.00$484.52
S. A. Graham Company, Inc., ALDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Wiregrass Construction Company, Inc.71 of 7
Grady Ralls & Sons, Inc.43 of 4
W. S. Newell & Sons, Inc.41 of 4
Apac-Alabama, Inc.20 of 2
PL Russell LLC20 of 2
Midsouth Paving, Inc.10 of 1
Chilton Contractors, Inc.10 of 1
Gibson Construction Services, LLC10 of 1
Lewis Incorporated..10 of 1
J. Hunt Enterprises General Contractors, LLC10 of 1
S. A. Graham Company, Inc., ALDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
28 AUG 2026202608280180705ROADWAY SAFETY IMPROVEMENTS (SLOPE FLATTENING TO INCLUDE CLEARING AND GRUBBING) ON CR-1101 AT THE CONECUH RIVER (SITE 1) AND OLUSTEE CREEK (2 of 6$599,107+3.0%
24 APR 2026202604240070604REST AREA NORTHBOUND I-65 NEAR GREENVILLE (SITE CONSTRUCTION) ON I-65 NEAR GREENVILLE1 of 5$11,739,966Low, 0.0% under the second
27 MAR 2026202603270470702MAINTENANCE STRUCTURAL REMOVAL ON SR-52 FROM A POINT WEST OF THE INTERSECTION OF 2ND AVENUE TO A POINT EAST OF THE JUNCTION OF COX STREET2 of 9$334,027+26%
27 FEB 2026202602270280702ROADWAY SAFETY IMPROVEMENTS (DRAINAGE IMPROVEMENTS) ON SR-12 (US-84) AT THE JUNCTION OF CR-502 EAST OF ELBA1 of 5$579,353Low, 15% under the second
27 JUN 2025202506270190704INTERSECTION IMPROVEMENTS/RELOCATION ON SR-6 (US-82) AT SR-1 (US-431) IN EUFAULA1 of 3$3,383,604Low, 0.0% under the second
28 FEB 2025202502280430705ROADWAY SAFETY IMPROVEMENTS AND INTERSECTION IMPROVEMENTS ON SR-9 (US-331) AT CR-39 (MT. IDA ROAD) (SITE 1) AND ON SR-9 (US-331) AT GLENWOOD1 of 2$914,125Low, 7.0% under the second
26 JAN 2024202401260520702ADDITIONAL LANES AND ROUTE RELOCATION ON SR-52 FROM EAST OF COX STREET IN SLOCOMB TO THE JUNCTION OF SCOTT ROAD IN MALVERN3 of 4$23,970,015+4.0%
30 SEP 2022202209300190705ROUNDABOUT (GRADING, DRAINAGE, PAVEMENT, LIGHTING, & STRIPE) ON SR-167 AT SR-87 (MP 52.194 TO MP 54.207) SOUTH OF TROY1 of 2$3,435,415Low, 1.0% under the second
29 JUL 2022202207290280702ADDITIONAL LANES (GRADING, DRAINAGE, PAVEMENT, SIGNALS) ON SR-167 FROM THE JUNCTION OF SR-12 (US-84) TO A POINT 0.280 MILE NORTH OF THE INTE1 of 2$12,884,263Low, 2.0% under the second
25 MAR 2022202203250070702INTERSECTION SAFETY IMPROVEMENTS (INTERSECTION CONVERSION) ON SR-134 AT CR-460 AND CR-461 EAST OF OPP2 of 4$867,199+1.0%
S. A. Graham Company, Inc.: latest ALDOT bids in the data

How this record was read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Every bid counted here matched its published total to within one dollar; ALDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy